Reason for Delay in Completion of Sheltered Linkway at Woodleigh Close

Parliament of Singapore · 24 March 2016

Official Report, 24 March 2016, Vol 94, Issue 10 · Open in the reader (summaries, search, filters)

6

Mr Sitoh Yih Pin asked the Minister for Transport (a) what is the reason for the delay in completion of the sheltered linkway at Woodleigh Close under the Walk2Ride programme; and (b) what is LTA's estimated date of completion of these works.

Mr Khaw Boon Wan: It was originally estimated that the sheltered linkway at Woodleigh Close would be completed by May 2016. Since then, Land Transport Authority (LTA) has found that it needs more time to ensure that the linkway’s construction does not affect existing utilities infrastructure and adjacent trees. The expected completion date is now August 2016.