Expediting Completion of Downtown Line 2 MRT Stations to Keep within Timeline
Parliament of Singapore · 17 August 2015
Official Report, 17 August 2015, Vol 93, Issue 22 · Open in the reader (summaries, search, filters)
Mr Christopher de Souza asked the Minister for Transport how was LTA able to expedite the completion of the Downtown Line 2 MRT stations ahead of schedule in December 2015 and make up for lost time such that the insolvency of the contractor Alpine Bau GmbH did not hamper the completion timeline.
Mr Lui Tuck Yew: The insolvency of Alpine Bau affected the completion timeline of three stations, Tan Kah Kee, Sixth Avenue and King Albert Park, and their associated tunnels. LTA and their contractors have worked hard to make up the lost time by mobilising resources from other completed DTL2 stations and extending work hours where possible. They also restructured the work processes and coordinated concurrent activities for the project where feasible.
For example, to expedite the testing and commissioning of the systems, LTA and their contractors carried out the works simultaneously on different parts of the line. To overcome the lack of cabling connection across the affected section to the Operation Control Centre (OCC) at Gali Batu Depot, a Local Control Centre was set up at Little India station to allow early commencement of testing for this stretch of the line.
Source: Singapore Parliament Official Report (Hansard) for 17 August 2015. Republished on SGParliament.