Dewan Rakyat · 7 October 2026

15th Parliament, session 5, meeting 3 · not final · 535 turns · 47,410 words · official PDF ↗ · Digital Hansard ↗

495 of 535 turns machine-translated from Malay (Claude Haiku 5.5), marked EN. The original is the record.

(Opening)

[Honourable Dato' Sri Doris Sophia anak Brodi (Sri Aman) in the Chair]

Oral QuestionsQuestions

Good morning. Peace be upon you. We begin with Puan Rodiyah binti Sapiee. The Honourable Member, please.

Puan Rodiyah binti SapieePBB · GPSBatang SadongEN

Question from Batang Sadong to Santubong. Question number 1.

Rodiyah binti SapieePBB · GPSBatang Sadong · questionEN

1. Puan Rodiyah binti Sapiee [Batang Sadong] asks the Minister of Women, Family and Community Development to state the latest status of the proposed Parents' Care Bill (RUU Penjagaan Ibu Bapa), and what form and mechanism of comprehensive social protection is expected to be announced to protect the welfare of senior citizens, in view of the rising demographic trend of the country towards the status of an aging nation.

Dato’ Sri Hajah Nancy binti ShukriPBB · GPSMinister of Women, Family and Society Development · SantubongEN

Thank you, the Honourable Member for Batang Sadong. Thank you, Mr Speaker. Bismillahirrahmanirrahim. Assalamualaikum warahmatullahi taala wabarakatuh. Madam Speaker, I seek to answer the question by the Honourable Member for Batang Sadong today together with two other questions, as they touch on the same matter, namely question number 27 by the Honourable Member for Jeli dated 2 October and question number 3 by the Honourable Member for Bukit Bendera dated 3 November.

Silakan.

Madam Speaker, thank you. The Ministry of Women, Family and Community Development (KPWKM) is now in the final phase of finalising the drafting of the bill

relating to the protection of senior citizens, to strengthen their welfare and protect this group from neglect, abuse and also exploitation. KPWKM is making the best use of the available space and opportunities to obtain input from various parties through a whole-of-government and whole-of-society approach, with permission. This extensive consultation process involves various ministries and agencies at the level of the Federal Government, state governments as well as non-governmental organisations or NGOs. In addition, the voices of the people at the grassroots level were also consulted through the conduct of a public survey to ensure that the bill reflects the actual needs of society. This engagement process has taken somewhat longer because the government is committed to examining the various matters and new proposals put forward by stakeholders. At the same time, there were also some stakeholders involved in the engagement sessions who were consulted more than once. This thorough and in-depth scrutiny is very important to ensure that the bill produced will be truly comprehensive, suited to current needs and, most importantly, can be implemented in an orderly manner. I wish to emphasise that the protection of the welfare of senior citizens has never stopped while waiting for this bill to be finalised. Their rights and safety remain protected under existing provisions of the law and mechanisms, such as, for example, the Penal Code and the Domestic Violence Act 1994 for cases of abuse and violence, the Persons with Disabilities Act 2008 for elderly persons with disabilities, as well as intervention channels through the Talian Kasih 15999 provided by KPWKM. Meanwhile, when discussing social protection, the concept is broader and wider than merely cash assistance. In international standards, the social protection ecosystem is formed to cover three main areas, namely social assistance, social insurance, and labour market intervention. In the Malaysian context, this ecosystem is integrated in a coordinated manner under the Malaysia Social Protection Council (MySPC), chaired by the Honourable Prime Minister and secretariat-managed by ICU JPM. Madam Speaker, allow me to continue answering on behalf of these three persons. So, this is also important for all of us who will reach the age of 60 later.

Baiklah.

So, thank you, Madam Speaker. Smile, Madam Speaker. In the Malaysian context, this ecosystem is integrated in a coordinated manner under the Social Protection Council just now, under ICU. It is chaired by the Honourable Prime Minister himself. Since these three areas cover various aspects of the lives of senior citizens, they involve the expertise and jurisdiction of various agencies, including the Ministry of Finance, the Ministry of Human Resources, the Ministry of Health, the Ministry of Housing and Local Government, PLANMalaysia and the Ministry of Transport. Specifically in KPWKM's field, the protection network is implemented, among others, through the disbursement of senior citizen assistance, namely targeted financial assistance of RM600 a month to those who are eligible. We also have the operation of 234 Senior Citizens' Activity Centres (Pusat Aktiviti Warga Emas), namely PAWE, to date this year, to encourage active ageing among more than 50,000 members. The Home Help Services Programme (Program Khidmat Bantu di Rumah), namely KBDR, currently helps more than 9,000 senior citizens through the services of more than 2,000 trained volunteers. We also operate senior citizen institutions under JKM as the last safety net, and are developing the National Senior Citizens Action Plan (PTWEN) 2026–2030, the strategic framework and the Malaysia Care Economy Action Plan 2026–2030, as well as caregiver competency training under RMK13. Leading the country's long-term preparation, the National Ageing Blueprint (Rangka Tindakan Penuaan Kebangsaan), or, with permission, the National Ageing Blueprint, namely NAB, is being comprehensively developed by the Ministry of Economy. NAB will act as the main strategic guiding document that sets out the comprehensive direction of the country to prepare Malaysia for facing the phase of an aged nation. KPWKM remains determined and committed to playing its central role, particularly in strengthening long-term care services or, with permission, Long-Term Care (LTC), social assistance and community empowerment, to support the government in achieving the best results for the welfare of senior citizens in Malaysia. That is all, thank you.

Thank you, Honourable Minister. Puan Rodiyah binti Sapiee, Batang Sadong, please proceed.

Puan Rodiyah binti SapieePBB · GPSBatang SadongEN

Thank you, YB Minister, for the answer given. Batang Sadong welcomes the Parents' Care Bill (RUU Penjagaan Ibu

Puan Rodiyah binti SapieePBB · GPSBatang SadongEN

Bapa) being tabled in Parliament in the near future, and I also heard many initiatives relating to senior citizens mentioned just now. So, Batang Sadong wishes to touch on one matter that is very close to family life, namely the burden of caring for parents who are increasingly ageing and require daily care. For low- and middle-income families, the cost of such care can be a heavy burden, especially for families or children who are the main caregivers. So the question is, what form of support is currently being, if any, and will be provided by the government to family caregivers, including assistance whether financial, home care support, as well as health or psychological, psychosocial support, so that it does not become too heavy a burden on families, especially as Malaysia moves towards becoming an aging nation? So, that is all, thank you.

Yes, the Honourable Minister, please proceed.

Thank you, the Honourable Member for Batang Sadong. Thank you, Mr Speaker. Thank you to, what's his name, the others who also asked. In relation to this matter, I wish to emphasise that KPWKM firmly holds to the position that the best care for senior citizens is in the company of their beloved family. The ministry always places emphasis on the principle of family-based care, with permission, and applies the concept of ageing in place. The government's message is clear. The responsibility of caring for senior citizens is not a burden to be transferred carelessly. Rather, the family institution is the main pillar of care, while admission to senior citizen care institutions is the last resort after all support efforts at the family and community level have been made. The government does not only provide assistance and support through KPWKM and JKM alone...

Tuan Zahari bin KechikBERSATU · PNJeli

[Bangun]

...but these government services are also delivered through various ministries and agencies so that senior citizens can continue to age in dignity, safety and well-being in their own homes together with their family members.

In addition to the welfare assistance and services provided by KPWKM in my first answer just now, the government, through various agencies, continues to provide the following support. First, for housing and mobility incentives under the National Housing Policy developed by the Ministry of Housing and Local Government (KPKT). The government provides grants for the renovation of senior-friendly and disabled-friendly homes, while public transport fare discounts of between 30 and 50 per cent are given to senior citizens to ease the burden of daily fares. Second, for the community health sector, the Ministry of Health provides domiciliary care services, home health care, palliative care, as well as a pilot project or Integrated Care for Older People, or ICOPE. To preserve mental and emotional health, intergenerational family relationships and family psychosocial intervention, KPWKM, through LPPKN, has developed the Grandparenting Programme. Not only parents, now it includes grandparenting to strengthen family relationships across generations, supported by the Loneliness Therapy Programme. In addition, KPWKM, through JKM, is conducting the RYTHM Programme or Ritma Kehidupan Harmoni to strengthen the social, health and therapeutic well-being of senior citizens. Meanwhile, the Ziarah Kasih Programme and YKN volunteers are also implemented at the grassroots level for monitoring and emotional support of senior citizens. We are doing a lot, Batang Sadong, yes. KPWKM also focuses on concrete long-term measures through efforts to professionalise care through the strategic framework...

[Bangun]

...and the Malaysia Care Action Plan 2026 to 2030. Among the focuses given is on structured training and increasing the competency of caregivers to ensure quality care can be provided efficiently and family caregiver support, namely caregiver support, with permission. To strengthen care, KPWKM is actively conducting training for caregivers, especially senior citizens, through the Social Institute of Malaysia (ISM). KPWKM is targeting training for 2,000 people this year. In conclusion, the government is indeed committed to building an inclusive care ecosystem so that family members receive proper assistance in terms of welfare support, facilities and

emotional support in caring for the welfare of senior citizens in Malaysia. That is all, thank you.

Thank you, the Honourable Minister. Supplementary question, Tumpat. The Honourable Member for Tumpat.

Thank you, Mr Speaker. My supplementary question, I— we are aware that in cases of caring for parents or senior citizens, this involves the sandwich generation who have to look after their parents and work. So, if we look at it, support is needed for them before we impose any penalty on them through the act that we are going to establish. My question is, does the government intend to increase the amount of assistance for neglected elderly persons or senior citizens, for caregivers, because the current cost is not sufficient for them to leave work and look after the family or elderly family members? That is the first. Second, we know that to face an aging generation, one ministry is not enough. Does the government intend to establish a National Senior Citizens Council to ensure that care monitoring will cut across ministries involving JKM, KKM, state governments, local authorities (PBT), communities and service providers, so that all government assistance and planning for senior citizens can truly reach its target? Thank you.

Thank you, the Honourable Member. The Honourable Minister, please proceed.

Thank you, the Honourable Member. Earlier, the Honourable Member, what's his name— Tumpat. Earlier, the Honourable Member asked about, what's it called, whether we cooperate with others for senior citizens. Indeed, we do have cooperation, we have, what's it called — council, yes, we have one. And also for caregivers with, with permission, later, that we cannot touch on here. If there is anything from the government that will be announced, perhaps if there is, it will be announced. However, we focus more on, what's it called, training, training for caregivers, with permission, of which I mentioned earlier there are 2,000 for this year. And now we are nearly at 3,000 already trained, and we are targeting for the year 2030, we have 50,000 of these caregivers. And from there we, although we

indeed plan for them— because they are mostly from among our institutions as well. So, we really want them to get a higher allowance, but we cannot commit to that yet because we cannot pre-empt what we are applying for. We only strive, we only pray and strive so that they can get all of that. And as for the other matters, we wait until this bill, once it has been passed. Because we cannot pre-empt the law that we, what's it called— that we establish, that we, that will come. And in fact we already have the National Senior Citizens Advisory and Consultative Council (MPPWEN), which I myself chair as the Minister. Only, that's it, Honourable Member, we wait together. We cannot say anything first because perhaps I can explain further, with permission, earlier you asked about this law, this bill. Yes, we are ready to table it, with permission, for our intention at the Cabinet. But we need to wait, we have a queue, Honourable Member. If we want to wait, our, what's it called— the intention is already included in this, in this Cabinet Meeting (MJM), so that takes time too, but God willing, we are ready for this year. However, for it to be tabled, perhaps early next year, God willing. Because too many have applied to be heard. So, we have to go back to those who have already asked. To repeat to be heard again, we, we give them the opportunity, and we must go through everyone, the whole country. We go to every state. So, please be patient first, yes. Thank you.

Thank you, the Honourable Minister. For the next question, I invite Dato' Seri Hamzah bin Zainudin, Larut. Please proceed.

Thank you, Mr Speaker. My question number 2.

Hamzah bin ZainudinBERSATU · PNLarut · questionEN

2. Dato' Seri Hamzah bin Zainudin [Larut] asks the Minister of Finance to state the total national tax collection for the current year compared with previous years.

Tuan Liew Chin TongDAP · PHDeputy Minister of Finance · Iskandar PuteriEN

Thank you, Mr Speaker. Thank you to the Honourable Leader of the Opposition. For the information of the Honourable Members, the Federal Government receives direct tax revenue and indirect tax revenue, which are collected respectively by the Inland Revenue Board of Malaysia and the Royal Malaysian Customs Department, respectively, by

Tuan Liew Chin TongDAP · PHDeputy Minister of Finance · Iskandar PuteriEN

the Inland Revenue Board of Malaysia and the Royal Malaysian Customs Department. Annual tax revenue collection data can be checked through the Financial Statement of the Federal Government published by the Accountant General's Department of Malaysia, or in the Malaysian Economic Quarterly Bulletin documents and the Federal Government Fiscal Outlook and Revenue Estimates published by the Ministry of Finance.

Tuan Liew Chin TongDAP · PHDeputy Minister of Finance · Iskandar PuteriEN

For 2026, Malaysia's economic growth recorded a better performance in the second quarter at six per cent compared with the first quarter at 5.4 per cent, despite the country facing global supply chain shocks that affected the world economy. This second-quarter achievement brings growth for the first half of 2026 to 5.7 per cent, thereby placing the Malaysian economy on a solid footing to achieve the growth projection of between four per cent and five per cent for 2026. This growth is supported by the strength of domestic demand, which continues to be a buffer against external pressures, encouraging performance in exports of electrical and electronics (E&E), as well as growth in the services and manufacturing sectors. Malaysia also recorded a trade surplus totalling RM84 billion, a significant increase of 449.2 per cent compared with the same period in 2025. In line with this economic growth, tax revenue collection up to June 2026 also increased by nine per cent, namely RM129.6 billion compared with RM119.1 billion for the same period in 2025. This increase in revenue is contributed, among others, by higher corporate income tax collection as well as sales tax and service tax collection, mainly from the food and beverage, services, insurance and logistics sectors. The government is committed to achieving the tax revenue collection target for the whole of 2026 totalling RM343.1 billion. A stable macroeconomic growth is expected to continue to have a positive impact on the increase in tax collection. Targeted tax reform measures also play a role in ensuring a more effective revenue collection mechanism and serve as a foundation for building investor confidence, economic stability and the country's competitiveness. That is all, thank you.

Supplementary question. Dato' Seri Hamzah bin Zainudin, Larut.

Thank you, Mr Speaker. Thank you, Minister. From what I hear, the tax collection or revenue that the government collects has increased by nine per cent this year. I congratulate you, and this is because of the tax regime that the government is implementing at present, which is getting returns from the food sector and also logistics, as stated by the Minister. This shows that this tax regime will be maintained under the Sales and Services Tax (SST) method, or as I have heard, the Honourable Tambun said there is a new tax regime. It is a combination of SST and GST. This is what I heard. I also heard the Deputy Prime Minister, Bagan Datuk, said we want to return to the Goods and Services Tax (GST). So, I want to know, is this because— as a businessman, many want to know the actual method so that planning can be done. What I fear is that this planning is not clear. For example, e-Invoice. Sometimes it is said the exemption threshold is being raised— RM150,000, RM300,000, RM1 million. Today it has been said RM3 million. So, this is what makes me less sure whether this government actually has a plan or not. Please.

Okay, the Minister may respond.

Tuan Liew Chin TongDAP · PHIskandar PuteriEN

Thank you, the Honourable Leader of the Opposition. There are two issues raised by the Honourable Leader of the Opposition. One is regarding SST and GST, and the second is regarding e-Invoice.

[Bangun]

Tuan Tan Kar HingPKR · PHGopeng

[Bangun]

[Bangun]

Tuan Liew Chin TongDAP · PHIskandar PuteriEN

With regard to the GST and SST, as stated by the Right Honourable Prime Minister on 18 August at the Ministry of Finance during an engagement session with various sectors, the government will absorb the elements considered good in the GST system into the existing system. The existing system is SST. However, there are indeed GST elements, such as ensuring there is no cascading effect and no double effect in the tax system. Those will be incorporated into the existing system. This means our system is the SST system, but we take elements from the GST system where we ensure there is no cascading element and no cascading effect in what we have.

Tuan Liew Chin TongDAP · PHIskandar PuteriEN

Now, why do we want to continue the SST system? Because the SST system is easier for everyone to understand and has a history of more than 50 years. Many have proposed the GST system because they feel it has been adopted by other countries. The GST or VAT, value-added tax, began in France in 1954. At that time, there were no invoices. At that time there were only inputs and outputs. Why does GST need inputs and outputs? Because GST at that time had no invoices. We already have invoices, so there will be no leakage. And why is GST not necessarily the best system? Because if GST requires 480,000 collecting parties, that means 480,000 companies will be made collection agents. But SST requires only 80,000 companies. So, this is the difference between the two systems. What we want to create is a system where we do not disturb the largest group. And GST has direct pass-through to users, consumers. This means consumers will bear everything, and businesses like it because they can pass it through directly. So, what the government wants to create is a balance so that consumers are not burdened and our businesses ensure there is no cascading effect. For e-Invois, what happened is that since 1 August 2024, companies with annual sales exceeding RM100 million, namely 5,578 taxpayers, have implemented e-Invois on 1 August 2024. After that, companies with annual sales between RM25 million and RM100 million, that has also been implemented and involves 14,567 taxpayers. After that, what exceeds RM5 million...

Honourable Minister, summarise your answer. Thank you.

Tuan Liew Chin TongDAP · PHIskandar PuteriEN

Summarise. Those who... [Speaking without using the loudspeaker]

Beberapa AhliKetawa] Dato’ Haji Tajuddin Abdul Rahman [Pasir SalakEN

Mic, mic, mic.

Tuan Liew Chin TongDAP · PHIskandar PuteriEN

Those exceeding RM5 million up to RM25 million, involving 51,710 taxpayers, have also been implemented. What has seen changes or pushback is among those at RM5 million and below. And what was decided by the Right Honourable Prime Minister cum Minister of Finance on 31 August, announced by the Right Honourable Prime Minister, is that, for now, those between RM3 million and RM5 million, namely 25,503 taxpayers, will be included in the e-Invois system.

Tuan Liew Chin TongDAP · PHIskandar PuteriEN

Others will participate voluntarily, and they may choose not to be involved in the e-Invois system. Thank you.

Thank you, Honourable Minister. The next supplementary question. Honourable Tebrau.

Tuan Jimmy Puah Wee TsePKR · PHTebrauEN

Thank you, Puan Sri Speaker.

Tuan Jimmy Puah Wee TsePKR · PHTebrauEN

Thank you, Deputy Minister, for the comprehensive answer. Actually, I want to ask about e-Invois, but half has been answered and half has not yet been answered. First, I hope the government can be more mindful of the challenges faced by PKS, and I hope there will be policies that are more friendly to SMEs, because there are indeed challenges out there. My question is, the implementation of e-Invois is one important instrument in increasing compliance and reducing tax leakage. Accordingly, taking into account the policy change that raises the threshold for e-Invois implementation from annual income of RM1 million to RM3 million, how many business entities or companies will now actually be exempted from the obligation to implement e-Invois? And what is the estimated impact of this exemption on the country's potential tax revenue collection? That is all, thank you.

Please, Honourable Minister.

Tuan Liew Chin TongDAP · PHIskandar PuteriEN

Thank you to the Honourable Tebrau. Actually, e-Invois is not a system to collect more tax. So, the last question is actually irrelevant because this is not—– the e-Invois system is not meant to add tax. Among those exempted from—– them, PMKS with annual sales of RM3 million and below, 1.1 million taxpayers were exempted in the recent adjustment. And among them, 160,000 have registered as taxpayers and they may choose to continue or they may choose not to continue. 160,000 taxpayers. I indeed agree with the Member of Parliament for Tebrau that among the challenges for PMKS are tax compliance and so on, which the government will try and is trying to reduce bureaucracy and also ensure PMKS do not need to comply with the e-Invoice system and other challenges. But the challenges for PMKS include influx from other states, including the shift from physical shop to online

Tuan Liew Chin TongDAP · PHIskandar PuteriEN

shop and the various challenges faced by PMKS in our country and also in the region and worldwide after the COVID-19 pandemic period. What we hope is that we as the government, and especially in the upcoming budget, the government will reduce the burden and also improve the resilience of PMKS against challenges that are serious, including influx from other states. Thank you.

Thank you, Honourable Minister. We move on...

Dato’ Rosol bin WahidBERSATU · PNHulu TerengganuEN

Speaker, may I have one more, Speaker? Speaker, Hulu Terengganu, one more regarding...

No, sorry. Sit down, Honourable Member. We move on to the next question.

Dato’ Rosol bin WahidBERSATU · PNHulu TerengganuEN

Because I see the Deputy Minister did not notice the GST in front of him. Thank you.

Honourable Member, Honourable Member. We move on to the next question, Dato' Seri Utama Haji Aminuddin bin Harun, Port Dickson.

Thank you. Port Dickson, question number 3.

Aminuddin bin HarunPKR · PHPort Dickson · questionEN

3. Dato' Seri Utama Haji Aminuddin bin Harun [Port Dickson] asks the Minister of Education to state the number of six-year-old children who have registered for Standard 1 for the 2027 school session compared with the estimate of 439,744 persons based on DOSM 2022 data, as well as the ministry's readiness in terms of teachers, classrooms, infrastructure and allocations to accommodate the 471,504 seven-year-old children who are required to enter Standard 1.

Tuan Wong Kah WohDAP · PHDeputy Minister of Education · TaipingEN

Thank you, Madam Speaker, thank you, Honourable Port Dickson, the third question. The Ministry of Education (KPM) has made a decision to expand access to Standard 1 by giving parents the option to register their children, the six-year-old cohort, for Standard 1 starting from the 2027 academic calendar. Implementation of this is based on parental choice, while enrolment of the seven-year-old cohort remains the main route throughout this transition period. For the information of Honourable Members, based on data as of 30 September 2026, a total of 73,498 applications for registration in Standard 1 for the 2027 academic calendar involving six-year-old cohort children have been received. Meanwhile, the total number of seven-year-old cohort children is 418,151.

Tuan Wong Kah WohDAP · PHDeputy Minister of Education · TaipingEN

This brings the total to 491,649 pupils registering for Standard 1 in 2027, covering both the seven-year-old cohort and the six-year-old cohort. KPM takes into account the needs and implications of various matters such as infrastructure, human resources and other preparations to ensure readiness following the implementation of this policy in 2027. As has already been answered before, in terms of infrastructure development, human resources and other matters, KPM is ready to face enrolment that shows a slight increase. In this context, KPM originally planned to provide a total of 2,596 new classrooms using the modular IBS (Industrialised Building System) method, involving 838 schools, to accommodate the entry of our children in the six-year-old cohort. However, given that registration is now around 73,000, taking into account the registration of the six-year-old cohort of 73,498 pupils, KPM is currently carrying out the construction of an additional 677 classrooms involving 605 schools, and all these projects are being implemented through the modular IBS concept. And for the same purpose, a total of 1,514 maintenance and upgrading projects are also being carried out in schools to enable an additional 1,514 new classrooms through a change of function from the original special rooms. And with the completion of classroom construction through IBS and also the change of function through maintenance and upgrading, the number of pupils registered next year can be accommodated. And at the same time, for teacher requirement planning based on enrolment projections and actual needs, as mentioned before, a total of 3,150 contract of service teachers have been approved. And at the same time, for those who have passed the health screening, they will receive appointment offers this month and the actual appointments will take place on 7 December 2026. And this appointment is specifically to accommodate the increase in enrolment of the six-year-old cohort pupils as we mentioned. KPM will continue to monitor the development of registration and the readiness of every school, every state and every district, and will carry out coordination from time to time. Because of the statistical dynamics or the data we have, it is dynamic, and we will carry out monitoring from time to time. Thank you, Madam Speaker.

Alright. Supplementary question, Honourable Port Dickson, please.

Thank you, Madam Speaker, thank you, Honourable Deputy Minister who answered the question. My supplementary question: of the 73,498 six-year-old cohort children who have registered as of 30 September 2026, what is the number and percentage compared with DOSM 2022 data by state? And will the ministry intensify incentives or promotion to encourage more parents to register their six-year-old children? If the number of registrations for the six-year-old cohort suddenly increases at the last minute, what is the ministry's assurance that states recording the highest registrations will not face shortages of teachers, classrooms and allocations before the 2027 session begins? Thank you.

Tuan Wong Kah WohDAP · PHTaipingEN

Thank you, Honourable Port Dickson, thank you, Madam Speaker. Madam Speaker, I would like to take the opportunity to make a slight correction or provide clarification regarding the number of new classrooms being built under modular IBS, which is 677 projects, covering 1,478 additional new classrooms in 605 schools.

Tuan Wong Kah WohDAP · PHTaipingEN

So, the total of new additional classrooms is 1,478, and this is added to the classrooms that have been converted in function to classrooms, a total of 1,514 additional classrooms that have been prepared. To answer the Honourable Port Dickson's question number one regarding the breakdown by state, I have the breakdown for each state in my hand, but I will hand it over to the Honourable Port Dickson first, though perhaps I will mention that the highest is in Selangor, where registration is approximately— is 108,893, and the remaining balance is divided among the related states. I will hand over the full list later. Number two, regarding whether KPM...

Please summarise the Honourable Minister's answer...

Tuan Wong Kah WohDAP · PHTaipingEN

Yes. Regarding the issue of whether we are able to handle admissions if registration suddenly surges. As I

Tuan Wong Kah WohDAP · PHTaipingEN

said earlier, our readiness in terms of teachers and infrastructure is in place. However, when we see the trend of increase, from my answer about three months ago until today, it is roughly the same. So we do not expect there to be a sudden increase in the next two months. And what has been prepared is sufficient at this rate, but as I said, we will monitor from time to time. What is important for this first year is that we give parents the opportunity and option, because parents are the ones who best understand the situation and readiness of their respective children, and this is the approach used by KPM, parental choice. Thank you.

Alright. Thank you. Honourable Kuala Krau, the next supplementary question.

Tuan Haji Kamal bin AshaariPAS · PNKuala KrauEN

Thank you, Speaker. Based on the answer just now, the six-year-old registration rate is very low compared with the DOSM report. So, has the ministry conducted a study on the main causes of this lack of registration? Are parents now more inclined to take a wait-and-see approach to ensure their children's admission is timely and capable of achieving what the ministry intends? Or has the ministry conducted a study on parents' fear of sending their children to school following the rise in cases that exceed the usual? Thank you.

Thank you, Honourable Member. Minister, please.

Tuan Wong Kah WohDAP · PHTaipingEN

Thank you, Honourable Kuala Krau. As I said earlier, first, we give priority or option to parents to decide whether to send their child to school, to enrol their child in school in the six-year-old cohort. And this option is given because we know that for this first year, indeed as mentioned by Honourable Kuala Krau, there are factors that may affect or cause concern as to whether we are ready or not. And this has been proven by the efforts from the beginning of the year until this tenth month, all efforts in terms of human resources, in terms of teacher training, in terms of improving this infrastructure, KPM is ready. For next year too, the option will also be given, and we believe that with a perfect implementation and a good implementation in 2027, next year we expect that enrolment will increase for the six-year-old cohort in the coming year. Thank you, Madam Speaker.

Tuan Wong Kah WohDAP · PHTaipingEN

Thank you, Honourable Minister. We move on to the next question. Dato' Hajah Siti Zailah binti Mohd Yusoff, Rantau Panjang, is invited. Honourable Member, please.

Thank you, Madam Speaker. I request that my question be answered, question number 4.

4. Dato' Hajah Siti Zailah binti Mohd Yusoff [Rantau Panjang] asks the Minister of Works to state the total of the RM157.15 million allocated for 385 Federal road maintenance works in the Central/East Zone in 2026 that was allocated to Kelantan, as well as the number of projects that have been completed.

Siti Zailah binti Mohd Yusoff (Kak Lah)PAS · PNRantau Panjang · questionEN

Honourable Minister, please.

Thank you, Rantau Panjang. She did not speak in pantun, and I will not speak in pantun. Whoever speaks pantun to me, I will answer with a pantun.

Datuk Seri Dr. Haji Ahmad bin Haji MaslanUMNO · BNDeputy Minister of Works · PontianEN

For the information of Honourable Members, the Ministry of Works, through the Public Works Department (JKR), is responsible for maintaining the Federal Roads in the state of Kelantan, with a total length of 1,250.879 kilometres, involving three categories of roads: protocol roads, 36.9 kilometres; main roads, 861.079 kilometres; and secondary roads, 352.9 kilometres. These roads are maintained by the appointed Federal Road maintenance concession companies. With reference to the Honourable Member's question, the allocation totalling RM157.15 million for the Central/East Zone, namely the states of Kelantan, Terengganu, Pahang and Selangor, is an allocation under the programme to empower G1 and G4 class contractors. For Federal Road maintenance works, they are offered by lottery draw. Of this total, RM33 million has been allocated for repairs of Federal roads in the state of Kelantan. This covers seven periodic pavement road maintenance works, RM9.8 million, 84 non-periodic pavement maintenance works, RM23.2 million, and 85 works have been fully completed. Meanwhile, six more works are still being implemented,

expected to be completed in November. Overall, 91 contractors from class G1 to G4 benefited in the state of Kelantan from this project. For the overall implementation of Federal Road maintenance works, up to September 2026, this ministry has allocated a total of RM784.6 million to carry out maintenance works on Federal Roads in the Central/East Zone involving 1,178 works in Kelantan, Terengganu, Pahang and Selangor, apart from what I mentioned earlier. Based on the estimate of state road maintenance for Kelantan for 2026 prepared by JKR, non-pavement road maintenance works, periodic pavement works, minor bridge maintenance, street light and traffic light maintenance totalling RM606.49 million involve 859 works, RM79.32 million under the periodic pavement maintenance programme, 53 works. A total of RM41.74 million under the periodic non-pavement maintenance programme involving 123 works. RM1.73 million under the minor bridge maintenance programme involving five works and RM4.07 million under the street light and traffic light maintenance programme involving 36 works, carried out by the concession companies through Work Orders (AK) for electrical maintenance works by departmental procurement. Overall, as of September 2026, a total of 158 works have been fully completed, while the remaining 66 works are expected to be completed in November 2026. Thank you.

Thank you, Honourable Minister. Supplementary question, Rantau Panjang. Please.

Thank you, Honourable Minister. Supplementary question, Rantau Panjang. Please proceed.

Yes. Thank you, Honourable Member. Thank you for the answer given. My supplementary question is: what formula is used to distribute maintenance allocations across the states so that they are commensurate with each state's needs? Likewise, areas affected by floods and the like may need — their needs differ from areas not facing floods. I would also like to know what efforts are being made to upgrade, especially the roads that are the main routes of border economic zones, particularly at the entry points, so that the roads are of high quality and repeated patching does not recur. It means every year we keep repairing the same road.

Likewise, roads that are affected, especially for safety needs, particularly in the flood season when the road is submerged, since floods easily submerge them. So, to what extent is the ministry's effort to address critical roads like these so that they are made stronger, more resilient and durable? Please explain.

The Honourable Minister, please.

We have begun what is known as the PCA test – pavement condition assessment – on road complaints, and we have completed the pavement condition assessment across all Federal Roads in Peninsular Malaysia, and we are in the process of conducting this PCA for Sabah and Sarawak. In Peninsular Malaysia, it was carried out by the company IKRAM, which was appointed under a concession. From the pavement condition assessment, we know the capability level of those roads, and it is not that we deliberately patch roads. Once an analysis of the road's condition has been conducted, then we will patch in accordance with all the maintenance projects for which we obtain funds from the Ministry of Finance.

For the Honourable Member's constituency, for example, this is a slightly different matter but I would like to inform you. Of course, the Honourable Member is well aware that we have approved a road and bridge enlargement of RM45.14 million for Gual Periok, Rantau Panjang. The enlargement of bridges is from two lanes to four lanes between the Rantau Panjang border and also Golok, Thailand. Thank you.

Thank you, Honourable Minister. The next supplementary question is invited from the Honourable Tenggara.

Thank you, Mr Speaker. Tenggara's supplementary question refers to the first question from Rantau Panjang, a good question. But that question concerns only the East Coast and Kelantan. So I would like to ask: what is the lottery draw data for other states? And what is the total amount of road maintenance, excluding the lottery draw, for 2026, and is this allocation sufficient? Thank you.

Mana cukup.

Silakan Menteri.

Ha, thank you Tenggara. The answer to that last question, whether it is sufficient, is that the answer is insufficient. Our requirement is five to six billion Ringgit for road maintenance in Peninsular Malaysia, in Sabah and also in Sarawak. But in 2026, we have only received RM3.18 billion, of which Peninsular Malaysia is 2.08 billion, Sabah 640 million, Sarawak 461 million, total 3.18. Whereas our requirement is five to six billion Ringgit. Therefore we apply to the Ministry of Finance in the upcoming budget to please provide an adequate allocation. As for the lottery draw, in 2026 the lottery draw for G1 to G4 for the benefit of small contractors, G1, G2, G3, G4, totals RM700 million. RM300 million for Peninsular Malaysia, RM200 million for Sarawak, RM200 million for Sabah, and we implement it by draw so that it is transparent to the contractors involved. Thank you.

Thank you, Honourable Minister. For the next question we turn to Tuan Haji Onn bin Abu Bakar, Batu Pahat. The Honourable Member, please.

Tuan Haji Onn bin Abu BakarPKR · PHBatu PahatEN

Kedondong fruit, pomegranate fruit, My question is number five.

Onn bin Abu BakarPKR · PHBatu Pahat · questionEN

5. Tuan Haji Onn bin Abu Bakar [Batu Pahat] asks the Minister of Communications to state the latest status of the ministry's efforts to acquire or purchase the ownership rights, copyright or management rights over the films of the Great Artist Tan Sri P. Ramlee that are currently owned by certain parties, so that these works can be preserved as a national heritage asset.

The Honourable Minister, please.

Puan Teo Nie ChingDAP · PHDeputy Minister of Communications · KulaiEN

Thank you. Thank you Madam Speaker, thank you to the Honourable Member for Batu Pahat. The Ministry of Communications, through FINAS (National Film Development Corporation Malaysia), recognises the works of the Great Artist, the late Tan Sri P. Ramlee, as an invaluable artistic treasure and national heritage. The government is committed to ensuring that his works and legacy continue to be preserved and can be enjoyed by the present and future generations. For information, the government does not currently hold the copyright over the films of the late Tan Sri P. Ramlee. However, these works are not left without preservation. Most of the films and also songs of

Puan Teo Nie ChingDAP · PHDeputy Minister of Communications · KulaiEN

Tan Sri P. Ramlee have been kept by the National Archives of Malaysia as national heritage records. In terms of ownership rights, this matter needs to be examined in detail because the late artist's works were produced under two different production companies. For the period 1948 to 1964, most of his films were produced by Malay Film Productions, a studio owned by Shaw Brothers in Singapore, with copyright associated with Shaw Brothers. Meanwhile, for the period 1964 until 1972 he produced 18 films under Merdeka Film Productions in Kuala Lumpur. Therefore the status of rights ownership needs to be determined for each work based on production records, agreements and related documents, because any negotiation to acquire or manage rights can only be carried out with the lawful rights holders. At the same time, preservation efforts continue to be implemented under section 7(c) of the National Archives Act 2003 [Act 629]. The National Archives of Malaysia has acquired 45 films and also 65 audio items of his songs from various sources including the Department of Broadcasting Malaysia and also EMI Sdn. Bhd., all of which are stored securely and can be accessed for research purposes. Accordingly, the ministry through FINAS will continue to examine the best mechanisms to acquire and make use of his works as national heritage assets, including through the acquisition of rights, joint management or forms of cooperation suitable with the rights holders. This examination takes into account the legal position, negotiations with the rights holders, the interests of the heirs and the government's financial capacity, so that any action can be implemented lawfully, in an orderly manner and fairly to all parties. The government will continue to ensure that the works and also the legacy of the late Tan Sri P. Ramlee are preserved since— as an artistic treasure and national heritage so that they may continue to be appreciated, studied and enjoyed by future generations. That is all, my answer. Thank you.

Thank you, Honourable Minister. Supplementary question, Batu Pahat. Please.

Tuan Haji Onn bin Abu BakarPKR · PHBatu PahatEN

Thank you, Madam Speaker. We are talking about the great works of the Great Artist Tan Sri P. Ramlee. His films Anakku Sazali, Pendekar Bujang Lapok, Ibu Mertuaku, Madu Tiga and Tiga Abdul, and the others. My supplementary question to the Deputy Minister is, is

Tuan Haji Onn bin Abu BakarPKR · PHBatu PahatEN

the government prepared to establish a National Tan Sri P. Ramlee Digital Archive that can bring together his films. If I am not mistaken, it is estimated there are 66 films in which he acted and 33 films he directed. It is said there are 300 to 1,000 songs composed, thousands of scripts, posters, photographs, recordings and historical documentation of his, in a national repository to be used for research and education for future generations.

The Honourable Minister, please.

Puan Teo Nie ChingDAP · PHKulaiEN

Thank you, Dato' Sri Speaker. Thank you to the Honourable Member. This is a very good proposal from the Honourable Member for Batu Pahat. As I mentioned earlier, the National Archives of Malaysia has now acquired 40 films and also 65 audio items of Tan Sri P. Ramlee's songs. I am not sure whether the National Archives of Malaysia currently has any effort to establish an archive in digital form. But under FINAS we do have efforts to digitalise all the materials that are in FINAS's storage. So, I will check whether FINAS and the National Archives of Malaysia are cooperating so that we can jointly digitalise all of Tan Sri P. Ramlee's works. That is all. And if we acquire more copies of Tan Sri P. Ramlee's works, FINAS will certainly do its best to ensure his works are well preserved. Thank you.

Thank you, Honourable Minister. Supplementary question, Pasir Salak. Please.

Tuan Haji Jamaludin bin YahyaPAS · PNPasir SalakEN

Thank you, Madam Speaker. The Honourable Deputy Minister, given that the copyright protection period for films is basically 50 years, has the ministry carried out a comprehensive audit to identify the rights still held by certain parties, including copyright, distribution and original copies? And how many original materials of P. Ramlee's films still exist and need to be urgently restored before they are damaged or lost forever? Thank you.

Silakan.

Puan Teo Nie ChingDAP · PHKulaiEN

Thank you, Dato' Speaker, and thank you to the Honourable Member. For FINAS, we do have efforts to contact the rights holders for the works of the late Tan Sri P. Ramlee so that we can obtain copies, but these negotiations are still continuing because, among other things, there are requests from the rights holder. But this effort will indeed continue

Puan Teo Nie ChingDAP · PHKulaiEN

until last month when we received feedback from Shaw Brothers, their office in Singapore. So, if we obtain any copies of Tan Sri P. Ramlee's works, we will certainly do our best to ensure his works can be preserved well. Thank you, Honourable Member.

Okay, thank you. For the next question, the floor is given to Datuk Seri Panglima Madius bin Tangau, Tuaran. Please, Honourable Member.

Thank you, Madam Speaker. The Tuaran question is question number 6.

Wilfred Madius TangauUPKO · PHTuaran · questionEN

6. Datuk Seri Panglima Madius Tangau [Tuaran] asks the Minister of Energy Transition and Water Transformation (PETRA) to state what plan, together with the Sabah State Government, there is to end water rationing and disruption in Tuaran, including projects, allocations, NRW targets, reserve margins, and the dates by which all villages will receive treated water.

Silakan, Menteri.

Dato’ Sri Haji Abdul Rahman bin Haji MohamadUMNO · BNDeputy Minister of Energy Transition and Water Transformation · LipisEN

Thank you, Mr Speaker. Thank you, Honourable Member for Tuaran. For the information of the Honourable Member, the Federal Government through the Ministry of Energy Transition and Water Transformation (PETRA) constantly works closely with the Sabah State Government through the Sabah Water Department (JA Sabah) to address the issue of water supply disruptions in the state, including in the district of Tuaran. At present there are two projects totalling RM624.7 million in the Tuaran District that have been approved, and to increase the reliability capacity and coverage of the water supply system, namely the Telibong 2 Water Treatment Plant Capacity Enhancement Phase 1, from 80 JLH per day to 160 JLH, including main pipelines and storage tanks, was completed on 23 July 2025. Good news, in that the Telibong 2 Water Treatment Plant Phase 2 Main Pipe and Distribution Pipe Installation Project, in the Kota Kinabalu district of Sabah, had a letter of acceptance issued on 5 October 2026. For the information of the Honourable Member, the ideal range recommended by the National Water Services Commission (SPAN) is between 10 percent and 15 percent. The current reserve margin rate for the state of Sabah is 1.81 percent. To increase the reserve margin rate in the state of Sabah, the Sabah Water Department is now

Dato’ Sri Haji Abdul Rahman bin Haji MohamadUMNO · BNDeputy Minister of Energy Transition and Water Transformation · LipisEN

carrying out four projects to construct new water treatment plants as well as upgrade existing WTPs. As for non-revenue water (NRW), based on 2025 records, the NRW rate for the state of Sabah is 59.6 percent. Implementing NRW reduction will in fact also help increase the reserve margin rate for water supply. Three projects have been completed in the state of Sabah under the NRW Approach 1 Programme Phase 1, with a total allocation of RM82.2 million as grants. As a continuation, PETRA will implement the NRW Approach 1 Programme Phase 2, which begins in 2025 and runs until 2030, involving the Critical Pipe Replacement Programme and holistic NRW solutions covering the establishment of District Metering Zones (DMZ) and Pressure Management Areas (PMA) as well as the implementation of Active Leakage Control (ALC). As the Honourable Member is aware, the management of operations and infrastructure planning for water supply in Sabah is under the jurisdiction of the Sabah state through JA Sabah. In line with the Sabah Water Supply Enactment 2003, therefore, setting a specific target date for treated water coverage in all villages requires detailed planning by JA Sabah, taking into account factors such as plant capacity, availability of water sources, pipe distribution network and adequacy of financial allocation. The Federal Government remains committed to supporting this effort through the federal development allocation channel in the form of loans and grants. Thank you, Mr Speaker.

Thank you, Honourable Minister. Supplementary question, Tuaran. Please.

Yes, thank you Mr Speaker. Thank you, Honourable Minister, for the comprehensive answer just now. Tuaran thanks you because, although water matters are a state matter, the Federal Government provides assistance including what was mentioned just now as grants, although most of what has been given is in the form of loans. My supplementary question just now is: the Honourable Minister has stated several projects to increase the treatment production capacity carried out by the Sabah Water Department, could the Honourable Minister state what those projects are, those four projects just now, state them. And once they are finished, presumably what would be the target reserve margin for the state of Sabah after they have all been completed? And

where are they located, on the East Coast, on the West Coast, in the south, where are they located? Thank you.

Thank you, the Honourable Minister may please proceed.

Thank you, Mr Speaker, Honourable Member for Tuaran. As for the Honourable Member's question just now, to state those four projects, and before I mention the four project names, there are simply too many in the state of Sabah. The Honourable Member's efforts may be, the main pipe installation project and the plant distribution pipes that I mentioned just now, the newly issued SST worth RM195.5 million, to be implemented at any time, namely at the Telibong 2 Water Treatment Plant Phase 2, Kota Kinabalu district. And for the Honourable Member's question just now, the water supply system in Lahad Datu Phase 1 worth RM270 million, in the implementation of capacity enhancement of the Kogopun Water Treatment Plant, is that right, the pronunciation Kogopun, from 40 JLH to 80 JLH, including the target main pipes and storage tanks worth RM379.6 million. Construction of the Cinta Mata 2 Water Treatment Plant, Tawau, Sabah, worth RM335 million, the project to upgrade the Kasigui Water Treatment Plant for the water supply of the Putatan district, and upgrading the Muka Sauk at the Beaufort 2 Water Treatment Plant including related works, RM69.6 million, and overall worth RM1.054.2 billion. And for the information, that the Honourable Member asked, which was not asked but is in line with KKDW (Ministry of Rural and Regional Development), the Honourable Deputy Minister is here, the entire Sabah is so enormous, I want to mention, too thick Honourable Member, you can see the pages I have, the pages are too many, the total value of the pages between PETRA and KKDW exceeds RM3 billion, RM3.39 billion in total that has been obtained in the state of Sabah. I think the Honourable Member for Tuaran is very, very satisfied with this answer of mine. Thank you, Mr Speaker.

Thank you, Honourable Minister. Supplementary question, Kubang Kerian. Please.

Bismillahirrahmanirrahim. Thank you, Honourable Deputy Minister. My question is about how we know that this El Nino phenomenon that is occurring is actually expected to bring a major impact on the national water supply. In that situation I see that there are several matters that need serious attention by the ministry and the state water companies.

My question is, what is the contingency plan of the ministry and water companies to face the El Nino phenomenon that is expected to cause water reserves in our catchment areas to decline very seriously, and at the same time, if possible, list the states expected to face critical problems when this El Nino phenomenon occurs because of very low reserve margins. Thank you.

The Honourable Minister, please.

Thank you, Mr Speaker. Thank you, Kubang Kerian. Regarding this El Nino, in fact JPS (Department of Irrigation and Drainage) has made fairly thorough planning in this matter, and coincidentally, for this question of the Honourable Member, I had just contacted the Director-General of JPS, although he is in a slightly unwell condition, suffering from influenza and having to be quarantined. By coincidence, in fact yesterday I asked about El Nino and he said JPS is carrying out a very thorough control of the water problem, and of course JPS is the one playing the main role in this matter. The state authorities, for example Pahang – PAIP, for Sabah, the Sabah Water Department, Johor – the Johor Water Department, and also in other states, and in our efforts at the state level we are in fact ensuring that this does not happen. I understand that if there are floods, if there is drought, of course the people will feel it. But nevertheless, the Honourable Member's question, our control is through JPS, and he also expressed doubts when there is currently haze.

He is also quite worried because we are carrying out cloud seeding to prevent heavy rain. However, that control is still being carried out by the Drainage and Irrigation Department (JPS) itself, and God willing, Honourable Kubang Kerian, we will ensure it in every state. Recently we also called four states to meet so that the El Nino control that will occur can be properly ensured. Thank you, Mr Speaker.

Thank you, Honourable Minister. We now move to the next question. Dato' Haji Mohd Suhaimi bin Abdullah, Langkawi, is invited.

Thank you, Dato'.

Speaker. Honourable MinisterEN

My heart longs for the bamboo flute; My question is number seven.

Mohd Suhaimi bin AbdullahBERSATU · PNLangkawi · questionEN

7. Dato' Haji Mohd Suhaimi bin Abdullah [Langkawi] asks the Minister of Works to state whether the ministry intends to tighten the conditions for the selection and performance evaluation of contractors, given that a large proportion of sick projects identified are caused by weaknesses in contractor management and financial problems, and what new mechanisms will be implemented to prevent repeated delays in government projects in the future.

Datuk Seri Dr. Haji Ahmad bin Haji MaslanUMNO · BNDeputy Minister of Works · PontianEN

Gather provisions for the monsoon season; To make breakfast for the family; Langkawi's question is number seven; Here is the answer given.

To empower government procurement of works, the Ministry of Works, through the Public Works Department (JKR), constantly conducts studies and prepares proposals for optimal improvements to government procurement for use by all agencies. JKR has advanced three proposals and initiatives to the Ministry of Finance (MOF), which have been agreed: (i) Determination of the cut-off price range. The existing method stipulates that evaluation is carried out on tenderers offering tender prices within a range of negative 15 per cent to positive 10 per cent of the adjusted builders work (BWAM) price, and MOF has permitted JKR to carry out evaluation on tenderers offering tender prices within a range of negative 10 per cent to positive 10 per cent on a pilot basis until 31 December 2027. This method is seen as able to list the tenderers offering prices closest to the current market price for implementing government projects. (ii) Verification of certified true copies of company financial statements after several engagement sessions with the association of chartered accountancy firms (AMCAF), a proposal that certified true copy verification of company financial statements may be carried out by either an individual chartered auditor or an audit firm, has been

Datuk Seri Dr. Haji Ahmad bin Haji MaslanUMNO · BNDeputy Minister of Works · PontianEN

accepted by MOF. Previously, certified true copy verification was only carried out by audit firms. (iii) Improvement of the method for submitting current work-in-hand forms and current work performance for JKR-managed projects and newly approved projects. Under existing rules, tenderers are required to declare all current work-in-hand and submit current work performance reports when submitting tender offers. MOF has allowed projects under JKR management that are registered under the exempted scale system to be exempted from submitting these forms. As of 30 September 2026, out of a total of 875 projects at the construction stage under JKR Malaysia's supervision with a total contract value of RM40.7 billion, 33 projects or only 3.77 per cent are categorised as sick projects. Based on analysis of these 33 sick projects, 77 per cent are caused by weaknesses in contractor management, particularly in terms of less effective planning and coordination of work on site, insufficient manpower, and weaknesses in the management of machinery and supply of construction materials. Thank you.

Thank you, Honourable Minister. Please proceed, Honourable Langkawi. Supplementary question.

Thank you, Honourable Minister, and God willing, I congratulate you. God willing, all these rules and benefits will be enjoyed by the people of Malaysia. But my question, Honourable Minister, is that if we look at these contractors too, where their projects have gone off track. For example, Honourable Minister, in Langkawi, every time Honourable Minister comes down at Langkawi Airport, Honourable Minister cannot see the sea. The view is blocked by project hoardings, Honourable. There are so many hoardings, project hoardings in Langkawi, which show that these projects have failed, lah. So, Honourable Minister, is the government taking action? For example, in Langkawi, by the company Widad, the Langkasuka Project, and this project has already— the LIMA Programme, Langkawi International Maritime, has been held five times, and I see the hoardings are getting faded, more and more faded and eyesore, Honourable Minister.

So, I request Honourable Minister, if possible, that it be included in the specifications for contractors that if a project is affected or cannot be implemented for more than two years, the hoardings must be cleaned up so that people who come down to Langkawi see the sea, not the hoardings, Honourable Minister. Thank you, Mr Speaker.

Thank you, Honourable Member. Please proceed, Honourable Minister, to answer.

I think this is the Widad project under the state government, yes. I would like to inform the Honourable Langkawi that there are five construction projects under JKR in Langkawi with a total contract cost of RM561.78 million. Of that amount, two projects are on schedule; three projects are behind schedule, which I will state shortly; while no projects are reported as sick. Okay. The construction of the additional building for Hospital Sultanah Maliha, Langkawi should be 95.64 per cent complete, but what is there up there is 91.89 per cent, four days behind. The construction of Quarters for the Ministry of Health Malaysia, the quarters next to it are 96.24 per cent complete, 36 days behind; this needs to be improved. Then the construction of the Fossil Walk at Pulau Anak Tikus, Pulau Langgun, related works, 23.52 per cent, five days behind. Then the construction of the Quarters for the Akademi Correctional Malaysia (AKM Langkawi), nine days early. Next, the fifth, other related infrastructure at Gua Langsir, Kilim Geoforest Park, Ayer Hangat mukim, 33 per cent, 10 days early. So, these are JKR projects, Honourable Langkawi. The project that the Honourable Member mentioned just now is not a JKR project. Thank you.

Thank you, Honourable Minister. Supplementary question, Honourable Tanjong Manis, please proceed.

Thank you, Mr Speaker. Delays in projects are related to weaknesses in management and also financial problems. But delays in projects can also be linked to a shortage of TVET skills and construction workers. I would like to ask the Honourable Deputy Minister, as Chef de Mission to WorldSkills Shanghai this year, recently: what experience can we gain from WorldSkills Shanghai 2026 and Malaysia's achievements at the WorldSkills level, and can that experience be translated into helping local contractors implement projects more effectively? Thank you, Honourable Minister.

Please proceed, Honourable Minister.

Thank you, Honourable Tanjong Manis, who was also in Shanghai for a week. What happened last week, compared with what happened in Lyon, France, two years ago at WorldSkills. I would like to inform Mr Speaker that WorldSkills begins at the national level. Then at the ASEAN level, I was asked together with the Honourable Lipis to be Chef de Mission jointly. At the ASEAN level, in Manila, we were champions. Champions of all ASEAN with 13 gold medals. Then, the Deputy Minister of the Ministry of Rural and Regional Development (KKDW) went to Taiwan. There we secured third place with five gold medals at the Asian level. At the world level, we improved our position from 32nd to 22nd place out of 65 countries. So, we are in the top one-third of the world, with an increase in medals from five medals in Lyon to 14 medals in Lyon.

That is a very high achievement, where 11 of the world skills we competed in, including skills in construction, computing, and life skills such as cooking, and others, we have 11 skills that we rank among the world's top 10. So, this is an achievement, and we thank KESUMA and also the other ministries. And, we at CIDB and the Ministry of Works will continue to further enhance our capability for the next competitions at the ASEAN level, the Asian level, and also WorldSkills in Japan in 2026, if we are still here. Thank you.

Thank you, Honourable Minister. For the next question, we move to Dato Anyi Ngau, Baram.

Dato Anyi NgauPDP · GPSBaramEN

Thank you, Mr Speaker. My question is number 8.

Anyi NgauPDP · GPSBaram · questionEN

8. Dato Anyi Ngau [Baram] asks the Minister of Domestic Trade and Cost of Living (KPDN) to state the steps and initiatives of the ministry to ensure that supplies of subsidised goods are provided in adequate quantity and quality, transparently and with integrity, in interior areas of Sarawak such as Baram.

Please proceed, Honourable Minister.

Datuk Dr. Fuziah binti SallehPKR · PHDeputy Minister of Domestic Trade and Cost of Living

Bismillahirrahmanirrahim, assalamualaikum

Datuk Dr. Fuziah binti SallehPKR · PHDeputy Minister of Domestic Trade and Cost of LivingEN

...and His blessings. Good morning. Thank you, Mr Speaker. Thank you to the Honourable Baram for the question earlier. Honourable Member, the government, especially KPDN, which handles price and supply control, takes great care regarding the prices of essential goods, particularly in interior areas, especially in Baram. We acknowledge that Baram is the second largest constituency in terms of area among the other parliaments. So, of course, the logistical challenges are not something we underestimate. For example, in the year before we held the essential goods distribution programme, there was a time in Baram Parliament when the price of an LPG gas cylinder once reached RM250 per cylinder, but now we are able to control it to a price of RM26.60 per cylinder, which is the controlled price. This was when we introduced the Essential Goods Distribution Programme in 2009, and Baram— Honourable Baram, the Baram Parliamentary constituency was among the earliest to implement the Essential Goods Distribution Programme. In 2026, a total of RM250 million has been allocated for this Essential Goods Distribution Programme, and it involves 1.03 million residents in six states, including Sabah, Sarawak, Terengganu, Kelantan, Pahang and Kedah. It involves 212 zones, 828 distribution areas and 1,532 points of sale. Meanwhile in Baram, specifically in Baram Parliament, there are 139 points of sale, 24 zones and involves 75,593 residents, Honourable Member. There are seven categories of essential goods included in this Essential Goods Distribution Programme, namely, as we know, LPG, rice, sugar, flour, petrol, diesel, cooking oil. So, those are the seven items included in the Essential Goods Distribution Programme. As for how we ensure there is integrity and nothing of what people say— that it is transparent in this distribution, there are several steps. Among them, first, providing SOPs for the programme for our transporters. Second, establishing a special committee, namely monitoring and coordination of the programme at ministry and state level to closely monitor the performance of supply, expenditure and logistics delivery operations. Third, regular inspections in the field and assigning price monitoring officers and enforcement officers to carry out regular physical inspections at point of sale locations.

Datuk Dr. Fuziah binti SallehPKR · PHDeputy Minister of Domestic Trade and Cost of LivingEN

And, if non-compliance is found, action will be taken. And, in the case of Baram, as of 30 September 2026, 67 out of 139 points of sale in Baram have been monitored by KPDN, and KPDN also received two complaints involving two outlets, and when it was found that they exceeded the controlled price, those outlets had their services terminated immediately. That is all, thank you, Mr Speaker.

Thank you, Honourable Minister. Supplementary question, Honourable Baram, please proceed.

Dato Anyi NgauPDP · GPSBaramEN

Thank you, Mr Speaker, and thank you also to the Honourable Deputy Minister for giving a very comprehensive answer, and I am confident that with the initiatives that have been explained by the Honourable Deputy Minister just now, we pray and we very much hope that controlled goods, including these subsidies, can be delivered to the people in interior areas, especially in Baram. So, my supplementary question is: what is the total amount of government allocation used to finance these transport contractors to deliver controlled and subsidised goods to sales centres? And in addition, I also ask the Honourable Deputy Minister to give an indication or tell us what method or policy determines the transport rate paid to transporters, because we see that there are parties who have complained that the rate paid to transport contractors may be doubtful, since sometimes it is high and in other years it is also different. So, this is the question for all of us. And I request an explanation from the ministry so that these goods can be delivered to people in the interior who really need this assistance. Thank you.

Thank you. Please proceed, Honourable Minister, to answer.

Thank you, Honourable Baram, for that supplementary question. The first concerns allocation. The total allocation is RM250 million for 2026. As for Baram, I only have the monthly quota figures, yes. The monthly quota in terms of sugar, flour, cooking oil, LPG, petrol and so on. In terms of value, I can give it to Honourable Baram in writing. Regarding complaints. How do we appoint contractors? We appoint transport contractors. Sorry, Mr Speaker, we appoint transporters through

a tender process. Transporters submit quotations and eventually the tender board will decide on that and who is awarded the tender and the contract. As for the rate, it is largely related to distance, in terms of logistics. Because this subsidy is for what people call logistics, for transport, distribution, not for the goods themselves, but for bringing the goods from outside to the point of sale. So, that is their basis and it is not specific to each one. Because sometimes it involves rivers, it involves roads, Mr Speaker. It is not the same from one area to another, and the travel distance is also not the same, Mr Speaker. So, one transporter is not the same as another transporter. So, for more detail, if the Honourable Baram has specific complaints regarding any transporter, or regarding any cases suspected of leakage, then you are welcome to come and meet me in person. Thank you, Mr Speaker.

Thank you, Honourable Minister. Please proceed with a supplementary question, Honourable Kapar.

Dr. Hajah Halimah AliPAS · PNKaparEN

Thank you, Deputy Speaker. I understand very well what Baram is raising, because my voters are also in Baram, and if you look at Baram, 61 per cent of its size is larger than Pahang, the largest state in Peninsular Malaysia. So, Minister, for the interior areas of Sarawak, what is the government's actual cost to deliver each litre of petrol or diesel and each subsidised LPG cylinder to the end consumer compared with urban areas? How many premises have experienced supply shortages in the past 12 months, and what mechanism does the government have to ensure that subsidies truly reach the interior population without leakage? Don't forget, Long Lellang is within the Baram area. Doctors need to use a helicopter to get there. So, that is the significant issue regarding the interior, the problems of the interior. Thank you.

Please proceed, Honourable Minister.

Thank you, Honourable Baram, for the concern and also for the supplementary question.

The actual cost of LPG, if for example it only involves when there is this programme, Kapar. If there is an essential goods distribution programme, then delivery costs are involved. In cases where there is no essential goods distribution programme, for example, if we go to ordinary dealers, delivery costs are not borne by the government. They are not borne by the government, except in the essential goods distribution programme. So, from the RM250 million, I need to obtain the LPG delivery costs specifically, Kapar, if you want to know specifically for each individual item for...

Dr. Hajah Halimah AliPAS · PNKaparEN

Written is also fine. [Tuan Syahredzan bin Johan (Bangi) took the Chair]

Written? I will— we will ask officers to do it in writing. Okay, thank you. Mr Speaker, thank you.

Thank you, Honourable Minister. The time is now 11.32. Therefore, Honourable Members, the session for oral question time has now ended. [Question and Answer Session for Oral Replies ended]

Motion — Sitting Hours and Business Exempted from Standing OrdersMotion

Tuan M. Kulasegaran a/l V. MurugesonDAP · PHDeputy Minister in the Prime Minister's Department (Law and Institutional Reform) · Ipoh BaratEN

Mr Speaker, "Pursuant to Standing Order 12(1), I beg to propose that today's Sitting will not be adjourned until the Ministerial Motion at the Prime Minister's Department, as at Number 1 in the Order Paper and Motions for today, has been debated and decided. After that, the Sitting will be adjourned until 10 a.m. on Thursday, 8 October 2026."

Datuk Wilson Ugak anak KumbongPRS · GPSDeputy Minister of Digital · Hulu RajangEN

I beg to second.

Honourable Members, I now put the question to the House for decision. The question is that the motion as moved be agreed to.

[Motion put for decision; and agreed to]

Minister's Motion in the Prime Minister's Department under S.O. 23(3) — Report of the Auditor General 2/2026Motion

Dato’ Sri Azalina Othman SaidUMNO · BNMinister in the Prime Minister's Department (Law and Institutional Reform) · PengerangEN

Bismillahirrahmanirrahim. Assalamualaikum warahmatullahi wabarakatuh. Mr Speaker, “NOTING that Articles 106 and 107 of the Federal Constitution, as well as the Audit Act 1957 [Act 62], provide the mandate of the Auditor General as part of the nation's system of checks and balances to ensure that public money and resources are managed with accountability, subject to independent, professional and evidence-based audit. TAKING NOTE that the amendments to the Audit Act 1957 in 2024 have strengthened the institution of the Auditor General through the expansion of audit scope, the Follow the Public Money Audit approach, the power to issue audit guidelines, the power to make recommendations regarding serious irregularities, and the power to carry out follow-up audits on the recommendations, comments and views reported. NOTING that the Auditor General's Report 2/2026 was tabled in the Dewan Rakyat on Monday, 5 October 2026, namely LKAN 2/2026 (Command Paper 26 of 2026) on the Financial Statements of the Federal Government for 2025 and LKAN 2/2026 (Command Paper 27 of 2026) on the Activities of Federal Ministries/Departments. ACKNOWLEDGING that the value of an audit report does not end with identifying weaknesses, but depends on corrective action, prevention of recurrence, recovery of public money and system improvements implemented by the parties responsible. AFFIRMING that the debate on the LKAN in the Dewan Rakyat completes the chain of public accountability by providing

Dato’ Sri Azalina Othman SaidUMNO · BNMinister in the Prime Minister's Department (Law and Institutional Reform) · PengerangEN

an opportunity for the findings to be examined, explanations to be given and follow-up action to be monitored openly. THAT this honourable House calls on all ministries, departments, agencies and related entities to examine the findings and recommendations in LKAN 2/2026 objectively and to implement appropriate corrective and improvement measures in order to strengthen governance and the management of public money.” Mr Speaker, I rise today to move a motion on the Auditor General's Report 2/2026. I would like to begin with a principle that is simple but very important: public money is the people's money. That is why every ringgit spent by the government must be accountable: how it is spent, for what purpose, what the results are, and, if there are weaknesses, what action has been taken. Auditing public money is not merely an administrative process or financial procedure; it has a constitutional basis under Articles 105, 106 and 107 and is part of the nation's system of checks and balances. The professional independence of the Auditor General, meanwhile, ensures that the assessment of the use of public money is carried out objectively, with integrity and on the basis of evidence. Mr Speaker and Honourable Members, today is the eighth time the Auditor General's Report has been tabled and debated in this House. Before 2023, the LKAN was usually tabled for the attention of Members of Parliament before being referred to the Public Accounts Committee (PAC). But since 6 June 2023, the MADANI Government has taken a different approach. The LKAN is brought for open debate in the Dewan Rakyat. Why? Because accountability should not stop when the audit report is tabled. Audit must lead to action, criticism must lead to correction, weaknesses must lead to improvement, and when people's money is involved, the people have a right to know what happens after a weakness is identified. That is why the debate in this House is important. Honourable Members do not only examine the report on behalf of Parliament; we carry the voice of the people in ensuring that the government is accountable for every public dollar spent.

Dato’ Sri Azalina Othman SaidUMNO · BNMinister in the Prime Minister's Department (Law and Institutional Reform) · PengerangEN

Mr Speaker, the government views the audit function and the Auditor General's Report as an important component in the nation's chain of accountability. Auditing is essentially an accountability mechanism after an expenditure or financial decision has been implemented, with permission, post spending, to assess whether public money has been spent properly, prudently and in achieving the objectives set. However, accountability should not only occur after an expenditure has been made or after a weakness has been identified through audit. That is why the government is also developing an institutional reform framework that places emphasis on prevention, integrity and accountability, as one of the components of the institutional reform ecosystem. Upcoming initiatives such as the Freedom of Information Act aim to expand access to information and enhance integrity in government processes. The Political Funding Act, meanwhile, aims to establish a more transparent and responsible framework for political financing. The establishment of the Ombudsman Malaysia will also strengthen the system of checks and balances over public administration. In other words, the Auditor General's Report helps us to see and correct what has happened. Meanwhile, the institutional reform that we are implementing aims to build a system that can prevent weaknesses before they occur. All of these complement one another. The ultimate goal is the same: a more transparent government, more responsible institutions and a system that the people can trust.

Dato’ Sri Azalina Othman SaidUMNO · BNMinister in the Prime Minister's Department (Law and Institutional Reform) · PengerangEN

Mr Speaker, LKAN 2/2026, tabled on 5 October, contains two main documents: the Financial Statements of the Federal Government for 2025 and a performance audit of four programmes or activities of ministries, departments and agencies. A total of 38 recommendations have been submitted, and for me, after this report is tabled, four questions must be answered. (i) who is responsible?; (ii) what is the corrective action?; (iii) when will that action be completed?; and (iv) how will its progress be monitored?

Dato’ Sri Azalina Othman SaidUMNO · BNMinister in the Prime Minister's Department (Law and Institutional Reform) · PengerangEN

Mr Speaker, this is the true measure of the effectiveness of audit, and we have already seen the results. As of 28 September 2026, follow-up action on audits by the National Audit Department has contributed to revenue collection and repayments to the government totalling RM920.91 million. This is not a small figure. It proves that audit that is followed by action can produce tangible recovery of public money. Therefore, the message to all ministries, departments and agencies is clear. Do not see audit criticism as an attack. See it as an opportunity to correct weaknesses, improve systems and protect the people's money. Mr Speaker, I would also like to make an appeal to the state governments. The principle of accountability cannot stop at Putrajaya. The people's money is managed at every level of government. Therefore, I call on the State Legislative Assemblies (DUN) to also provide space for the Auditor General's Report to be examined and debated openly, and not merely tabled for information. Accountability knows no political boundaries. Whether it is the Federal Government or a state government, the government or the opposition, when people's money is involved, the standard must be the same. Mr Speaker, we are now in a new phase for the national audit institution: the mandate has been strengthened, technology has expanded monitoring, and Parliament has opened space for scrutiny. But all these reforms must ultimately converge on one thing: action. Action by ministries to correct weaknesses, action by management to strengthen controls, action by oversight institutions to ensure recommendations are implemented, and action by Parliament to ensure that every ringgit of the people's money is managed with trust, efficiency and integrity, because in the end audit is not about finding who is to be blamed. Audit is about ensuring mistakes are corrected, leakages are stopped and the people's money is protected. That is accountability, that is integrity, and that is our shared responsibility to the people. Thus, Mr Speaker, I respectfully move this motion. Thank you.

Thank you, the Honourable Minister.

Tuan M. Kulasegaran a/l V. MurugesonDAP · PHDeputy Minister in the Prime Minister's Department (Law and Institutional Reform) · Ipoh BaratEN

I second the motion.

Honourable Members, the question now is that the motion of the Honourable Minister in the Prime Minister's Department be opened for debate. However, before this motion is debated, I would like to convey the wish of the Speaker of the Dewan Rakyat regarding the debate on the Auditor General's Report in this House, which has now entered its fourth year. This debate is the government's continuing commitment, through this motion of the Honourable Minister, within a Parliamentary Democracy system, to ensure that the management of public money and resources remains subject to scrutiny, checks and balances, and accountability. The amendments to the Audit Act 1957 passed by this House in 2024 further strengthened the role and mandate of the national audit institution so that the Auditor General has the independence to carry out audits, make professional judgements and submit findings, comments and recommendations based on audit facts and evidence in accordance with relevant international auditing standards. The willingness to bring the Audit Report to this House for open debate reflects the openness of the government, including the National Audit Department, to scrutiny and its commitment to strengthening accountability and governance in the management of public money. Honourable Members, before I announce the list of House members who will debate, I call on the debate to focus on the issues raised in the Auditor General's Report 2/2026 that was tabled on the tables of Honourable Members, in accordance with Standing Order 38(i). I will now read out the list of speakers. I see that there are 31 speakers on the list. Each speaker will be given five minutes unless I decide to extend it or give additional time. First, the Honourable Member for Kota Belud, the Honourable Member for Tanah Merah, the Honourable Member for Kampar, the Honourable Member for Kuala Terengganu, the Honourable Member for Putatan, the Honourable Member for Lumut, the Honourable Member for Semporna, the Honourable Member for Parit, the Honourable Member for Pasir Gudang, the Honourable Member for Kota Bharu, the Honourable Member for Betong, the Honourable Member for Kuala Krau, the Honourable Member for Rasah, the Honourable Member for Kuala Nerus, the Honourable Member for Sri Gading, the Honourable Member for Rantau Panjang, the Honourable Member for Tampin, the Honourable Member for Batu Pahat, the Honourable Member for Jerlun, the Honourable Member for Bentong, the Honourable Member for Tuaran, the Honourable Member for Tumpat, the Honourable Member for Shah Alam, the Honourable Member for Bakri, the Honourable Member for Jerantut, the Honourable

Member for Tebrau, the Honourable Member for Sipitang, the Honourable Member for Arau, the Honourable Member for Jelutong, the Honourable Member for Tanjong Karang and, last, the Honourable Member for Beaufort. Accordingly, I invite the Honourable Member for Kota Belud to begin the debate. Five minutes, Honourable Member.

Bismillahirrahmanirrahim. Mr Speaker, in March 2024 I wrote a letter to the Chairman of the PAC. What did I request? I asked that the PAC begin an investigation into the Pan Borneo Sabah Highway Project. At that time, the basis of my request was the Auditor General's Report series 1/2019 and also the course of the project, which had progressed very slowly, was doubtful and was experiencing many problems. Unfortunately, two and a half years have passed and until today there has been no action. Now today it has been proven what I have been voicing all this time, what I was worried about has been exposed by the Auditor General. This report is more complete and more detailed. A project worth nearly RM25 billion, RM24.89 billion, has experienced many problems, and clear weaknesses from the early stage, left to drag on, resulting in the project being only 11 per cent complete even though 10 years have passed. I want to ask here. Audit reports have given criticism twice already. Why is there no action? Until when will there be no thorough investigation? Until when will the enforcers continue to keep silent and take no action? Oh, if it is the Tabung Haji issue, if it is the FELDA issue, if it is the UiTM issue and it does not suit your politics, you are all exposed, all prosecuted. So, what about Sabah? Are they just left alone? Mr Speaker, to be honest, I am very disappointed. Five minutes is far too little for me to touch on all the issues for just one subject, Pan Borneo, which was raised by the Auditor General. It is not fair to be given only five minutes because the people of Sabah have the right to know what really happened. Mr Speaker, previously there were many versions. We heard about the main cause of the delay in the Pan Borneo Sabah project. Previously it was supposedly the cancellation of the PDP that was the main cause. But the fact is, page 12, point 5(e). What did the Auditor General say? I quote. “Overall, the delay in completing the LPB Sabah Phase 1 project was due to weaknesses in

project planning involving the provision of the project site, weaknesses in the implementation of the project under the PDP, weaknesses in the implementation by the consultant contractor, design changes and utility diversion.” Now we have read and we have heard that not only is the termination of the PDP not in the category of main causes, it is not even mentioned in the list of causes of delay identified by the Auditor General. In fact, the PDP that was boasted about as supposedly the best is listed as a cause. I want to say just one thing. If from now on anyone still says that the cancellation of the PDP is the cause of the delay, then you may as well go. Go and see, go and visit that audit. Mr Speaker, why do I emphasise the issue of the termination of this PDP, Mr Speaker? Because the government— It does not matter whether you are the Federal Government or the state government, when asked, first look for the fault of the previous government. That is what is prioritised instead of looking for solutions.

[Speaking without using the microphone] Correct!

Why do I say that? In the same paragraph of the report, it is stated that the same problems still occur for Phase 1B. There are still delays, there are still issues of land acquisition and valuation and utility diversion work. Sigh, it is the same as it has always been.

Instead of going to great lengths to find excuses to confuse the people for political interests, these issues should have been resolved from the beginning. Mr Speaker, first, let us go to the land issue. Page 16, paragraph 5.2.2.1(a), page 18, Schedule 5 and page 19. This describes how the RMK guidelines were breached when the SST was issued before the land was acquired and cleared. Because of non-compliance and planning failures from this early stage, it is reported that thousands of structures have not yet been demolished, involving not only Phase 1A but also Phase 1B, even though the works have been ongoing for between 13 and 15 months. What troubles me most, Mr Speaker, is when I read page 20, which states that there were only seven valuation officers from the Department of Lands and Surveys to manage a corridor 706 kilometres long. Mr Speaker, so what does that mean? Seven people, seven people, one officer would have to measure 100 kilometres each. On top of that,

it was left like that for so long until last year, only in December, that 12 private valuation firms were appointed. As if our angels only just sent them down. Mr Speaker, this is what I have repeatedly, for years, raised in this House. If we already know the project is big and will be carried out in Sabah, do not let the excuse be that there are not enough valuation officers, not enough engineers. If we already knew from the start, let us solve it, let us find a solution. We are not new at this work, it has been decades, right. And at the centre too, is it the same, was there or was there not any criticism given to the state government? Money from you, why was it left like that for so long? Second, underground utility diversion...

Honourable Member, your time is up. Land, land.

This is the main problem reported by the audit, page 11, chart two shows that this issue became the main cause of the delay of Pan Borneo, where a total of 24 EOTs were granted involving 7,994 days. These two issues, Mr Speaker, land management and utility diversion, fall under state jurisdiction and have been confirmed to have failed from the beginning. Although feedback has been given by KKR and JKR Sabah, the audit on page 13 still considers that significant weaknesses in planning and implementation resulted in cost and delay to the project.

Honourable Member, your time is up, Honourable Member.

Mr Speaker, I have just started, Mr Speaker.

Never mind, there will be other opportunities later in...

I ask to be allowed, I ask to finish, Mr Speaker. Five pages, can?

One paragraph only. One page only.

I want to make this conclusion, there is still so much of it.

You can stand up during the budget speech later.

In the budget speech we ask for allocations for the constituency, Mr Speaker. Okay Mr Speaker, since I am not allowed to continue. Never mind, later I will look for another medium to explain how I want it. Just one thing I want to tell you, let us put aside all this politics first. Okay, everyone also uses that Pan Borneo. It is not only one party and we also do not know how to learn this. We make these political colours different, can our problems be solved? No, they cannot. So for me to land, for me to land. The Pan Borneo Highway is not an act of generosity. It is not a donation, much less a political favour. It is the most important responsibility promised to us, the people of Sabah. This is a right that has been denied for a long time. The people do not care who started it, who replaces it. What the people of Sabah want to know is when the roads will be completed, that their tyres will no longer burst, that their journeys will be safe, and that Sabah's economy will grow as a result of a good road network. [Applause] That is all, Mr Speaker, thank you.

Thank you, Honourable Member for Kota Belud. Next, I invite the Honourable Member for Tanah Merah.

Dato’ Sri Ikmal Hisham bin Abdul AzizBERSATU · PNTanah MerahEN

Thank you, Mr Speaker. I hope Mr Speaker is well. I saw you walking rather unsteadily just now. Mr Speaker, in the name of Allah, the Most Gracious, the Most Merciful. Peace be upon you and the mercy and blessings of Allah, greetings of peace. Mr Speaker, the latest Auditor General's Report dated 5 October on the construction status of the Littoral Combat Ship (LCS) for the Royal Malaysian Navy (TLDM) is in fact not surprising to all of us, and to me. I myself in this august House have raised many times the questions about the rationale of the timeline and the ability of the company LUNAS to complete this project within the promised period. From one date to another new date. The Auditor General's Report once again confirms that the goalposts will shift, and the physical handover of the first LCS, LCS 1, which was guaranteed by the Honourable MENHAN in this House

Dato’ Sri Ikmal Hisham bin Abdul AzizBERSATU · PNTanah MerahEN

this past January. According to MENHAN, it would be completed in December 2026, but now it has slipped again to April 2027, next year. My question is short and firm to the Ministry of Defence (MINDEF), which must safeguard the interests of TLDM and taxpayers, not protect the feelings and interests of contractors, full stop. Will MINDEF impose a definitive penalty on LUNAS or still wish to give them face? Mr Speaker, this problem should not drag on if the real cause of the delay is identified and resolved wisely by the government today. I want to ask this August House, which government approved the additional allocation to LUNAS in 2023 when the project cost soared from 9.12 billion to 11.2 billion, although the number of ships was reduced from six to only five? Which government signed the joint agreement with Kongsberg Defence & Aerospace, Norway, during LIMA 2025 for the supply of Naval Strike Missiles (NSM) for the Kedah class? Then, we were shocked by the news that the export permit for these weapons was not approved by the Norwegian Government less than a year later. Was there no due diligence carried out by MINDEF before making such a major decision? I raise this matter because I am worried that LUNAS will use the issue of the export licence suspension for NSM missiles from Norway as a scapegoat or their latest excuse, for their failure to complete LCS 1 on schedule. Yet the Auditor General's Report clearly states that the delay was caused by the failure of vendor management under LUNAS itself. For example, one of the problems that delayed the ship's provision is related to the supply of rigid-hulled inflatable boats (RHIB) that failed to meet the contract specification standards. The Capability Management Board of TLDM itself on 18 June 2026 officially rejected these RHIBs because they would place TLDM personnel at risk of danger or loss of life. The issue of the vendor's carelessness and professionalism has dragged on since 2019 without a thorough resolution by LUNAS, or by the government itself. Mr Speaker, the public understands that in 2023, the government fully took over Boustead Naval Shipyard under the Ministry of Finance through the special purpose vehicle company, Ocean Sunshine Sdn Bhd, with the promise that oversight and project efficiency would be improved dramatically. However, the Report

Dato’ Sri Ikmal Hisham bin Abdul AzizBERSATU · PNTanah MerahEN

of the Auditor General this week proves that there has been no real change in terms of efficiency or the effectiveness of monitoring by Ocean Sunshine Sdn Bhd. Moreover, when looking at the visuals of the sea trial, the sea trial of KD Maharaja Lela in the waters of Lumut recently, it was very disheartening to see the untidy finish of the hull and the obvious rust marks on a ship that is brand new. Do not give the excuse that this problem can be easily solved with new paint, when shipbuilders elsewhere in the world do not present ships in a worn and rusted condition for their sea trials. Never happened in any part of the world except Malaysia, with permission. Therefore, I put forward two firm recommendations in this House. Just a little more, I am about to land now. First, my two firm recommendations are that the government should give a firm reminder and warning to impose a surcharge under section 18 of the Financial Procedure Act 1957 on the PMC, the Project Monitoring Committee, including— sorry, the Secretary General of Defence (KSP), the Chief of Navy (Panglima PTL), the Secretary General (KSU), for their failure to perform their oversight functions which has resulted in losses of public money, the people's money. Previously, Members of this House were given assurances when the government announced the increase of the budget ceiling from 9.3 billion to 11.2 billion, through the strict implementation guarantee by the PMC. The LCS ships would be completed on time, but this is clearly not entirely true.

Dato’ Sri Ikmal Hisham bin Abdul AzizBERSATU · PNTanah MerahEN

I suggest that this surcharge be imposed on all who have failed to carry out the duties entrusted to them, especially all members of the PMC. At the same time, the LAD penalty must be enforced against LUNAS without compromise. Second, this is the last one. Limit, limit the construction of LCS to only three ships. LCS 1 to 3, there is no need to build a fourth or fifth LCS. Cancel the construction of the fourth and fifth LCS. Until now, the government has paid RM8.3 billion to LUNAS. However, not a single ship has been officially handed over for commissioning by TLDM.

Tuan Mohd Sany bin HamzanAMANAH · PHHulu LangatEN

Tanah Merah. Tanah Merah. Can you give a little, Tanah Merah? I want to ask for a suggestion from Tanah Merah. Can Tanah Merah accept if on this LCS issue we ask the government to set up a Royal Commission of Inquiry to investigate matters relating to these LCS ships?

Hulu Langat, Hulu Langat.

Tuan Mohd Sany bin HamzanAMANAH · PHHulu LangatEN

Because I recall that we once had submarines, but the submarines could not dive. We had jets, jets that could not

Tuan Mohd Sany bin HamzanAMANAH · PHHulu LangatEN

fly. This one, meanwhile, the LCS was supposed to be completed in 2013. The original project was supposed to be completed in 2023. [Microphone switched off]

Hulu Langat, that's already too much. The point, we have got the point. Do you agree or not to a RCI?

Beberapa AhliKetawa] Dato’ Haji Tajuddin Abdul Rahman [Pasir Salak

Setuju.

Dato’ Sri Ikmal Hisham bin Abdul AzizBERSATU · PNTanah MerahEN

[Speaking without a microphone] I agree that an RCI should be set up.

Okay, press, press, press.

Dato’ Sri Ikmal Hisham bin Abdul AzizBERSATU · PNTanah MerahEN

I agree with part of the proposal, not all of it, I agree with some of it.

Time is almost up now.

Perenggan terakhir, I think the last one minute.

Okey.

Dato’ Sri Ikmal Hisham bin Abdul AzizBERSATU · PNTanah MerahEN

Okay, thank you, Mr Speaker. Until now, the government has paid RM8.3 billion to LUNAS. However, not a single ship has been officially handed over for commissioning. The remaining savings from the RM11.2 billion ceiling should be immediately redirected to increase the procurement of the number of Coastal Mission Ships (LMS), Batch 2 Ada-class, which are currently being built by the company STM in Turkiye. Given that the procurement of NSM faces export licence issues and MINDEF has had to switch to the Exocet MM40 Block 3c, it is more rational and economical for TLDM to focus its surface combat assets through the Corvette LMS Ada-class, which has proven its ability to be built according to schedule. Do not make the urgent needs of TLDM a shield for the government to keep pampering LUNAS. Three LCS ships are enough, and redirect the remaining funds to assets that can truly be completed and delivered on time for the sake of the sovereignty of the nation's waters. Mr Speaker, I beg to propose. Thank you.

Beberapa AhliKetawa] Dato’ Haji Tajuddin Abdul Rahman [Pasir Salak

Setuju.

I think I beg to second. Thank you, the Honourable Tanah Merah.

Tuan Chong ZheminDAP · PHKamparEN

Already became a Minister.

I now invite the Honourable Kampar. Five minutes, Honourable Member.

Tuan Chong ZheminDAP · PHKamparEN

Thank you, Deputy Speaker. Thank you for giving Kampar the opportunity to debate the Auditor General's Report 2/2026. I will go straight to my first point. The Littoral Combat Ship (LCS). As of 25 June 2026, cumulative payments under the main contract have reached RM8.557 billion. Overall physical progress is 78.99 percent against a target of 86.54 percent, which is delayed by 7.55 percent. LCS 1 itself is 108 days late. The original handover on 26 August could not be achieved. The December 2026 target is also at risk of failing. In fact, the report records the contractor's proposal to shift the physical handover to 19 April 2027. The date keeps being changed. So, who will bear the consequences? The TLDM personnel who need assets to defend the nation, and the people who are financing this project. I want to raise this from Free Malaysia Today. It was reported: "LCS 1 may not be fully operational until 2035". This means the LCS will not have full battle operational capability until 2035. But why did the ministry accept the LCS before we have full operational capability? We order an LCS, Deputy Speaker. We are not ordering a Titanic. We want a ship that can fight in war, not a ship that can only carry passengers. What is more worrying is that physical delivery does not necessarily mean the ship has reached full combat capability. We find that the training audit and weapons systems are not yet complete, with five complete contract procurements determining the ship's readiness. This is a risk scenario raised by the audit. So, I hope the government must present an exit plan that can be proven with the suppliers, with a clear cost schedule. The project that was approved is not one approved yesterday or five years ago. This project was approved in 2011. If full capability is only achieved in 2035, this means 24 years after this project was approved, at that time approved by Bagan Datuk. How many technological changes and security threats will occur during this period, 24 years. We are buying ships to face current threats, will we ultimately receive a capability planned yesterday when the threats have already changed tomorrow.

Tuan Chong ZheminDAP · PHKamparEN

Deputy Speaker, we want an LCS combat ship but we will receive a Titanic, impressive in appearance and name but without the full combat capability that was promised. The people are paying for a ship that can defend the nation. Combat capability must be the measure of the success of this project. I want to ask the Minister of Defence. If the training and weapons systems are still incomplete, on what grounds can the ministry accept the handover of the ship. Why is the physical handover to proceed before combat capability has been achieved. And in this issue, the political responsibility of Bagan Datoh must be answered, because at the time of 2010...

Tuan Mohd Sany bin HamzanAMANAH · PHHulu LangatEN

Can Kampar give a little, Kampar?

Tuan Chong ZheminDAP · PHKamparEN

Let me finish first. In 2010/2011 he held the post of Minister of Defence when the initial procurement decisions were made. The letter from Boustead Naval Shipyard dated 8 July 2010, disclosed in the previous investigation report, contains his notation, "SUB procurement please implement". That instruction is part of the record of his involvement. Therefore, he must explain the decisions and oversight under his administration and how the interests of TLDM and the people's money were protected. I want to ask Bagan Datoh. What responsibility did he take for the initial decisions of this project? What lessons did he acknowledge from the prolonged failure? In 2010, please implement. In 2026, the people are still asking when we will get an LCS that has full combat capability. I demand an explanation of his political and administrative responsibility based on the records. If the investigation finds evidence of wrongdoing by any party, action must be taken regardless of position or party. The Minister responsible for defence bears responsibility for the decisions of his ministry. So the people must know whether these possibilities have protected the national interest. Let us look at the figures...

Tuan Mohd Sany bin HamzanAMANAH · PHHulu Langat

YB Kampar.

Tuan Chong ZheminDAP · PHKamparEN

One more paragraph to finish.

YB Kampar, nearly finished, time is almost up now.

Tuan Chong ZheminDAP · PHKamparEN

Yes. The audit report records that the original contract was worth RM9.128 billion, involving six LCS ships. After restructuring, the value increased to RM11.22 billion for five ships. This

Tuan Chong ZheminDAP · PHKamparEN

means the price has increased by RM2 billion but the number of ships has decreased by one, one ship. So, the people are paying more money but getting fewer ships. If we want to investigate this, what happened is already clear. There was indeed money that has been, has been misappropriated. So, I want to know, from 2011 until today, many administrations have changed, but why has the MACC or SPRM still not carried out any investigation to date. If we are to investigate this properly, I think five years back. This case, we've already wrapped it up.

Tuan Mohd Sany bin HamzanAMANAH · PHHulu LangatEN

It seems you don't want to let Kampar speak.

Tuan Chong ZheminDAP · PHKamparEN

So, I hope the MACC can investigate transparently because this money has been paid over RM2 billion, and there is one ship less.

Kampar.

Tuan Chong ZheminDAP · PHKamparEN

I think a commission must be set up.

Kampar, time is up.

Tuan Mohd Sany bin HamzanAMANAH · PHHulu LangatEN

Let Kampar give way to me, Deputy Speaker. Can I?

Yes, yes, you can.

Tuan Mohd Sany bin HamzanAMANAH · PHHulu LangatEN

It was supposed to be completed in 2023. It began in 2013 and the government has already paid almost RM8 billion. But until now we see not a single ship has been completed, one that can sail. Yet this is an aspect related to national security and the issue of national sovereignty. On this matter we cannot compromise. But I want to ask Kampar, is there, is there, is there an element of sakau over there? Sakau, sakau. Is there an element of stealing, robbery, sweeping up, or embezzling the people's money in our country? If there is, does Kampar agree with me that we set up a Royal Commission of Inquiry to investigate this LCS issue. The people's money in our country has been sacrificed. Thank you, Speaker. Thank you, Kampar.

Tuan Chong ZheminDAP · PHKamparEN

I think this is clear because now we have to pay over RM2 billion more. Over RM2 billion more for six ships, and we're left with one ship. If this isn't sakau, I don't know what sakau is.

Okay Kampar, time is up.

Tuan Chong ZheminDAP · PHKamparEN

I agree with Hulu Langat. We must set up a Royal Commission to investigate down to the very last detail.

Okay Kampar, time is up. Thank you. I now invite the Honourable Kuala Terengganu. Five minutes, Honourable Member.

In the name of Allah, the Most Gracious, the Most Merciful. Peace be upon you, greetings of peace. Thank you, Mr Speaker.

I would like, er, to bring up an issue that is close to the people of Terengganu, namely the Kuala Nerus Coastal Erosion Control Project. I am raising this matter on the basis of public safety. This project is worth around RM70 million and involves the construction of breakwater structures as well as beach reclamation work. However, the Auditor General's Report found that this project is experiencing a delay of 144 days. This delay involves breakwater number seven and number eight. Both of these structures are related to the protection of the road connecting Mengabang Telipot – Batu Rakit. The road had previously been damaged by erosion and required repair work. In Terengganu, every year when the monsoon season arrives, we face severe coastal erosion. Any failure to implement the project according to the specified schedule will result in the protection not being provided in time. According to the report, as long as the protective structures are not yet completed, the road that has been repaired, before it has been protected, will be damaged again. Mr Speaker, this is not merely a question of a project being delayed. This is a matter of risk management and public safety. If the road is already damaged due to erosion, then we repair the road, but the coastal protection is still not complete, then it is wasteful. It will cause the damage to repeat over and over. We are getting closer to the Northeast Monsoon, and if more serious erosion occurs, we will face not only the risk and damage to infrastructure, but also disruption to transport links and the safety of road users. My question is, when are both expected to be completed and provide the necessary protection? And if they cannot be fully completed before the monsoon season,

what temporary measures have been prepared to protect the road and the safety of users? Mr Speaker, I would also like to chip in on this LCS issue. I saw pictures that supposedly show this ship is already complete. I was once involved in the field of shipbuilding.

This is a ship expert. [Speaking without a microphone]

I looked at the ship that has been completed. I looked at its walls, its plating, and the side sections. If it were a new ship, it would be straight. This is like a ship that has just come back from war, with its sides wrinkled. So, apart from the question of completion, the matter of quality and quality monitoring must be looked at. This issue cannot be viewed merely as a delayed project. This is a national defence project involving a large amount of public allocation. Over and over again, for years, we have been talking about the same thing. Gentlemen, we must distinguish two things: a ship that is ready for handover and a ship that is ready for use. These are two different things. How is the progress scheduled? Is it according to the requirement that the ship can be used, or merely so that the contractor can reach the progress payment milestone? That is one matter that must be looked at. LKAN identified problems relating to several complementary contracts, including logistics support, missile systems, cannon ammunition and defence systems, for the Integrated Logistics Support and Trial Aids (ILS-TA) contract. Its value exceeds RM500 million. As at the audit date, the contract could still be finalised, and its physical progress was around 30 per cent, compared with a target of around 37 per cent. I note that there were developments after the audit date and that the contract was signed in August 2026. So my question is: what is the latest status of all the related complementary contracts, and what is still needed before LCS 1 can operate as stipulated? Mr Speaker, the Auditor General's Report shows that the full readiness of this project depends on complementary contracts which, based on audit findings, are projected to be completed only by December 2035, whereas the main contract ends in April 2030. If this gap exists, it is no longer merely a delayed project issue. It shows that there is a question that

major in terms of the overall coordination of this project. That is why I support the National Audit Department's recommendation that the Ministry prepare a realistic recovery plan and ensure that the critical works under the main contract and the complementary contracts are coordinated with the ship's delivery schedule.

[Bangun]

Sila.

Dato’ Sri Ikmal Hisham bin Abdul AzizBERSATU · PNTanah MerahEN

Okay. Kuala Terengganu, so Kuala Terengganu, I too— I think Kuala Terengganu can agree. I think the Hulu Langat RCI proposal is indeed good. Does Kuala Terengganu support it? And our ship, this ship of ours, is not only the most expensive, but also the slowest to be completed. Even for me, as a ship expert, as he said just now, as Kuala Terengganu said just now, that ship's wall— So, what is the effect on— This is a new ship, this is not a second-hand ship. Give comments.

Tuan Mohd Sany bin HamzanAMANAH · PHHulu LangatEN

Tanah Merah, can Tanah Merah add a little, Tanah Merah? The year 2013 first. The government in power at the federal level at that time was the DAP government, the DAP government. 2013 was a DAP government. It was the government at that time. Thank you.

He did not ask my permission, he cross me [Unclear].

Dato’ Sri Ikmal Hisham bin Abdul AzizBERSATU · PNTanah MerahEN

Hulu Langat, this ship was supposed to be completed not in 2013, but actually in 2019, not 2013. Mr Speaker... [Loudspeaker switched off]

Done? Okay. Wait, press again. Time is up. Whether you agree or not with that proposal, then can already...

I will finish.

Okey.

I will finish completely. It involves the public, a large amount, and questions that have been raised for years. People are wondering what it is. Therefore, I agree. We need to conduct a thorough investigation into

this matter. If a Royal Commission is needed, set up a Royal Commission. The people need an explanation regarding these public funds. That concludes my speech. Thank you.

Thank you, Honourable Kuala Terengganu. [Applause] Next, I invite the Honourable Putatan. Five minutes, Honourable Member.

Thank you, Mr Speaker. I give way to Rasah briefly.

Tuan Cha Kee ChinDAP · PHRasahEN

Honourable Member. Thank you to Honourable Putatan. Dato' Speaker, I seek permission to welcome the visiting delegation of principals, teachers and students from Sekolah Menengah Kebangsaan (SMK) Seremban 3 from the Rasah Parliamentary constituency. Welcome, everyone.

Okay, welcome.

Tuan Cha Kee ChinDAP · PHRasahEN

Thank you, Honourable Putatan. Thank you, Speaker.

Welcome. For this debate, Putatan wishes to raise the matter of the management of the Littoral Combat Ship project, or LCS for short. Putatan wishes to begin the debate with one question: what considerations did the government make that led to the change of the surface-to-surface missile, abbreviated SSM, to the Naval Strike Missile type in November 2017? That change was the beginning of the episodes of confusion that have plagued the LCS project until today. Speaking of the Naval Strike Missile, we certainly cannot escape questioning the decision of the supplier company from Norway. The sudden decision communicated to Malaysia on 4 February this year led to the permanent cancellation of the export permit by the Government of Norway. That permanent cancellation of the permit has had a domino effect on the progress of LCS 1. Based on Schedule 3 regarding the physical handover target of the LCS, the physical handover contract for LCS 1, which was set for 26 August 2026, needs to be postponed to December 2026 due to delay factors. The cancellation of the export permit, which was finalised in April this year, will certainly affect the extension period for completing LCS 1. The crisis

has resulted in a gap in the construction of LCS 1, given that the SSM or Naval Strike Missile is the main weapon system in the construction of a warship. By analogy, the absence of the Naval Strike Missile in the construction of LCS 1 is like the absence of a striker in a football team. How could a Royal Malaysian Navy (TLDM) warship not equipped with the Naval Strike Missile carry out a counter-strike against intrusion from external elements? Although bitter to swallow, the Ministry of Defence (MINDEF) should already have started proactive steps to find a replacement for the Norwegian supplier company. The replacement must be a highly credible supplier from any country that has good diplomatic relations with Malaysia. The imbroglio surrounding the Naval Strike Missile supply agreement must serve as a guide for MINDEF

in entering into any agreement relating to the supply of military equipment more carefully. From Putatan's perspective, the dispute involving MINDEF and the Norwegian supplier company is a dark tragedy in the nation's diplomatic history. The contractual dispute has plunged the nation into financial loss. The sum of EUR124.35 million that the government has spent has lost all meaning after the Government of Norway cancelled the export permit. Even more unfortunate, the claim of EUR214.66 million submitted to the Norwegian supplier was rejected. The rejection of that claim is a gesture that reflects their barbarity and careless attitude towards Malaysia as their client. If it is not resolved through a harmonious diplomatic approach, the dispute over the claim will not be settled within the expected period. Putatan is of the view that the imbroglio must be resolved in the spirit of diplomacy, through a government-to-government approach. Wisma Putra must also play a role as a peacemaking bridge that can bring MINDEF and the Government of Norway to one negotiating table. The dispute regarding the claim must be resolved in the spirit

of security diplomacy. Diplomacy must be forged with the objective of completing the construction of LCS 1 according to plan, using the claim money that is returned. To conclude the debate, Putatan wishes to put forward one question for our reflection, Honourable Members. Who is the unseen voice that whispered to Norway to block the export of surface-to-surface missiles to Malaysia? What hidden agenda lies behind that plot? Mr Speaker, that concludes my debate. Thank you.

Thank you, Honourable Putatan. Next, I invite the Honourable Lumut as the next debater. Five minutes, Honourable Member.

Thank you, Mr Speaker. Bismillahirrahmanirrahim. I wish to debate the Auditor General's Report on the management of the LCS project. I stand to raise a question that is no longer merely about the construction of ships. The LCS issue is an issue of the credibility of national defence procurement, the people's money and the readiness of the Royal Malaysian Navy (TLDM). We must ask frankly how a project that should strengthen the TLDM fleet can face delays, cost increases and changes in implementation, to the point of raising major questions for the people. Mr Speaker, I do not dispute the nation's need to possess modern warships. Rather, I support efforts to strengthen the TLDM in developing its capability, where the 15-to-5 Transformation Plan, with permission, sets out to reduce 15 ship classes to five ship classes, including 12 LCS with four-dimensional warfare capability. However, support for the TLDM does not mean we should remain silent about weaknesses in project management. The first question is cost. The people want to know what the actual amount spent is. How much more is needed to complete the whole ship? And what is the guarantee that this project will not keep becoming one that requires additional allocations without end? We cannot build warships with a cost-first, accountability-later approach.

Mr Speaker, the LCS should be the backbone of the TLDM fleet. But every year of delay means something. The TLDM keeps waiting for new assets, while maritime security threats do not wait. The South China Sea does not wait, the Straits of Malacca do not wait. Territorial disputes and Malaysia's maritime economic interests also do not wait. So I want to ask the ministry: what is the actual date on which the LCS will be handed over to the TLDM, and what is the mechanism for penalties or action should the contractor once again fail to meet the set schedule? Mr Speaker, a warship is not merely a hull. What determines its strategic value is the combat system, radar, sensors, warfare systems, missiles, air defence, sonar and the integration of the whole ship. We do not want to own a beautiful warship that lacks combat capability matching the real threat. One very important matter is the anti-ship weapons system. The LCS is built as a modern warship. We need to ensure it has truly credible surface strike capability. I want the government to answer clearly: what is the status of the compensation claim for breach of contract against the firm Kongsberg Defence & Aerospace? What is the status and direction of planning for the replacement of the anti-ship system? How much is the cost increase for the new anti-ship replacement, and the cost of rework and reintegration works, with permission? Because for me, a warship without armament that meets the operational concept is like owning a sword without a sharp edge. Mr Speaker, the TLDM needs ships, a sufficient number of ships to carry out patrol duties, escort and surveillance, surface warfare and operations in the maritime area. If the LCS is delayed, the capability gap must be borne by existing assets. The question is, what is the effect of the LCS delay on the TLDM's current readiness level? And how much longer must existing ships have their operational lives extended to fill that gap? Mr Speaker, we must view this issue as a major lesson in national defence procurement management. We cannot merely look for who is at fault after a project runs into trouble. We must build a management system that prevents the problem from occurring. I propose that the Ministry of Defence strengthen the milestone-

based payments, regular technical and financial audits, independent oversight of project progress, contractor risk assessment, transparency on specification changes, truly effective penalty mechanisms and periodic reports to Parliament on the progress of strategic defence projects. The people want ships that can truly sail, operate or fight when the nation needs them. Let us not end up with a ship that is expensive but late, a ship that is completed but not fully armed, or a ship that is fully equipped but lacks the operational capability the TLDM needs. In conclusion, I recommend and urge that the government establish a Royal Commission of Inquiry to investigate thoroughly, given that the PAC Report from the previous government's era confirmed that there were leakages and recommended that prosecution be carried out immediately.

Tuan Mohd Sany bin HamzanAMANAH · PHHulu LangatEN

Lumut, Lumut, Lumut, can you spare a little, Lumut?

13 seconds only.

Tuan Mohd Sany bin HamzanAMANAH · PHHulu LangatEN

Lumut agrees with me that a Royal Commission of Inquiry should be set up, right Lumut?

Tuan Mohd Sany bin HamzanAMANAH · PHHulu LangatEN

But the problem is, when we table the Royal Commission of Inquiry Report relating to Tabung Haji, over there they walk out of the House! That is the problem!

Tuan Haji Kamal bin AshaariPAS · PNKuala KrauEN

Eh, that's wrong, that fact.

Tuan Mohd Sany bin HamzanAMANAH · PHHulu LangatEN

Agree, saying agree, but walk out of the House! All of that walks out of the House. This one speaks like a snake!

Tuan Haji Kamal bin AshaariPAS · PNKuala KrauEN

That day was not the Tabung Haji RCI...

Tuan Mohd Sany bin HamzanAMANAH · PHHulu LangatEN

The one who twists all of this is the one on that side who says that.

Eh, do you understand language?

Tuan Haji Kamal bin AshaariPAS · PNKuala KrauEN

...Only the Minister's explanation.

Enough, enough, enough. Enough, enough.

That's all, thank you. Thank you, Mr Speaker.

Continue, Lumut. Ha, is that all?

Okay, thank you, Honourable Lumut. Next, I invite the Honourable Rasah.

Tuan Cha Kee ChinDAP · PHRasahEN

Thank you, Mr Speaker, for the opportunity given to me to take part in debating the Auditor General's Report Series 2/2026 today. I also thank the Malaysian MADANI Government led by the Most Honourable PMX. This once again proves that the Malaysian MADANI Government keeps its promise on institutional reform. In the past, the Auditor General's Report was merely stated, and the report tabled was only placed on the table. Now it is open to be debated, including by Honourable Members from both sides, who may give their views, criticisms and suggestions, and which must then be wound up and answered by the government. This is genuine institutional reform, which we hope will prevent our national institutions from being continuously manipulated by certain parties. I see that this report mostly revolves around two ministries: the Ministry of Works (KKR) and the Ministry of Rural and Regional Development (PETRA). Although the project involved, for example under KKR, is Pan Borneo, which has nothing to do with my area, I take note, or rather take seriously, the recommendations from the audit report, namely the seven audit recommendations under pages 1/61 and 1/62. Regarding the five recommendations from the Auditor General's Report: firstly, the issue of site preparation and utility relocation that takes a long time, causing delays to this project. Secondly, document review to ensure compliance before finalisation. The recommendation of the Auditor General's Report is that clear limits of authority should be given to all entities so that they do not exceed the powers they have. 7.3, implementation of the recovery plan must be monitored continuously.

Tuan Cha Kee ChinDAP · PHRasahEN

7.4, monitoring of the whole project through the project information system. If an extension of time is given, the underlying basis is value for money, the best value for money.

Tuan Cha Kee ChinDAP · PHRasahEN

And the fifth, 7.5 — improve the existing standard operating procedures, or SOPs, to avoid financial or legal implications for government agencies. I note that these five matters are general, general matters for project implementation. This is because, in my area, a project to upgrade Jalan Labu to Persimpangan Gateway, 2.7 kilometres long, is taking place or being implemented, costing half a billion, or RM500 million. I see there are delays. Perhaps the Honourable Minister who— I thank the Honourable Minister who attended in person to hear the debate himself and can make a decision or respond afterwards. So, why is there a delay on the ground? I am not sure. Perhaps when replying, the Honourable Minister can give some comment on this matter. The second matter, the second ministry involved, concerns PETRA, relating to the management of the Integrated River Basin Development Project (PLSB) Sungai Golok. That is in Kelantan. But, coincidentally, in my area, in the Rasah Parliamentary constituency, there is also the Sungai Linggi Phase 5 Integrated River Basin Development Project (PLSB), which started earlier and is expected to continue. The delay in that project was caused by the previous government's failure to implement it. It only began to be implemented under the Malaysian MADANI Government led by the Most Honourable PMX. I see that the audit recommendations are four matters, at pages 3-29 and 3-30, concerning several issues that need to be taken seriously by the agency concerned to avoid continued delay. So I request PETRA, when winding up later, to give the latest status of the PLSB Sungai Linggi Phase 5 project to me as Member of Parliament for that area. For this audit report, Mr Speaker, I think our Audit Act allows the National Audit Department to take more proactive steps towards agencies or bodies, not only government agencies but bodies that collect many fees, charges or royalties from the public.

Tuan Cha Kee ChinDAP · PHRasahEN

I have given three examples this afternoon. The first is MyEG. The Honourable Minister of Transport only announced two days ago how MyEG failed to pay collections that should have been paid to the government. So, can the National Audit Department (JAN) step in to take action against MyEG, expose who is behind it, who the mastermind behind it is? That is the first. Second, the Legal Profession Qualifying Board (LPQB), which we know administers the CLP examination. It has been mentioned repeatedly, where is the audit? Because it collects millions every year. So, what is the status? I am informed there is one, but is there really one? Perhaps the government can inform us later. And finally, the three collective management organisations (CMOs) that I can name here, MACP, PPM and RPM, which collect fees, levies and also royalties from many private premises. Where, MyIPO, yes, the Intellectual Property Corporation of Malaysia (MyIPO) has no power to monitor, for one, the collection formula. I had engagement with MyIPO only yesterday evening as Chairman of the Select Committee. It has no power. So, how do we control these three companies, these three entities? So, in my view, can the Auditor General's Department step in? First, to find out how the formula works. And second, want to know how much has been collected and how that money is channelled to the rightful parties such as songwriters, singers, lyricists and so on. So, I humbly ask the National Audit Department to do its best to ensure that our country, where public funds and funds touching the interests of the people are always monitored in the best possible condition, to prevent leakage and also sakau activities from continuing in our country. Thank you to Mr Speaker.

Thank you, Honourable Member. Not Dato' yet. Alright. Next, I invite the Honourable Parit. Five minutes, Honourable Member.

Bismillahirrahmanirrahim. Assalamualaikum warahmatullahi wabarakatuh and good afternoon. Thank you, Mr Speaker. I also extend my heartfelt thanks to the Auditor General and all officers of the National Audit Department who have worked tirelessly to complete this report.

Allow me to begin the debate by mentioning the Programme Perumahan Rakyat (PPR) project, namely 67 units of houses in Kampung Selagon in Beaufort, Sabah. These Programme Perumahan Rakyat houses were completed in 2017 and the defect liability period ended in 2019. Up to July 2026, which is nine years later, no one has occupied them because the land beneath them is alleged to be moving. The repair contract of RM2.72 million was also terminated in March 2025 with progress at only 15 per cent. Herein lies the question today. The 2025 Financial Statements received an unqualified audit opinion. But, Selagon, public money has been spent while the people have not received its benefits. An unqualified opinion means the figures reported are true and fair. It does not mean the expenditure was prudent. I seek clarification on this issue. Related to money that has not been returned. Accounts receivable stood at RM102.032 billion in 2025. In 2025, RM1.22 billion was written off. Seventy-five per cent of it is more than six years old. Recoverable loan arrears amounted to RM8.084 billion but annual collections were only RM0.46 billion, which is only five per cent. Sixty-six loans worth RM4.637 billion have never been repaid. Indah Water owes RM3.338 billion and KTMB owes RM867.76 million. Meanwhile, NFC, National Feedlot Corporation, has not paid anything since 2014. Restructuring has been repeated up to five times whereas the guidelines should only allow two times within an extended period of up to 40 years. Mr Speaker, regarding the principle of legality, the Marine Department has paid RM2.55 million in allowances from two trust accounts without legal authority. The Chairman allowance of KWPPL was increased from RM1,500 to RM5,611 a month, which is the committee itself. That is public money. No one should be able to determine payments from it without valid authority. Regarding RMK12 and LCS. Of 9,578 RMK12 projects, only 32.6 per cent are completed and 2,208 projects are still at the pre-implementation stage even though the plan has ended. A year ago, the Auditor General's Report (LKAN) reported the RM100 million project in Tawau as troubled, and a year later the audit found no progress. The Galeria Perdana Langkawi also rose from RM20 million to RM56 million.

The LCS project is more serious. As we are well aware, the original contract was RM9.128 billion for six ships. Now it has become RM11.227 billion for only five ships and the average cost per ship has risen by nearly 48 per cent. RM8.557 billion has been paid. Progress is behind by 7.55 per cent, equivalent to delayed work of approximately RM844 million and the gap is widening. The delivery date for the LCS was supposed to be 26 August 2026. It has already passed. Missiles that have been paid for amounting to EUR124.35 million cannot be shipped because their export licence is reportedly suspended. And one very shocking matter, it turns out the audit estimates that the fully capable ship will only be delivered to us in December 2035. Who bears the consequences of this delay if not us as taxpayers? Mr Speaker, neat figures on paper do not have the same value as their function. A house that can be lived in at Kampung Selagon, Beaufort, or a ship that can be used for war, that money is a trust and the trust will be questioned, whether in this world or in the hereafter.

Accordingly, I seek clarification on all the questions that I have raised just now. Thank you.

Thank you, Honourable Parit. Next, I invite the Honourable Pasir Gudang. Five minutes, Honourable Member.

Tuan Hassan bin Abdul KarimPKR · PHPasir GudangEN

Thank you, Mr Speaker. Assalamualaikum and peace be upon you. I want to debate a very important issue in the Auditor General's Report Series 2/2026. Namely, regarding the debt of the Federal Government. In the report it is recorded that the debt of the Federal Government has risen by 5.9 per cent in the past year. And the debt of the Federal Government now totals RM1.321 trillion. We don't say billion anymore, now it is trillion. Mr Speaker, I observe that previous governments up until the current Federal Government are quite skilled at borrowing. But this Federal Government is not good at collecting debts. To recover debts, it is not good. What is the evidence? In the Auditor General's Report, billions of ringgit in debts owed by many parties to the Federal Government have not been paid.

Tuan Hassan bin Abdul KarimPKR · PHPasir GudangEN

Last year, out of the total RM9.273 billion in debts owed to the Federal Government, the Ministry of Finance only managed to collect five per cent. Billions are still not collected, some have reached 40 years, the debts keep on and on. So, the Auditor General's Report reveals that the debt collection system, collection of debts by the Federal Government, has failed. In matters of large debts, at the same time, debt collection is very weak. I ask the government, please do not bail out, do not rescue GLCs, GLICs, government companies that are making losses. Please don't. That is, because our debt is too high. And at the same time, my appeal, I ask the government not to use taxpayers' money to bail out private companies, not government companies, if there are private companies. For example, I have been told, there is a big company, our national airline with the slogan "Everyone Can Fly". I do not want to mention the full name of the company. The short-term debt of this company is RM18.4 billion and this company has recorded quarterly losses reaching RM830 million. So, if this company knocks on the door of the Ministry of Finance, asking the government for help, I hope the government will refuse. Because the government is in debt. Although this company is important, this private company is important, but I am informed that its taukes, its shareholders, have assets worth billions. So, let them rescue their own company, the government has other business. And finally, I also want to mention our warships, the LCS. I— it has been mentioned by my colleagues earlier, I am also puzzled. How can this government operate like this? First, the contract with the LCS was for six ships. The total was RM9.128 billion. But in the end, there was a supplementary contract that changed it to five ships, fewer. So, five ships but the total increased to RM11.227 billion. Is this wisdom or what kind of mathematics is this? Fewer ships acquired, the debt grows larger. This, Minister of Defence, eh, look. Then, finally, Mr Speaker, regarding this LCS issue. I see this issue is big. Just like the issues of Tabung Haji, FELDA and 1MDB. There were proposals from several Members of Parliament earlier, for a Royal Commission of Inquiry (RCI) to be set up. But I see that this RCI has a weakness, it is slow and cumbersome. I see in this ship issue that began in 2013. The LCS, we use a fast track, investigate directly. MACC, police, Inland Revenue Board, investigate directly. Investigate from— in

Tuan Hassan bin Abdul KarimPKR · PHPasir GudangEN

13 years— from 2013 until 2026, 13 years, five times the government has changed and five Ministers of Defence. In that 13-year period, I do not know how many Secretaries-General (KSU) were involved in this procurement. So ultimately, Mr Speaker, do not just investigate the generals, drag them to court, charge them. So far, the Chief of Army was dragged to court, the Chief of Defence Force was dragged to court. And I see that the five Ministers of Defence from before until now and these KSUs are not infallible, not angels, investigate them. [Applause] Investigate them, bring them to court, then we will know. This RCI is slow and cumbersome. Important at times but swift action— I have lost my patience, Mr Speaker. That's all, thank you.

Thank you, Honourable Pasir Gudang. Next, I invite the Honourable Kota Bharu. Five minutes, Honourable Member.

Assalamualaikum. Peace be upon you. Thank you, Honourable Member, Mr Speaker. I am also able to debate this Auditor General's Report Series 2/2026. The first point I would like to touch on is regarding performance auditing, which is one of the core functions of the National Audit Department introduced following the implementation of the Program and Performance Budgeting System up until the Audit Act was amended in 1978. Honourable Mr Speaker, I want to raise in the Auditor General's Report Series 2/2026, I find that the number of performance audit reports tabled in this House has been somewhat decreasing, compared with 2023 and the years before that. My question, has there been any change to the KPIs of Auditors after 2023 such that performance auditing is no longer given priority or in fact performance auditing is still carried out but is no longer reported in this Auditor General's Report? If there is indeed a reduction, what is the justification of the JAN? Whereas performance auditing is a main instrument for assessing the effectiveness

of public expenditure, particularly when the government allocates increasingly large funds every year. Mr Speaker, the second point I would like to touch on is regarding the auditing of government companies and also the e-SelfAudit system. I understand that the audit by the Auditor General's Department under section 51(d), Audit Act 1957 focuses more on aspects of governance and management of government companies and not on auditing financial statements. Because financial statements are audited by external auditors. The question I want to raise. Why is the report on the auditing of these companies, namely, no longer tabled in this Auditor General's Report this time? And how many government company audits have been completed by the National Audit Department for the current year? And of that total, how many were ultimately reported to this Dewan Rakyat? Likewise I would like to touch on— I would like to get an explanation regarding the use of the system called e-SelfAudit. What exactly is meant when a company is subject to or said to have been audited through this e-SelfAudit system?

Is information that is only filled in by the company itself in the system, but can be verified and validated through field inspection by JAN auditors, considered to have been fully audited? These are the questions that I feel need to be explained by the Auditor General's Department when using this e-SelfAudit system. Next, I would like to touch on the auditing of Malaysian representative offices overseas and also the auditing of the government companies I mentioned earlier. Based on the audit scope report, the audit of overseas representative offices focuses on aspects of governance and financial management. However, when I examined the audit findings, most of the issues raised involve matters such as vacant posts, delays, allocation of provisions, surprise inspections not carried out, weaknesses in maintaining the register cards, stock and some operational weaknesses which in my opinion are more of daily administration only. My question is, are not issues like these normally within the scope of action of the internal audit unit

in each ministry or agency to be rectified, and not at the level of the Auditor General's Department, which needs to focus on these matters? I am not disputing the importance of the issue but I would like the views of the National Audit Department on whether the report to Parliament should focus more on issues that have strategic and national impact. Therefore, surely the hope of our people and also the hope of this House is that more significant analysis be given, for example— what I mentioned earlier, management of strategic government companies at national level such as Khazanah Nasional, Permodalan Nasional Berhad (PNB), TEKUN Nasional, government-linked companies that manage large-scale public funds need to be given focus by the National Audit Department. And lastly, I would also like to obtain an explanation from the Auditor General's Department regarding the auditing of Tabung Haji after the asset restructuring process implemented in 2008. What were the audit findings related to Urusharta Jamaah Sdn. Bhd. (UJSB)? This will be given focus by the National Audit Department after audits were carried out in 2017 and after 2018. What was the scope of that audit and what— if any, what is the audit scope that is to be carried out? What is the main finding to be obtained and what improvement recommendations have been submitted so far to Tabung Haji? What will be continued in the times to come? So, I want an explanation on this matter. Thank you, Mr Speaker.

Thank you, Honourable Kota Bharu. Next, I invite the Honourable Betong.

Peace be upon you and thank you, Mr Speaker. Betong wishes to take part in the debate on the Auditor General's Report 2/2026 with one basic question. Is every ringgit of public money spent truly traceable, accountable and beneficial to the people? Betong appreciates the improving fiscal position of the government. Federal Government revenue for 2025 increased to RM336.069 billion, while the deficit decreased to RM75.288 billion or 3.7 per cent of

GDP compared with 4.1 per cent previously. However, in my view fiscal discipline must go hand in hand with governance discipline. Betong's first question concerns recoverable loans. At the end of 2025, arrears of repayment totalled RM8.084 billion. Of that amount, there are 66 loans worth RM4.637 billion that have never been repaid since the repayment schedule took effect. More worrying, Mr Speaker, there are 39 loans worth RM4.766 billion that have passed their repayment period, some even up to 42 years, but have still not been fully collected. So, Betong wants to ask the government why this matter has dragged on for so long? What monitoring and enforcement system is being used? Betong understands that restructuring is sometimes necessary to help loans. But when a loan is restructured up to five times with the repayment period extended up to 40 years, what measure is used to ensure it is truly a recovery step and not merely postponing the problem? Mr Speaker, the second question concerns legal authority. The audit found that RM2.55 million in allowances and facilities were paid using the Dius Api Fund and the Sea Trading Centre Fund without proper legal authority. The question is, how can payments be made without proper legal authority? Will the government carry out a review of trust accounts and other government funds so that the same matter does not recur? For me, the amount of RM2.55 million is not the main issue but the principle is what matters. In the management of public money, every payment must have a clear legal authority. Mr Speaker, the third question concerns contractors' advance payments. The audit found that RM68.1 million can still be collected across the five ministries examined. Of that amount, RM59.63 million or 86.7 per cent is more than 10 years old. Betong wants to ask why this money has been in arrears for so long? Does the government have an early warning system so that collection problems are identified earlier and not only acted upon after the debt has become too old? Mr Speaker, in my view the approach needs to change from only collecting after a problem occurs to early warning and immediate collection. Mr Speaker, the same matter needs to be examined in the implementation of development projects. Of 9,578 RMK12 development projects, only 3,120

projects, or 32.6 per cent, are at the post-implementation stage as of 31 December 2025. Betong does not say that all unfinished projects have failed, but the question is simple. What are we actually measuring? How much money has been spent, or how many benefits have the people out there received? So for the people, a project is only successful when it is completed, functioning and can be used. This is very important for Sarawak in particular, because projects such as the Sabah–Sarawak Link Road Fasa 2 and the Lebuhraya Trans Borneo are not merely figures in a report. They concern connectivity, safety, trade and also the economic opportunities of the people. So, a delayed project means the people wait longer. A delayed road means economic opportunities are also delayed. Therefore, Betong would like to propose that every future audit finding should have three clear points. First, who is responsible? Second, when must it be completed? Third, how much money or benefit has been recovered? Can the government prepare follow-up reports that are clearer and periodic to Parliament, so that we can see not only the audit findings but also the status of action taken on those findings? Mr Speaker, in conclusion, Betong would like to raise one major question. Is the Auditor General's Report (LKAN) merely a record of mistakes that have occurred, or do we want it to be a tool to prevent the same mistakes from recurring? In my view, the success of an audit is not measured by the length of the list of findings. The success of an audit must be measured by how many findings have been successfully resolved and no longer recur, because every ringgit of the people's money must have a purpose, must have a record, must have accountability and ultimately must produce benefits for the people. That is the true meaning of good governance. Thank you.

Thank you, the Honourable Member for Betong. The next debater is the Honourable Member for Kuala Nerus. Honourable Member, I see that the time is 12.59 noon. Perhaps you could start a little later, and after the break you can restart.

Tuan Haji Kamal bin AshaariPAS · PNKuala KrauEN

Kuala Krau is not Kuala Nerus.

Sorry, sorry. Kuala Krau. Kuala Krau, sorry, sorry. Okay, it is already 1.00 noon. Honourable Members, since the time now shows 1.00 noon, I adjourn the sitting now and it will resume at 2.30 p.m.

[Sitting suspended at 1.00 noon]

[Sitting resumed at 2.30 p.m.]

[Deputy Speaker (Puan Alice Lau Kiong Yieng) presided

Deputy Speaker (Madam Alice Lau Kiong Yieng)EN

I invite the Honourable Member for Kuala Krau.

Tuan Haji Kamal bin AshaariPAS · PNKuala KrauEN

Assalamualaikum warahmatullahi wabarakatuh. Thank you, Mr Speaker. The Auditor General's Report on the Federal Government's Financial Statements for the Year 2025 records a government loan to Warisan Jengka Holdings (M) Sdn. Bhd. The purpose of the loan is stated as financing operating expenditure following the takeover of the Jengka Wilayah Development Authority (LKWJ) by Warisan Jengka Holdings (M) Sdn. Bhd. (WJHSB). Mr Speaker, the Jengka territory was previously developed by the Jengka Wilayah Development Authority (LKWJ). It was dissolved through the Jengka Wilayah Development Authority (Dissolution) Act 1997, which is Act 567, and was passed by this House. However, from the findings of this report, it means that the company which took over this authority had to borrow from the government to cover operating expenses. Before 2025, the entire outstanding loan balance of RM5.05 million had been in arrears for eight years. In 2025, this loan was restructured for the second time, and the interest rate was reduced from four per cent to two per cent. The report also records that the interest of Syarikat Jengka Sdn. Bhd. totalling RM10.20 million was written off after Amanah Saham Pahang took over the outstanding principal of RM1.92 million. I also understand that since 2010, the Federal Government has entrusted the East Coast Economic Region Development Council (ECERDC) with a special fund to enable the former DARA LKWJ area. However, it must be understood that ECERDC was established for the entire East Coast economic region, not an authority specific to one region. The Pahang State Government itself stated in February 2025 that it would not leave the areas abandoned by these two agencies. This means the need is still acknowledged to this day. So, I would like to ask, what is the total amount of the Federal Government's loans to Warisan Jengka

Tuan Haji Kamal bin AshaariPAS · PNKuala KrauEN

Holdings and Syarikat Jengka since privatisation, and how much has been written off? Is the Ministry of Works (KKW) prepared to conduct a study to assess the need for an authority for the former Jengka territory, or at least for Pahang? Mr Speaker, Warisan Jengka is not the only problematic borrower. Up to the end of 2025, more than RM8 billion in Federal Government loans remained unpaid. Of the arrears carried forward from the previous year, only five per cent was collected throughout 2025. There are loans that have never been repaid at all since their repayment schedules began in 1981. However, Mr Speaker, there is one limit that was not observed. The Federal Government loan guidelines stipulate that a loan may only be restructured a maximum of two times. The audit report here finds that some loans have been restructured as many as five times. When the two-time limit can be exceeded five times, this shows a considerable structural problem. My question is, how many loans have been restructured beyond the two-time limit, and at what level were they approved? Will the Ministry of Finance ensure that the borrower's ability to repay is assessed first before a loan is restructured, and when will this begin? Mr Speaker, the 12th Malaysia Plan (RMK12) ended at the end of 2025. However, more than 2,200 projects under it have not yet begun. I agree that from the perspective of government expenditure, the government has fully spent the RMK12 allocation and even more in some cases. However, money spent does not mean projects have reached the people. For the Ministry of Rural and Regional Development (KKDW), 452 rural projects have not yet started, nearly one in every four projects of that ministry. Areas such as Kuala Krau, including the former Jengka Wilayah, depend on these projects. My question— so, I would like to ask, of these 452 KKDW projects, how many are located in Pahang and how many are in the Kuala Krau Parliamentary constituency, and will all of them be carried over to RMK13 with guaranteed allocations or not? Mr Speaker, secondly I would like to raise another matter relating to the management of public money, namely contractor advances. The audit report finds that as of 31 December 2025, RM68.81 million in contractor advances for 24 projects had still not been recovered, and what is even more worrying is that RM52.63 million

Tuan Haji Kamal bin AshaariPAS · PNKuala KrauEN

or 86 per cent has been in arrears for more than 10 years. Most of these arrears involve companies that have been wound up or dissolved. We often discuss delayed projects and projects that are still unfinished, but in this issue, the project may have moved, the money has been advanced, yet the government's own money has still not returned after more than a decade. A little more, Mr Speaker, just a little. So, I would like to ask the government, why could RM9.63 million be in arrears for more than 10 years? Of the RM68.81 million, how much is still realistically recoverable by the government? What action has the government taken against the officers or ministry responsible when follow-up collection was not carried out within a reasonable period? And finally, does the government have a clear timeframe after which an advance becomes a debt that must be collected before legal action becomes mandatory? Thank you.

Deputy Speaker (Madam Alice Lau Kiong Yieng)EN

Thank you, the Honourable Member for Kuala Krau. I invite the Honourable Member for Kuala Nerus.

Dato' Dr. Hj. Alias bin RazakPAS · PNKuala NerusEN

Bismillahirrahmanirrahim. Assalamualaikum warahmatullahi wabarakatuh, greetings of peace. Alhamdulillah, thank you Deputy Speaker for giving Kuala Nerus the opportunity to join the debate on the Auditor General's Report Number 2 of 2026. Firstly, I would like to touch on the concern raised by the Honourable Member for Kuala Terengganu this morning regarding the delay in the Kuala Nerus coastal erosion control project, particularly the need to accelerate the protective structures before the coming Northeast Monsoon. However, I see this issue from a broader perspective. LKAN 2/2026 not only records the delay of the project in Kuala Nerus, but also shows that another coastal erosion control project in Marang has been terminated. This raises the question of whether we are facing a bigger problem in the planning, monitoring and management of coastal protection project contracts in Terengganu.

Dato' Dr. Hj. Alias bin RazakPAS · PNKuala NerusEN

For the Marang Beach erosion control project, valued at RM15.63 million, the actual progress only reached 21 per cent, when the expected progress was

Dato' Dr. Hj. Alias bin RazakPAS · PNKuala NerusEN

100 per cent. Although an extension of time of 125 days was granted, the contract was eventually forced to be terminated on 9 July 2024. LKAN also records that Liquidated and Ascertained Damages (LAD) totalling RM155,480,00,000 have yet to be collected because the certificate of completion and final payment have not been finalised. Therefore, I would like to seek an explanation from PETRA and JPS, namely what is the latest status of the settlement of this project, including the remaining coastal protection work that has not been completed, as well as the collection of the said LAD. Madam Deputy Speaker, the situation in Kuala Nerus and Marang must serve as a lesson that east coast coastal protection projects cannot be managed like ordinary construction projects. The effective working period is strongly influenced by the Northeast Monsoon, sea conditions, and the capacity to mobilise materials and machinery. As also emphasised by the Right Honourable Menteri Besar of Terengganu, weather factors and the capacity of implementing agencies must be taken into account in evaluating and planning coastal projects on the East Coast. Hence, are PETRA and JPS prepared to re-evaluate the planning model, contractor selection, implementation schedule and risk management for coastal projects in the east coast states, so that problems of delay or contract termination do not keep recurring? I hope the Federal Government does not view Kuala Nerus and Marang as two isolated cases, but as a signal to strengthen the overall governance of the Coastal Protection Project. For east coast states such as Terengganu, delays or failures of projects are not merely figures of physical progress and contract administration issues, because every monsoon season that passes without adequate protection means that the people, infrastructure and coastal areas remain exposed to risk. That is why corrective action must not only be expedited, but must also ensure that the same weaknesses do not recur in subsequent projects. Next, Madam Deputy Speaker, I would also like to touch on the findings of LKAN 2/2026 regarding the Accounts Receivable (ABT) of the Ministry of Health (KKM), which recorded RM281.08 million or 83.6 per cent of the total ABT of KKM revenue involving medical bills of non-citizens. What is even more worrying is that the responses from KKM and the same report state that more than 80 per cent of the highest arrears and ABT involve in-patients in the category of Undocumented Immigrants (PATI).

Dato' Dr. Hj. Alias bin RazakPAS · PNKuala NerusEN

This matter needs serious attention because prolonged revenue arrears raise questions about the effectiveness of collection management and the financing of public health services. This issue should not be viewed merely as a problem of hospital bill collection, but calls for a more comprehensive solution to the management of PATI in this country. I take note of the Report of the Special Select Committee on Human Rights, Elections and Institutional Reform, which also recommends an identity verification mechanism to distinguish refugees, PATI and economic migrants, in addition to strengthening immigration enforcement and border control. The question now is how far the coordination between KKM, the Ministry of Home Affairs (KDN) and enforcement agencies has been strengthened, so that documentation problems and the presence of PATI do not continue to affect the government's ability to manage revenue, for example the capacity of public health services. Hence, I urge the Federal Government to take firmer, integrated and decisive action, particularly in combating the entry and activities of PATI that violate the law. Strengthen the detection system and the collection of arrears for treatment, and provide a more sustainable health financing mechanism for citizens. Hence, what coordination mechanisms and implementation timeline have been set by the Federal Government to ensure that the recommendations of the Special Select Committee are translated into real action, particularly in addressing the treatment revenue arrears of PATI that have been identified by the Auditor General. We do not want the weaknesses in immigration management...

Deputy Speaker (Madam Alice Lau Kiong Yieng)EN

Honourable Member, your time is up.

Dato' Dr. Hj. Alias bin RazakPAS · PNKuala NerusEN

Just a moment. And the eventual collection of revenue adds pressure to the public health system, which must continue to meet the needs of the people without neglecting the responsibility to provide emergency treatment or humanitarian consideration. In conclusion, I wish to stress that the findings of the Auditor General's Report are not only meant to expose administrative weaknesses, but should become the basis for more effective corrective action. The resolution of the issues raised encompasses management efficiency, inter-agency coordination and firmness in policy implementation.

Dato' Dr. Hj. Alias bin RazakPAS · PNKuala NerusEN

I hope the Federal Government will seriously take into account every audit projection, ensuring clear, integrated and measurable follow-up action. Finally... [Microphone switched off]

Deputy Speaker (Madam Alice Lau Kiong Yieng)EN

Thank you, Honourable Member. I invite the Honourable Member for Sri Gading.

Tuan Haji Aminolhuda bin HassanAMANAH · PHSri GadingEN

Assalamualaikum warahmatullahi wabarakatuh. Salam Malaysia MADANI. Thank you, Mr Speaker. First of all, Sri Gading congratulates the Auditor General for successfully producing this financial report, and thanks the MADANI Government for providing a platform for Members of Parliament to debate in Parliament, whether positively or negatively. It provides a platform for the people to know the policies and also what has been spent in each ministry in our country. Although we are well aware of what has been stated by the Minister during the earlier tabling this morning, Sri Gading fully supports that this Auditor General's Report should be debated not only in Parliament. If possible, it should also be debated in the State Legislative Assembly. So that the State Legislative Assemblies, particularly those involving states that are criticised in this report, can debate it. Because we are well aware, as stated by several colleagues earlier, of collections and arrears that are collected late or not collected. Here also lies the impact of the Federal Government's responsibility when collections from agencies or any parties, whether state governments or GLC agencies, are not collected efficiently, then the liability falls on the Federal Government. So if we look here, for example, we see several states with arrears that have never been paid or are paid late, where, for example, the LKAN records that the Kedah State Government has 33 certain loans that have never been repaid. So, this is an example. What this means is that what happens to the states is not only Kedah and so on, but this is one example, if shown, then collection must be carried out so that if collection is not carried out, that means re-coordination so that it can be paid and collected again and does not burden the Federal Government. That is the first point.

The second point concerns delays. The delay of a project, as we discussed earlier, many debaters from both the left and right have mentioned the LCS. In the past, in war, people used keris, swords and spears, but now there are ballistic missiles. If it takes 34 years to complete, from 2011 to 2035, 24 years before completion, we want to use ammunition that may already be out of date. So, this is also something very shameful for us and requires firmness from the government level to see how we should take it. I fully support the speech by the Pasir Gudang Member, that there should be no bailout to any private company that once made profits and, when it makes losses, asks for a bailout from the government, and this is really very shameful for the government. And I, Sri Gading, strongly agree that we must not become what people call the payers who bear the debts of others, when we ourselves are bearing a very heavy burden.

Finally, Sri Gading wishes to inform this Honourable House about the Accounts Receivable of Contractor Advances at the Ministry of Education level. Where, if we look, the account called contractor advances is usually given to companies as advances to ensure they can carry out projects. Ideally, if we give a project to any company or to those who have won this tender contract, why is it not examined in terms of capab––, that is, if they got the contract, surely they can do it, they have capacity, they have ability. But if the advance is given, in the end the government cannot collect it. Cannot collect, even though the period in which the contractor advance should be paid, where they have completed 70 per cent, or 75 per cent, the advance should have been fully paid. But what is recorded in this financial report, this audit report, is that there are RM28.13 million involving 16 projects that have not been collected. So, this is a form that ultimately harms the government, and we are worried that money from the government given to contractors, the contractors run away and the government bears the loss. And the people also bear it.

Tuan Haji Aminolhuda bin HassanAMANAH · PHSri GadingEN

Secondly, regarding delays. As for the delay of a project, as we debated earlier, many of the debaters from both the left and the right have mentioned the LCS. In the past, when wars were fought, they used keris, swords and spears; now they have ballistic missiles. If it is said that it took until 2035 to complete, from 2011 to 2035, which is 24 years to complete, we want to use munitions that may already be out of date. So this is also a matter that is very shameful for us and requires firmness from the government level to see how we need to take it. I fully support the speech from Pasir Gudang that there should be no bailout for any private company that once made a profit, and when it has incurred losses, asks for a bailout from the government. This is very, very shameful for the government. And I, Sri Gading, strongly agree, and let us not become what others say: taxpayers bearing other people's debts, when we ourselves are also bearing a very heavy burden.

Tuan Haji Aminolhuda bin HassanAMANAH · PHSri GadingEN

Finally, Sri Gading wishes to inform this Honourable House about the Contractor Advance Payments Accounts Receivable at the Ministry of Education. Where, if we look at it, the account called contractor advance payments is usually given to companies as an advance to ensure they can carry out projects. Ideally, if we give a project to any company or to those who have won this tender contract, why is it not viewed in terms of keboleh–– meaning, if they obtained that contract, surely they can do it, they have the capacity, they have the ability. But if the advance is given, in the end the government cannot collect it back. It cannot be collected, whereas the proper period for the contractor advance is that when they have completed 70 percent, or 75 percent, the advance should have been fully repaid. But what is recorded in this financial report, this audit report, is that there is RM28.13 million involving 16 projects that has not been recovered. So, this is a form that ultimately harms the government, and we are worried that the money given by the government to contractors, the contractors run away and the government bears the loss. And the people also bear it.

Tuan Haji Aminolhuda bin HassanAMANAH · PHSri GadingEN

Why? If the project is not completed, it will cause losses to the users or to the people themselves. Apart from that, the money used is the people's money, but users such as schools will end up neglected. So, that is the hope of Sri Gading, that we can implement this, and not only for the interests at the Federal level in seeing this situation, but at the state level too we need to pay attention. That is all, thank you. Assalamualaikum warahmatullahi wabarakatuh.

Deputy Speaker (Madam Alice Lau Kiong Yieng)EN

Thank you, Honourable Sri Gading. I invite Honourable Rantau Panjang.

Bismillahirrahmanirrahim, Assalamualaikum warahmatullahi wabarakatuh. Thank you, Mr Speaker, for giving me the opportunity to take part and debate the findings of the Auditor General's Report No. 2 of 2026. I focus my debate on the Sungai Golok Integrated River Basin Development Project. This issue, we find, is not merely a project that is delayed in completion, but the problem is that every monsoon season, people's houses face damage, farms are destroyed, as well as people's infrastructure, including the economy and various people's activities have to be postponed and face various losses. I wish to touch on the project starting from Phase 1, which began in 2018 and was supposed to be completed in 2022. It is now 2027. And for this project, we see that the initial expected completion date was 22 April 2022. But in November 2023, the government said that progress had reached only 76 per cent and the project was expected to be completed in August 2024. And August 2024 has passed. Now the completion date has shifted to 21 July 2027. So, this matter will certainly have a very large impact, losses, on the property of the people and also on the costs deferred by the government. So, I want to know what are the results of the independent engineer's investigation, how much the losses are, collapses, and especially regarding the damage to the pump, and the pump house that was damaged and has to be demolished, and also the incident involving losses of RM3.2 million, which was also damaged.

So, I want to know what results of the study have been made, what is the status of compensation claims so far, and who certified the design that led to this situation. I also want to ask that the government explain what long-term plans there are to ensure, especially now that we face the monsoon season. Every time there is flooding, Kelantan records losses of almost RM271.7 million. At the same time, the project that was supposed to be a protective barrier for the people is facing delays, increased costs and technical weaknesses. So, what are the short-term and medium-term plans, and before this mitigation is completed, so that it can reduce the cost of risk, especially to the people. And I also want an explanation from the Ministry of Energy Transition and Water Transformation (PETRA) in particular, on what the cause of the embankment breach was, and what study has been made that caused losses of hundreds of millions. So, what are the results of the study that have been made? Please explain one by one. So, the next matter I also want to touch on is the delay in the SST. How is it that the SST approval was delayed by 3.5 years for the Flood Mitigation Project Phase 2. And it should have been approved in September 2002, but the SST was only issued on 31 March 2026. So, I ask for the procurement timeline and the latest implementation plan for Phase 2 and Phase 3, so that losses do not continue to be experienced. And likewise the preparedness made to face the monsoon season in the near future. I also want to touch on Phase 3. That is, where Phase 3 is ahead of schedule. Let us not be afraid, because being too fast makes its impact large on the people. So, how is it that Phase 3 is now ahead of the original schedule. So, I, especially in the Rantau Panjang Parliamentary constituency, face this flooding issue every year, and Phase 2 is the phase specifically to help the flood problem in the town of Rantau Panjang. But, until today, we have not been able to see its operation. And I am embarrassed in front of our neighbouring country. Because the neighbouring country sees that the flood mitigation wall is almost complete. And this directly affects us when heavy rain occurs in the neighbouring country. It will certainly have a very large impact on our state, especially in Rantau Panjang. And we see from past experience that water from Thailand has caused several people's houses to be swept away because of the strong currents that

entered our country through the flood water from Thailand. So, I want an explanation of how this matter can be expedited. Finally, what efforts does the government make to ensure that all these losses or delays do not recur. And I hope that the government will table a special recovery plan for the Golok River so that the risks faced by the areas involved with the Golok River do not continue to burden the people and cause losses to the people and the nation. That is all for now, thank you, Mr Speaker.

Deputy Speaker (Madam Alice Lau Kiong Yieng)EN

Thank you, Honourable Rantau Panjang. I invite Honourable Tampin.

Bismillahirrahmanirrahim. Thank you, Madam Speaker, for giving me the space to take part together in the debate on the Auditor General's Report No. 2/2026. First, congratulations to the Auditor General and all staff of the National Audit Department for their continuous commitment to ensuring that every sen of the people's money is checked and scrutinised. Madam Speaker, I take note of the good news based on the national financial performance in 2025, which shows positive developments, where the revenue of the Federal Government has recorded an increase to RM336.07 billion, while the fiscal deficit recorded a decrease to 3.7 per cent of GDP compared with 4.1 per cent. Even so, let us not be lulled by the annual deficit figure falling. We also need to look at the bigger picture, namely the commitments and liabilities borne by the nation in the future. Which, based on the record of this LKAN, the total liabilities of the Federal Government have risen quite high, to RM1.653 trillion in 2025. So my question, the question I put to the government, is: what is the strategy or concrete measure to reduce the pressure of this long-term debt burden? And a more important question, when the government implements austerity measures or increases revenue, what is the government's assurance that this burden

will not be transferred to the low- and middle-income groups. My view is that the fiscal discipline to be implemented must go hand in hand with the social situation, and we must not overlook the purchasing power of the people whose wallets are getting thinner by the day.

Madam Speaker, the second matter I wish to touch on concerns the Accounts Receivable (ABT), where money that should have become the government's rightful property and could be spent for various public interests still fails to be collected. Based on this audit report, the total outstanding ABT is still as high as RM51.19 billion. More shocking than that amount, RM17.42 billion has been outstanding for more than six years. The people out there wonder, if they are late in paying taxes or loans, action is taken against them very quickly. But when the government's own money has been outstanding for many years with such a huge amount, its status can still remain as ABT and be left alone. I do not intend to urge the government to collect it immediately or in an instant, but the people have the right to know how much can be recovered, how much has become bad debt and how much has to be written off. For that purpose, Madam Speaker, I propose that the government develop an online revenue recovery dashboard and that it be presented periodically in this august House. This matter should be implemented with all possible effort, because the people out there want to see the government's firmness in collecting money that is rightfully the nation's and can be spent on various development activities. Madam Speaker, the third matter I wish to touch on concerns the recoverable loans, where the LKAN recorded that the outstanding principal balance of loans was RM49.22 billion as at 31 December 2025, while interest and late interest totalled RM2.375 billion. What is more important, the outstanding loan repayments totalled RM8.084 billion, which consists of outstanding principal of RM5.70 billion. Government loans from various parties are not free money; they are the people's money that cannot be compromised. My question: out of this RM8.084 billion in arrears, how much has a high probability of being collected, and how much is at risk of eventually being written off? In this matter I fully support the Auditor General's recommendation that the mechanisms for monitoring, enforcement and risk assessment be strengthened by the government. I also propose that every future restructuring of loans be accompanied by a recovery plan with a clear collection target within a clear time frame. If borrowers are given leniency, the people have the right to know what economic and financial basis allows such leniency to be granted? Madam Speaker, based on the whole of this audit report, I can see one very clear theme, namely that the nation's problem is not merely a shortage of money. The truth is that the main problem we must overcome is how public money is planned, spent, monitored and recovered when failures or unforeseen matters occur. Therefore, I call for this audit report to be used as an instrument to improve the system, because in the end the true measure of success in national financial management does not lie in how much money is spent, but the truth is that success lies in how many people's lives we have managed to improve with that money. That is all, thank you, Madam Speaker.

the high likelihood of collection, and how much is at risk of eventually being written off? In this matter I fully support the Auditor General's recommendation that monitoring, enforcement and risk assessment mechanisms be strengthened by the government. I also propose that every future loan restructuring be accompanied by a recovery plan with a clear collection target within a clear time frame. If borrowers are given leniency, the people have the right to know what economic and financial basis allows that leniency to be given? Madam Speaker, based on the whole of this audit report, I can see one very clear theme, namely that the nation's problem is not merely a lack of money. The truth is that the main problem we must overcome is how public money is planned, spent, monitored and recovered when failure or something unforeseen occurs. Therefore, I call for this audit report to be used as an instrument to improve the system, because in the end the true measure of success in national financial management does not lie in how much money is spent, but the truth is that success lies in how many people's lives we have managed to improve with that money. That is all, thank you, Madam Speaker.

Deputy Speaker (Madam Alice Lau Kiong Yieng)EN

Thank you, Honourable Tampin. I invite Honourable Batu Pahat.

Tuan Haji Onn bin Abu BakarPKR · PHBatu PahatEN

Bismillahirrahmanirrahim. Thank you, Mr Speaker, for giving me the space to take part in the debate on the Auditor General's Report No. 2/2026. Batu Pahat wishes to record appreciation to the National Audit Department. For me, this audit report is not merely to find faults, but is an important instrument to improve weaknesses, close leakage gaps and ensure that every Ringgit of the people's money is spent with full trust. Madam Speaker, Batu Pahat begins with the financial performance of the Federal Government. We must acknowledge that there are positive developments.

Tuan Haji Onn bin Abu BakarPKR · PHBatu PahatEN

The fiscal deficit was successfully reduced from 4.1 per cent of GDP in 2024 to 3.7 per cent in 2025; better than the target of 3.8 per cent. New federal government borrowings also decreased by 8.2 per cent from RM202.248 billion to RM185.577 billion. This shows that the fiscal consolidation efforts of the MADANI Government are producing results. But we must not feel too comfortable too quickly, because the federal government's debt still rose to approximately RM1.321 trillion, while debt service payments rose to RM53.711 billion. So, Batu Pahat wants to ask the Ministry of Finance, what is the government's strategy to continue reducing the deficit to below three per cent and at the same time, controlling the burden of the nation's debt service? The Audit also reports that collection of recoverable loan arrears was only about RM465 million, or five per cent of RM9.273 billion in 2025. So, Batu Pahat wants the government to please explain what actions are being taken to recover these arrears? Do not let money that should have been returned to the government go uncollected for years and eventually be written off. Madam Speaker, Batu Pahat turns to the national security issue, namely the littoral combat ship or LCS. As of 25 June 2026, the audit found that the LCS Project still experiences a delay of 7.55 per cent, involving delays between 30 and 108 days. More worrying, there is a risk that LCS 1 will be handed over without achieving full operational capability because training and weapon systems have not yet been fully completed. So, Batu Pahat wants to ask the Minister of Defence, what is the actual status of LCS 1 today? And when the ship is handed over to the Royal Malaysian Navy (TLDM), is it truly ready to operate or to fight? We must not just chase the handover date. We do not want a ship to be at the jetty and then we announce that the project has been completed, and TLDM also needs a ship that truly has functioning weapon systems, functioning sensors, trained crew and has reached a state of operational readiness. So, Batu Pahat also wants MINDEF to explain what the recovery plan is so that the delay of LCS 1 does not have a knock-on effect on LCS 2, 3, 4 and 5. Madam Speaker, the second matter relating to MINDEF is also the management of army armoured vehicles. The audit found that there were weaknesses

Tuan Haji Onn bin Abu BakarPKR · PHBatu PahatEN

in contract administration and procurement management for the period 2020 to 2023. For example, Gempita. Its supply was late between six and 1,048 days, but penalties totalling almost RM162 million have not yet been collected. More shocking, the notice of penalty claim was only issued 745 days, more than two years after the contract ended. Therefore, my question is simple. Have the RM162.75 million been collected or not? If not, why? The audit also found delays of between two and 227 days for repair maintenance and supply of spare parts, with RM1.2 million in penalties not yet imposed. More worrying is that this procurement was done by splitting it into small lots. Therefore, I want MINDEF to answer whether this practice has been stopped? What new mechanism has been established so that it does not recur? Finally, I appreciate that as of 28 September 2026, a total of 12,117, or 94 per cent of the 12,835 follow-up audit issues, have been successfully resolved, and audit follow-up actions produced collections and repayments to the government totalling RM920.91 million. So, this is the people's money, every Ringgit must be guarded, every weakness must be corrected and every party entrusted must be held accountable. That is all, thank you, Madam Speaker.

Deputy Speaker (Madam Alice Lau Kiong Yieng)EN

Thank you, Honourable Batu Pahat. I invite Honourable Jerlun.

Bismillahirrahmanirrahim, assalamualaikum warahmatullahi wabarakatuh. Mr Speaker, Jerlun also takes part in debating the Auditor General's Report No. 2/2026 concerning the Financial Statements of the Ministry of Energy Transition and Water Transformation (PETRA), specifically the Drainage and Irrigation Department (JPS). The government allocated RM1.490 billion for five years, 2021 to 2025, while a total of RM1.479 billion (99.3 per cent) has been spent for that period on three programmes, namely the Coastal Erosion Rehabilitation Programme, River Mouth Restoration and overcoming the problem of the phenomenon of big tides (FAPB).

I want to focus this audit report on the programme to overcome the phenomenon of big tides (FAPB). The audit finding is that the programme

to overcome the FAPB problem still cannot be evaluated because four projects were newly completed between September and December 2025, and 18 projects are still under implementation. My questions here are, first, what is the real cause of 18 FAPB projects still being under implementation, when the threat of big tides is a matter of public safety and protection requiring immediate action. Second, can the government give a guarantee that these projects will not experience delays, cost increases or weaknesses in contract management? And thirdly, when will all 18 of these projects be fully completed? In Jerlun, namely the areas of Kuala Jerlun and Kuala Sanglang, are strategic locations that frequently experience FAPB problems. Usually, these FAPB problems occur during the monsoon transition and stormy weather. Every time there is a big tide, residents have to buy sand and put it in bags, placed on the riverbank to buffer the sea water so that it does not enter their homes. I refer to the residents' representatives, Encik Mohd Fadil bin Sulaiman and Encik Zainuddin bin Ismail, that residents very much hope that the government will build a breakwater in the area by upgrading the riverbank by at least two or three feet to prevent overflow of big tides. The construction of this breakwater should include coastal erosion structures suited to the local problem. It is intended to ensure that there is no overflow of salt water into residential and agricultural areas, and besides that to ensure the safety of lives and property is guaranteed for residents in the coastal stretch concerned. I also refer to the Federal Government's Financial Statements, particularly regarding the highest Accounts Receivable (ABT) in 2025 involving the Inland Revenue Board of Malaysia (LHDN), the Public Service Department (JPA) and the Ministry of Health Malaysia. The LKAN shows that the ABT issue must be seen not merely as an accounting figure but as money that should have come into the government but has still not been received. In Audit Report No. 1/2026, the audit itself emphasised the need for arrears collection mechanisms to be strengthened to avoid prolonged arrears or eventual write-offs. Government money that has not been collected is an issue of the nation's cash flow. If revenue should have been received but is still in the ABT, the government has not obtained cash benefit from that revenue. The question is, it is not only how much ABT there is, but how much can really be

...collected and when will it be collected? LHDN needs to be given special attention. ABT at LHDN, amounting to RM40.389 billion, is a very large portion of the reported ABT revenue. Therefore, it needs to be clarified whether it consists of outstanding tax arrears that are still active, cases under appeal, litigation cases, or amounts that carry a risk of not being collected. ABT at JPA and KKM also needs to be itemised. For JPA, the important question is what the components of the debt are? For example, claims, loans or repayments not yet received. For KKM, it needs to be examined whether the ABT arises from service charges, hospital claims or other matters. Do not let ABT turn into write-offs. Previous audits have stressed that collection or adjustment mechanisms must be put in place immediately to prevent ABT from becoming bad debts and eventually having to be written off. Finally, it appears the government is very firm in ensuring that the people and companies pay taxes and all other payments to the government on time. But when tens of billions of ringgit become accounts receivable (ABT), is the government itself showing the same discipline in ensuring that money which is the government's right is actually collected, rather than being left outstanding until it is eventually written off? Thank you, Mr Speaker.

Deputy Speaker (Madam Alice Lau Kiong Yieng)EN

Thank you, Honourable Jerlun. I invite the Honourable Bentong.

Bismillahirrahmanirrahim. Assalamualaikum warahmatullahi wabarakatuh and greetings of peace, good afternoon everyone. Madam Speaker, thank you for giving me the opportunity to take part in the debate on the Auditor General's Report today. Allow me first to record my congratulations and high appreciation to the National Audit Department and the Auditor General for their tireless efforts in presenting a report that is honest, transparent and courageous, in order to ensure that every sen of the people's money is properly looked after. This audit report is not merely a collection of figures or a list of accounts that have been checked for their own sake. It is a mirror of the integrity of a government's governance. Every number recorded in it carries great meaning. It

represents the hopes of the people, including my voters in Bentong, who pay their taxes in the hope that these will return in the form of services, facilities and security that truly function. Madam Speaker, however, when we examine this LKAN, it is hard not to feel disappointed. Old issues keep recurring. Variation orders (VO) that swell, assets and systems worth millions of ringgit that are left idle and unused, and the continuing delays in important infrastructure projects. These issues of leakage and delay are not merely discussions on paper. Their impact continues to be felt by the people at the grassroots level, including in Bentong. My constituency frequently faces issues of slope maintenance, road repairs, and urgent flood mitigation and river infrastructure projects. When the LKAN reveals weaknesses in contract administration, delays in project completion and repeated approval of VOs without commensurate physical progress, it is the people who must bear the consequences. Why did the allocations approved to repair public infrastructure take such a long time to be truly felt by the people? Why is there a case where project costs swelled due to VOs, yet road and drainage problems in high-risk areas such as Bentong are still not fully resolved? It is like buying clothes that are too big, which in the end are only used as rags. As another example in Bentong, at Kampung Janda Baik. The process of replacing old pipes with new pipes is still not complete, even though almost two years have passed since this project was approved. When the people come and ask me, "Where is the Honourable Member for this project, when will the pipes be replaced?" I have no answer, because I am still waiting for when it will start, and they are angry with me instead of with the implementing party. Madam Speaker, we have allocated large funds, but because of management weaknesses at the implementing level, in the end the results do not provide the optimum facilities and protection as promised to the people of Bentong and the people of Malaysia in general. My message is clear. Leakage is a form of betrayal of the people's trust. Whether it involves ICT systems that are completed but not used, or public projects that are abandoned, such blatant wastage of funds must be stopped.

The same goes for contract administration, where the liquidated ascertained damages (LAD) penalty clauses are often not enforced firmly. As the saying goes, "Steal in the open, hide in the dark." This leniency gives room to malicious contractors to slow down projects because they know no firm action will be taken against them. The time has come to stop the culture of doing wrong, apologising, promising to fix it next year, and repeating the same again and again. The audit dashboard is indeed a good step towards revenue recovery, but the people want more than that, so that they can see real responsibility imposed on the individuals who are accountable. Therefore, Madam Speaker, I wish to put forward three firm proposals. The first is the enforcement of the amended audit act. Use the power of follow the public monies, with permission, aggressively to trace every sen of public funds that flows to government-linked companies (GLC) or agencies that fail to achieve their objectives. The second is specific monitoring of rural projects and high-risk areas. Ensure that every infrastructure allocation in areas such as Bentong and others is monitored in phases so that payments are not made before work is completed according to specifications. And the third is disciplinary action and blacklisting of failed contractors. Officers who are negligent must be subjected to disciplinary action, and contractors with records of delay or inflated costs without reasonable cause must be permanently blacklisted from government procurement.

Madam Speaker, remember the proverb, "A drop of indigo spoils a whole pot of milk." The mistakes of a few parties must not be allowed to tarnish the good name of the entire public service that has served honestly and with full dedication all this time. The people of Bentong and the people of Malaysia are watching. Let us not allow this audit report to become merely an annual debate document without any bold and firm follow-up action. With that, Madam Speaker, I support this debate and urge that firm action be taken immediately. Thank you.

Deputy Speaker (Madam Alice Lau Kiong Yieng)EN

Thank you, Honourable Bentong. I invite the Honourable Tuaran.

Kopisanangan, Madam Speaker. Tuaran rises to debate the Auditor General's Report Series 2 of 2026, focusing on one basic and very important question, namely the implementation of government projects, with a single question. Are all the government projects proposed in the government's five-year plan truly completed, functioning and providing benefits to the people on time? Tuaran welcomes the Auditor General's certificate without remarks. However, this certificate only confirms the fairness of the financial statements. It is not a guarantee that all projects have been completed, are functioning and have been enjoyed by the people. The Auditor General's Report reports that of the 9,578 projects reported, only 3,120 projects, or 32.6 per cent, have been completed. This means 6,458 projects, or 67.4 per cent, are still not completed. The people have a right to a clear explanation. How many are delayed? Projects that are troubled, abandoned or have not yet started at all? In Sabah, of 941 development projects under the Twelfth Malaysia Plan, only 405 projects, or 43 per cent, have been completed. A total of 411 projects, or 43.7 per cent, are still being implemented. Meanwhile, 125 projects, or 13.3 per cent, have not started or are still at the planning stage. The overall total is 941 projects, equivalent to 100 per cent. These figures cannot be viewed in isolation from the reality faced by the people. Sabah still faces shortages of roads, dilapidated schools, health facilities, water and electricity supply. Every delay means longer journeys, inadequate facilities and continuous supply disruptions, especially in rural and interior areas. More seriously, Sabah's development expenditure has reached 95.3 per cent. 95.3 per cent, whereas only 43 per cent of projects have been completed. How is it that almost the entire allocation has been spent, while more than half of the projects are still not completed? So, we request an answer from the Ministry of Finance. Tuaran is not accusing anyone of wrongdoing. However, the government is obliged to provide an explanation. Are payments made based on actual physical progress? Did costs rise due to delays in scope changes? Why has such high expenditure not been translated into facilities that can be used by the people?

The people do not use the figure of 95.3 per cent. The people use roads that are completed, schools that are safe, clinics that function, and stable water and electricity supply. Expenditure without usable results is not delivery; projects that are completed and functioning are the real achievement. What is more disappointing is that there are still 70 projects from the Ninth Malaysia Plan, 358 from the Tenth Malaysia Plan and 1,602 from the Eleventh Malaysia Plan, at least 2,030 projects that have not been completed. This total is the sum of the reported figures and does not necessarily represent unique projects if there is overlap between periods. Why have projects since the Ninth Malaysia Plan remained delayed until the Twelfth Malaysia Plan? What are the causes? Is it land problems, design, procurement, allocation, contractors or weaknesses in accountability? Every delay has the potential to increase costs and postpone benefits to the people. The government cannot keep announcing new projects while old projects are still not completed. Therefore, Tuaran puts forward five clear, measurable demands that must be implemented. First, the Ministry of Finance together with the implementing ministries must implement a project readiness certificate within six months. No project may be tendered without confirmation that land matters, design, utilities, technical transparency, cost and financing have been finalised. Second, the Implementation Coordination Unit together with the implementing ministries must launch a public project dashboard within 90 days. This dashboard must display contract value, contractors, physical and financial progress, completion dates, EOT, and reasons for delay. Information must be updated at least once a month. Third, every project that applies for a second EOT must undergo independent review within 30 days. The decision to continue, rectify or terminate the contract must be made within 60 days. If necessary, the remaining work must be re-tendered within 120 days, subject to procurement law. EOT is not a licence to fail. Every EOT must state the reason, additional costs, new completion date and the officer who approved it. Fourth, the government must set up a legacy project resolution team within 30 days. All Ninth Malaysia Plan and Eleventh Malaysia Plan projects that have not been completed must be audited within a period of

six months and resolved within 24 months, whether completed, scope changed, re-tendered or cancelled. Progress reports must be tabled in Parliament every six months. Fifth, every implementing ministry must appoint a project accountability owner within 30 days after the contract is approved. The names of officers, time targets, costs, quality and project outputs must be recorded. Monthly reports and quarterly reviews must be carried out. Tuaran also demands that the government table in Parliament within 90 days a list of projects under the Project Scope of the Ninth to Twelfth Malaysia Plans that have not been completed, projects that have received two or more EOTs, cost increases, contractor status, accountable project owners and the final completion date. As for Sabah...

Deputy Speaker (Madam Alice Lau Kiong Yieng)EN

Time is up.

Okay, there is a little more, Madam Speaker. The report must explain how the 95.3 per cent expenditure has been translated into projects that are completed and functioning. Madam Speaker, these demands clearly set out who must act, what must be done and when the results must be seen. Within 90 days, the people must receive transparent data. Within six months, every problematic project must have a recovery plan. Within 24 months, legacy projects must be completed or a final decision must be finalised.

Deputy Speaker (Madam Alice Lau Kiong Yieng)EN

Thank you, Honourable Member. Thank you.

I will end with just one pantun. May I?

Deputy Speaker (Madam Alice Lau Kiong Yieng)EN

Eight minutes have passed already. Please sit down.

Terima kasih.

Deputy Speaker (Madam Alice Lau Kiong Yieng)EN

I invite the Honourable Tumpat.

Assalamualaikum warahmatullahi wabarakatuh, Mr Speaker. Bismillahirrahmanirrahim. In

reading the Auditor General's Report, I noted the report stating that the objective of the Sungai Golok PLSB project under the MyProjek system is to reduce flood risk to a 50 ARI level, in addition to protecting agricultural areas and residents' incomes, stabilising the Malaysia–Thailand border and improving navigation safety and border defence. The question is, when the LKAN reports that there was a change involving the scope of the flood barrier construction from 2.5 kilometres to a flood barrier of 42.5 kilometres using steel sheet pile. Why did such a huge increase occur? That is the first. The second, in the year— in December 2022, a major flood occurred that reached 91 ARI, compared with the original design for PLSB of 50 ARI. My question is, what action and variation orders have the government taken to update the design following the unexpected change in ARI, whether design changes and related matters? Could it be that preparations for 100 ARI need to be made? And as an example, we also see in this report that two water pumps had to be demolished, with losses worth RM3.2 million. So, what follow-up actions and contingencies have been proposed by the consultant as preparation for the instability of PLSB due to global climate change that may occur in other places? Next, due to the delay in PLSB, we see many things happening. For example, at Kampung Simpangan, Pengkalan Kubor. During the summer, the situation becomes very dusty. Almost all houses are covered in dust and the road surface is like a roller coaster. During the rainy season, they face extraordinary flooding because this has not been completed, and in terms of security, there have been complaints during floods. Our people are exposed to intrusion and also theft involving boats from neighbouring countries, because at that time there is no border they can determine, as they can simply enter, and the situation has become like a sea.

Tumpat requests the ministry to table a recovery plan, including progress targets and the period for resolving each problem comprehensively. The people want to see work at the site moving faster and project progress being reported regularly to the public. Next we see,

I also wish to know specifically from whom the people can claim compensation for damaged agricultural land and for residents' displacement over several years due to the delay of this PLSB project. Tumpat requests an explanation on action against the weaknesses and the status of the investigation by the Board of Engineers Malaysia (BEM). The ministry must ensure that the division of responsibility between the two consulting firms is itemised so that each party can be held accountable. We also see in this report that there are administrative weaknesses at the Department of the Director General of Lands and Mines (JKPTG) and also at the office. It is reported that the delay involved 285 days, which is roughly nine and a half months. I would like to ask what the land acquisition charter of JKPTG is, and the number of permanent and contract staff taken on to complete this important and urgent project? It was reported that there were problems with land status checks. I want to know how many are problematic and how many are not. What remedies are there, and who is responsible for repaying the losses of the people who suffered floods due to such administrative delays? We know this matter is recurring because this is a high-impact project. And we see that all of this was only resolved regarding land division on 30 July 2026, whereas the project began about four years ago. I also want to ask the government, in view of the reporting today, that water control infrastructure involving the Drainage and Irrigation Department (JPS) and also KADA must optimise the use of technology such as remote control devices as a supplement to manual operations by people in controlling water in flood areas. This is because often the staff on duty cannot open the pump houses or open the water control gates to release water, as they themselves are stranded by the floods. So, the use of the latest technology is needed. PLSB... [Unclear] is located at the border and within the KESBAN area, which covers security and development. The contract value is reported to have increased from 198.02 million to 601.20 million, partly due to the scope change of the KESBAN road. I understand that scope changes may involve additional costs, but the people have a right to a thorough explanation of the necessity and breakdown of such increases. Most importantly, such expenditure should produce effective flood protection and benefit the people, especially for Tumpat and areas such as Sungai Golok.

The increase in cost arose from changes to the project scope to meet border security requirements decided through the second VA in May 2025. Was this not screened from the outset? This is a border area, and KESBAN has been implemented since the 1970s, and it is the estuary of the Sungai Golok. The entire Sungai Golok PLSB project has not achieved the desired objective. If these changes or this project are not completed with the construction of the Pengkalan Kubor-Tak Bai bridge to facilitate movement between the two countries, the PLSB is highly likely to be damaged by boat activity from unlicensed operators, because the nearest bridge that would speed up crossings to Tak Bai is far. The nearest bridge at Rantau Panjang is about 50 additional minutes from Tumpat. In addition, the new ferry provided by the government is always breaking down periodically. So, if we want to meet the SDG standards as originally intended for the Sungai Golok PSB, the Pengkalan Kubor–Tak Bai Bridge becomes the cherry on the top of the cake for this entire project. Do not, after this, realise only later, suddenly become aware of KESBAN, suddenly realise a bridge is needed, and only then want to add it. This will incur higher costs, because we see that building this mega facility for flood and border security is the catalyst and complement to the well-being of the people in Tumpat and the sustainability of KESBAN. Thank you.

Deputy Speaker (Madam Alice Lau Kiong Yieng)EN

Thank you, Honourable Tumpat. I invite Honourable Shah Alam.

Tuan Haji Azli bin YusofAMANAH · PHShah AlamEN

Assalamualaikum warahmatullahi wabarakatuh. Greetings of peace, Malaysia MADANI greetings. Mr Speaker, thank you for giving me the opportunity to debate the Auditor General's Report (LKAN) Series 2 Year 2026. In my view, LKAN is not merely a report for us to identify weaknesses or non-compliance in the government's financial management. More important than that, LKAN gives us an picture of the extent to which every ringgit of public money is translated into benefits that can be felt by the people. Therefore, I wish to touch on three main matters, namely the progress of the Littoral Combat Ship (LCS) Project. The management of recoverable loan arrears

Tuan Haji Azli bin YusofAMANAH · PHShah AlamEN

of the government, as well as the implementation of development projects under the Twelfth Malaysia Plan. Mr Speaker, I wish to touch on the LCS issue because it is not merely a ship development project. This is a national defence project. It involves the security and sovereignty of the nation as well as the operational capability of the Royal Malaysian Navy. As of 25 June 2026, the overall progress of the LCS project was recorded at 78.99 per cent compared with the planned 86.54 per cent, which is a delay of 7.55 percentage points. What is more worrying is that the trial and commissioning component has only achieved 1.41 per cent compared with the planned 31.64 per cent. This figure is important, Mr Speaker, because the success of the LCS project cannot be measured solely by what percentage of the ship has been built. The more important question is when this ship is handed over to the Royal Malaysian Navy (TLDM), whether it can truly operate as planned. We are talking about a warship, so we need not merely a ship that is physically complete, but a ship that has the weapon systems, integration and operational capability required. LKN also raised the issue of the Surface To Surface Missile or SSM as well as several other complementary contracts that have not yet been finalised. Mr Speaker... [Interjection]

Dato’ Rosol bin WahidBERSATU · PNHulu TerengganuEN

Shah Alam. Briefly. LCS. Do you agree, Shah Alam, that since perhaps LCS is no longer relevant, we should simply cancel whichever ones are not yet completed? What is Shah Alam's view? Thank you.

Tuan Haji Azli bin YusofAMANAH · PHShah AlamEN

I want to continue my speech because the ship's construction is still under implementation, yes. Let me finish my speech. What is the definition of complete, Mr Speaker? It is true that the Honourable Minister mentioned that this ship will be completed on 21 December. My colleagues and I are part of the PAC. This PAC is the second PAC that examined in detail, investigated and reviewed the implementation and construction of the LCS ship. But we are at the stage of monitoring implementation. The details were carried out by the previous PAC. We only monitor every three months when the LCS team comes to provide information on the progress of implementation. We have gone twice to Lumut to inspect, and boarded the ship ourselves. True, the ship may be completed in December. But what does complete mean? Because we are very

Tuan Haji Azli bin YusofAMANAH · PHShah AlamEN

worried that in May recently, the Norwegian Government cancelled the licence for the missile system that was supposed to be supplied to our country. For this LCS. So, we do not want, when this ship is completed, for it to become a patrol vessel rather than the warship that we hope for. This is what worries us greatly. Mr Speaker, the second matter concerns the recoverable loan arrears. LKAN recorded that up to the end of 2025 there were RM8.084 billion in recoverable government loan arrears, while RM578 million had been written off. More importantly, the audit report shows that a large portion of these arrears are not new arrears: RM5.024 billion or about 62.1 per cent are arrears that have exceeded six years. This means that too many arrears that the government should have recovered were not successfully recovered, so that in the end the government had to dispose of millions of Ringgit to ensure that the fiscal records and fiscal position of the country were in the correct condition, on the correct track.

Deputy Speaker (Madam Alice Lau Kiong Yieng)

Sila gulung.

Tuan Haji Azli bin YusofAMANAH · PHShah AlamEN

Yes. This also includes the development projects under the Twelfth Malaysia Plan (RMK Ke-12), where LKAN recorded 9,578 development projects up to the end of 2025, of which only 3,120 projects had been completed.

Tuan Haji Azli bin YusofAMANAH · PHShah AlamEN

Many more, thousands more, are being implemented and are at the pre-implementation stage, while 193 projects consist of projects that have been put on hold or cancelled. We are spending billions. This year alone, RM77 billion we are borrowing to carry out these development projects, but if these projects are problematic, of course they will affect the fiscal position of our country, which will undermine the hopes of the people below who need various developments and improvements. Therefore...

Deputy Speaker (Madam Alice Lau Kiong Yieng)EN

Time is up.

Tuan Haji Azli bin YusofAMANAH · PHShah AlamEN

Yes, I will wrap up. Mr Speaker, therefore the three matters I have raised today, the LCS, the government's loan arrears and the RMK12 development projects, actually share one same theme, namely that they are about the accountability of the people's money. The government

Tuan Haji Azli bin YusofAMANAH · PHShah AlamEN

should have a stronger, better fiscal space. We already have accountability, the fiscal responsibility of the nation, which has already been approved. We want development to continue, but at the same time we also want every allocation to be managed prudently, transparently and results-oriented for the people. In the end...

Deputy Speaker (Madam Alice Lau Kiong Yieng)EN

Thank you, Honourable Member.

Tuan Haji Azli bin YusofAMANAH · PHShah AlamEN

Thank you, Mr Speaker.

Deputy Speaker (Madam Alice Lau Kiong Yieng)EN

I invite Honourable Bakri.

Tuan Tan Hong PinDAP · PHBakriEN

Thank you, Madam Speaker. Madam Speaker, the Navy needs modern ships to defend our waters and the sovereignty of the nation. However, the repeated delays in the handover of the LCS show weaknesses in coordination, compliance with procedures and also project oversight. This situation has reminded me of history, namely that in the past the Qing Dynasty of China had the most formidable army in the Far East, but by the end of the nineteenth century, the country suffered a collapse due to corruption and internal weaknesses. At the same time, its neighbour Japan, a country so small, much smaller than China, succeeded in defeating this giant in 1894. This must become a lesson for us in any era, and this reminds me that if a ship has not been completed for 24 years, how do we ensure that our waters are always secured and the sovereignty of the nation is always protected? Because we have vast waters and maritime interests that must be defended. Threats will not wait until our procurement processes are ready. We cannot tell our enemies, who do not know where, to wait, wait first, the LCS has been completed, then come and attack me, that is impossible. But this is the situation we are facing now. How can we allow this situation to shackle us for a dozen years, when it is in fact decades. This is not the first case. Auditor General's Report after Auditor General's Report reveals all kinds of leakages. If other departments

Tuan Tan Hong PinDAP · PHBakriEN

are already serious enough, what more when this involves defence. This involves the sovereignty of the nation. How are we going to find a way out? Madam Speaker, handing over a ship does not mean the ship is ready for combat. The first ship, which was originally scheduled to be handed over in April 2019, is now targeted for handover in December this year, and even that is not yet known whether it will be complete or not. As of 25 June this year, four supplementary contract documents have not yet been finalised. These are important components to ensure that our ship can operate, attack and defend itself. The building of the ship, the procurement of weapons, testing and training should have been coordinated from the beginning. First, LISTA for logistics support and test assistance. The period of four months to finalise these contract documents has been exceeded because of disputes over guarantees and spare parts. Second, 3P cannon ammunition. Third, IBLS, namely the decoy launcher system for ship defence. Its procurement also went through a tender that was cancelled and shifted to direct negotiation. The system for confusing threats also got stuck in the procurement process. In the end, it is the people who are confused about looking at these project schedules. So, the ship's weapons, ammunition, protection systems and operational support must be completed according to one coordinated plan. When contracts are delayed, payment claims are stuck, implementation is disrupted, in the end the entire ship schedule bears the impact. Where is the coordination and oversight before this problem drags on? Even if this ship is handed over, it is not certain that it will be ready for combat, yes. Do not let the people pay billions of ringgit but the Royal Malaysian Navy (TLDM) receives a ship without teeth, which could later be sneered at as floating scrap iron at such an expensive price for a ship.

Deputy Speaker (Madam Alice Lau Kiong Yieng)

Sila, gulung.

Tuan Tan Hong PinDAP · PHBakriEN

Yes, so here I hope, Madam Speaker, that the incidents mentioned earlier, a submarine that cannot dive, a jet with no engine that cannot fly, and now a ship that cannot be found. When will we put a full stop to these weaknesses? I hope these matters need to be taken seriously so that we can stop them, because we do not want these matters to become a ghost that shackles us. Where is the Minister involved? Bagan Datuk, Sembrong are involved, Bera is also involved, so where is their responsibility? Answer: set up a Royal Commission of Inquiry (RCI), investigate and give an answer and provide a way out to

Tuan Tan Hong PinDAP · PHBakriEN

stop such things from recurring again in our country. That is all, thank you.

Deputy Speaker (Madam Alice Lau Kiong Yieng)EN

Thank you, Honourable Bakri. I invite Honourable Jerantut.

In the name of Allah, the Most Gracious, the Most Merciful. Assalamualaikum warahmatullahi wabarakatuh and greetings of peace. Mr Speaker, thank you for giving me the opportunity to take part in debating the Auditor General's Report (LKAN) Second Series 2026. As an active member of the Special Select Committee on Transport and Communication Infrastructure, we have had the opportunity to go and make official visits to the problematic projects as set out in this Auditor General's Report. I wish to state several matters, which I see not merely as a question of figures, but as a question of planning, control and accountability in the management of projects and the people's money. First, the Pan-Borneo Sabah project. We went together with Sipitang to see the project. We often talk about the delays of this project, but I want to look at this issue from a slightly different angle. The audit found that in Phase 1B there were 3,771 structures that had to be demolished, but as of March 2026 only 411, or 10.9 per cent, had been demolished. A total of 3,360 structures still have not been demolished. Meanwhile, about RM84 million in compensation payments has still not been settled. The question is, why was the physical work of the project started when site readiness had still not been fully resolved?

If land acquisition, site clearance and compensation payments are still obstacles, should this not have been settled first before the contractors were mobilised? We cannot keep looking at delays as a problem at the end of the chain. We need to ask where the original planning failed, because when the site is not available, the contractors cannot work fully. Then the project will be delayed and in the end the people will also have to wait longer to enjoy its benefits. Second, Madam Speaker, the Sungai Golok Integrated River Basin Development Project. This is not merely an ordinary infrastructure project. This is

a project that determines the safety and protection of the people from floods, particularly in the Rantau Panjang, Pasir Mas and Tumpat parliamentary constituencies. Phase 1 of this project began in April 2018 and was originally scheduled for completion in April 2022. However, up to now, the project is still incomplete, whereas when we made our visit, the Thailand side had already been completed. What is more worrying is that this project is a interconnected system. If one phase is not yet completed, the effectiveness of the entire flood mitigation system cannot be fully achieved either. This has also been clearly stated in this Auditor General's Report. Indeed, it was once reported that flood mitigation works on the Thailand side had been completed whereas the Malaysian side had still not finished Phase 1. The question is, how much longer must the people of Rantau Panjang, Pasir Mas and the areas near the Sungai Golok bear the effects of this delay. Thirdly, Mr Speaker, regarding the Malaysian Marine Department (Jabatan Laut Malaysia). The audit found that RM2.55 million in allowance and facility payments through KWDA and KWPPL had been made without a valid legal basis, and it subsequently recommended that these payments be stopped until the legal position and financial procedures were finalised. The question is simple: how can payments using public money be approved and made if the legal basis is invalid and does not exist? This shows that internal control must not only look at whether a payment has been approved, but also whether that approval has a valid legal foundation. If audit only discovers something after a check is made, then the government must ensure the internal mechanisms of the ministries and departments themselves are able to detect non-compliance before it becomes an audit finding, and this question becomes more relevant, Madam Speaker, when we look at the issue now occurring in the management of Road Transport Department (JPJ) revenue collection. I want to link this matter with current issues involving MyEG and Zetrix AI. Two days ago, the Ministry of Transport confirmed that RM314 million in government revenue collections for the period 19 May to 30 September this financial year had still not been transferred to the government while the services of MyEG and Zetrix AI as JPJ revenue collection agents were suspended. The Minister of Transport has explained that the RM314 million is not arrears for three years since 2023, but rather collections for

the period 19 May to 30 September 2026. Must we wait until this matter is reported by foreign media before action is taken? Yet the LKAN Series 2021, LKAN 2021 Series 1, once recorded delays in transferring JPJ revenue and recommended that the collection and transfer mechanisms be tightened. So my question is, what follow-up action has been taken on the recommendations of LKAN 2021, and what monitoring mechanism ensures that issues of this kind can be detected earlier. Finally, Madam Speaker, we are talking about money paid by the people to the government. All the matters I have raised are one and the same question, namely whether our control system only acts after problems occur, or whether we truly have mechanisms to prevent problems before they become more serious. Audit is not merely to look for mistakes after money has been spent or projects are delayed. Audit should be part of a mechanism to improve the system and prevent the same things from recurring. Our aim is not merely to look for weaknesses in the audit report, but to ensure that today's audit finding does not become the same headline in future audit reports. That is all, I beg to propose.

Deputy Speaker (Madam Alice Lau Kiong Yieng)EN

Thank you, Honourable Jerantut. I invite Honourable Tebrau.

Tuan Jimmy Puah Wee TsePKR · PHTebrauEN

Thank you, Mr Speaker. In the Tebrau Parliamentary constituency, at the tip of Johor, in the south, there is a traditional Malay fishing village named Kampung Perigi Acheh. A small village, with a population of only 541 people. In 2017, the villagers were happy when the Johor Government approved a project to build a new bridge that was even more beautiful and more sophisticated. For many there, they thought this was the beginning of their dream of getting a new infrastructure, but unexpectedly, from that beautiful and pleasant dream, it eventually became a nightmare, with respect, for the village. Mr Speaker, the story of the bridge construction in Perigi Acheh is very well known in Johor. Imagine, I will read its chronology. Approved for the project to be built in 2017, site ownership handed over in May 2019, the scheduled completion date was December 2020, 18 months. In the end it was not completed, the government was forced to terminate the contractor on

Tuan Jimmy Puah Wee TsePKR · PHTebrauEN

July 2025 and appoint a new contractor this year, January, with the completion date expected in July 2027. That means that if we can hit the target, with permission, and finish building this bridge by July 2027, the whole process of getting one bridge for a village of 541 people will take almost 2,427 days. Mr Speaker, what I do not understand, and why I want to raise this issue today, is how the Public Works Department (JKR) could allow something like this to happen. The contractor originally requested extension of time (EOT) not once, not twice, not three times. Six times. A total of 1,201 days, and physical work at the site has not moved since 2023 until we were forced to cancel the contract. Because we had to cancel and appoint a new contractor, the original cost of RM14 million has now doubled to RM28.36 million. I will simply say that I am rather disappointed that JKR did not terminate this contractor earlier. Why wait until five years before terminating? If I look at the report, it issued six warning letters, six. In my view, looking at the clause, two would have been sufficient, but it chose to issue six. Who is suffering now? The villagers. The bridge is not complete, so a new contractor has to come in. The new contractor comes in, and the cost has doubled. Not only is the bridge not complete, Madam Speaker, the road leading into the village in front of the bridge cannot be tarred. It often floods, and when it floods we face problems. But the government cannot tar it because we understand that lorries would then enter with new construction materials, which is why it has not been tarred. In the end, I say this has become a nightmare for the villagers. That is why, when such matters appear in the audit report, we hope such things will not happen again. I came here today and I request, I see the Minister is also present, and I hope the Minister will give attention to this issue, so that first, this project can truly be completed as now stated, in July 2027. I believe this is just the tip of the iceberg, Mr Speaker, as I believe many cases like this still persist and occur in Malaysia now. Lastly, I also want to give a brief view because the audit report also states that until today the government has not yet claimed Liquidated Ascertained Damages (LAD) compensation, even though the contractor has been terminated since 2025.

Tuan Jimmy Puah Wee TsePKR · PHTebrauEN

Why until today has it still not claimed RM1.3 million? That is the people's money. [Dato' Sri Doris Sophia anak Brodi (Sri Aman) presiding over the Sitting] Second, I hope for the future that when the government chooses contractors, it will choose contractors who are truly of quality and have a good reputation. Let there be no cases like this. We appoint a contractor who keeps rolling over for five or six years and cannot finish a single project. Blacklist them, or put them on a blacklist, and ensure that no time or money of the people entrusted to the government is wasted. That is all, thank you.

Thank you, Honourable Tebrau. I now invite the Honourable Sipitang to speak. Please, Honourable Member, five minutes, Honourable Member.

Datuk Matbali bin MusahBEBAS · GRSSipitangEN

Bismillahirrahmanirrahim, assalamualaikum warahmatullahi wabarakatuh. Greetings of peace, greetings of Malaysia MADANI. Thank you, Dato' Speaker. Sipitang rises to join in debating the Auditor General's Report No. 2/2026 because it is moved by the various issues disclosed, especially those relating to financial management and governance at the Federal and state levels. This Audit Report is a mirror of how the people's money is managed, how the people's projects are implemented, and how the people's trust is held accountable. Therefore, Sipitang views this report from a very simple perspective. The people's money must be protected, the people's projects must be completed, and the people's benefits must be prioritised. These three matters must be the principles in every planning and development. We do not want projects to be announced but completed late. We do not want allocations to be approved but the results not to materialise. Most importantly, we do not want the people to keep waiting and waiting. In the context of Sabah, the matter closest to the pulse of the people is the Pan Borneo Highway Project, Sabah. This project is not an ordinary project. It is not merely a road; it is the connecting artery between districts, villages and towns, between the lives of the people and economic opportunities.

Datuk Matbali bin MusahBEBAS · GRSSipitangEN

For the people of Sabah, Pan Borneo is a promise of development. Pan Borneo is hope, and Pan Borneo is the road towards the future. However, the Auditor General's Report reveals that there are various weaknesses in the planning and implementation of the Pan Borneo Highway Project, Sabah. This project was planned for a long time, and management changed hands repeatedly until it was handed over to the Ministry of Works in September 2019, but until 31 March last, the project still had not been fully completed. Therefore, the simple question is, how much longer must the people of Sabah wait? How much longer must the people of Sabah be patient? How much longer before the road that was promised will truly become a road that can be used? Sipitang does not wish to elaborate on the contents of the Auditor General's Report because we all already know and have read it, but we want to emphasise, as firmly as possible, that this criticism must become a point of correction. Dato' Speaker, Sipitang is among those affected by the delay in implementing this Pan Borneo project, especially the Sindumin–Melalia, Beaufort section, which still has not been completed, even though our district is the gateway into Sabah from Sarawak as well as from the nation of Brunei Darussalam and Kalimantan, Indonesia. In this regard, Sipitang would like to propose that this report be tabled by the government, and not stop at merely providing feedback to the National Audit Department. We need a special Pan Borneo Sabah monitoring mechanism that is more systematic, with a timeline. The target of each package, the status of land acquisition, the status of compensation, the status of variation orders, the status of contracts and physical progress. If necessary, progress reports should be tabled periodically to Parliament so that the district representatives of Sabah are not left unaware of the actual developments. As a closing, I would like to recite a poem from Sipitang's home village. For a long time I have spoken, my mouth has frothed from pleading and asking, for nearly five years we have waited a long time, yet Pan Borneo still has not become a reality. Many sections are not yet perfect, and now the general election is at the very door. I beg the wise leaders, complete it swiftly before the time comes. Do not let the people continue to suffer, nursing bitter disappointment, lest later the YB becomes the victim.

Datuk Matbali bin MusahBEBAS · GRSSipitangEN

That is all, thank you.

Thank you, Honourable Sipitang. I now invite the Honourable Arau to speak. Please, Honourable Member.

Thank you, Mr Speaker. LCS, I propose, first, that the Ministry of Defence (MINDEF) must table in Parliament a detailed LCS recovery schedule for each ship, including milestones, PHO rates and the amount of payments. Second, the outstanding balance of RM2.67 billion must be precisely linked to verifiable milestone achievements. Third, the government must provide periodic reports to the PAC on the progress of the LCS until all five ships are delivered. Fourth, every change in cost and scope through supplementary contracts must be accompanied by clear technical and financial justification. Mr Speaker, I will give the proposals first because there may not be time to read them later. So, first of all, the LCS. Honourable Member, if we follow the plan made by the experts, it was very neat, yes. In 2013, the contract was signed. After that, we would begin purchasing the ships in 2019. It was to end in 2023. Now it is 2026, and it was proposed for August 2026, that is not possible. It was proposed that it might be December, but the risk is still there. So it was proposed for 27 April 2027, then another one in 2028, 2029. The question, Mr Speaker, is this: this was the proposal of experts. The experts who proposed it must certainly have been in the market from time to time. So, we want to know who the experts are. People see that the Minister involved must answer. This is not a matter for the Minister alone, this is the Cabinet. The Cabinet is responsible for this matter. The Cabinet at that time, the Cabinet of this time and also the current Cabinet. Do not treat this collective responsibality lightly. The Cabinet should not blame the Minister alone. Previously you lot were friends with him, now he is not your friend, still mentioning names in Parliament. What kind of friends, I also do not understand, but UMNO is still waiting for what, I wonder? So, I want to tell the Honourable Member that this is a Cabinet that takes responsibility. That is the second point. The first point, we must remember that today we are discussing what the audit has recommended. Good,

alhamdulillah, today it seems all parties are discussing the audit. If not, previously the RCI discussed the audit conducted by external auditors, not the government's audit. Today we are discussing the audit. We discuss the audit: the ship delay happened, but do not forget that when this ship enters the water later, as my friend said earlier, its age will be different. If we planned it in 2013, the hull of the ship, Mr Speaker, which was built at that time, by 2027 that hull will be old, yes. The hull has aged, and when it enters the water, what will happen and so on. So, we think if we build a ship within three years, the hull might be taken into account. But if it goes through that period, we must be told what the hull is? Including my friends in the PAC when we visit there, we must ask that question. When was this hull made? Because often, if these are five ships, they will build five hulls first, then they will do the next one and so on. So, that hull is already aged, yes. Secondly, from six to five. But Honourable Member, all of this, we have discussed and have looked at, and we have made many proposals. The big question now is that many of the Royal Navy's ships have reached 50 years of age. Overseas, a ship that is 30 years old is considered can already be disposed of. So, we have received several ships from Japan and also from the US, ships that are 30 years old they want to dispose of and we take them. In fact, we use them at 45 years old. But now I want to tell this House many times, if that ship is only five more years from its age limit, we cannot wait until it is 50 years old before we order a ship. A ship must be ordered when it is 45 years old. So, we are all discussing the LCS, but I want to ask the Ministry of Defence, what is the comprehensive plan to replace the ships? We are worried that we are discussing the LCS, but the plan to replace ships in the Royal Malaysian Navy (TLDM) may be somewhat neglected, but it must be given attention because this is a matter of defence. We speak of national sovereignty, but if our ships have aged to such an extent, they have already lost— If before they could run up to 35 or 40 knots, now perhaps only below 20. Certainly we will face problems.

So I want to ask, what plans have been made to ensure that the TLDM always remains in the nation's mainstream? The pressures of the world now are increasingly severe and intense. So, we must ensure that we also have great capability.

Regarding what has happened, we must look at who proposed these ships, so that suddenly in 2023 it could not, could not be delivered. So, if the same experts are going to build other ships, I ask the government to review the expertise of any party, so that they do not ignore what has happened now. In fact, if we ordered ships from outside, the ships would certainly be completed now. But when we build locally, this is what happens. However, we also want local expertise, but security conditions cannot be compromised. Finally, Speaker, I want to propose that security matters, two or three matters, should be discussed at Cabinet level. This is security. If we discuss it openly, people will know that Malaysia has weaknesses, six ships, now five, and cannot be delivered until now, with permission. So, people look at our security. Many of these security matters should be discussed at Cabinet level and implemented. If there are matters involving audit and so on, okay, but for managing security, it is not something that should be included in the Malaysia Plan (RMK). I visited the security forces recently in Sabah and Sarawak. When I asked, when are we going to build this? Oh, now we have made a proposal in the RMK. Can war wait for the RMK? It does not wait for the RMK. The RMK is a proposal for other projects. But security projects must be given priority through a different approach. If it is discussed openly like this, the enemy will know who Malaysia is, thank you.

Thank you, Honourable Arau. I now invite the Honourable Jelutong to speak. Please, Honourable Member.

Thank you, Mr Speaker. Greetings of unity, greetings of Malaysia MADANI. I thank you for the opportunity given to join in debating the Auditor General's Report. However, I would like to bring this august House to commemorate what happened on 8 September this year at Long Lellang, Ulu Baram, Sarawak, where a helicopter carrying

the late Captain Zainol Afiq Bee Sham, the pilot who once flew our Honourable Prime Minister; the late Dr Ainul Baraah Kamarudin, a medical officer who also perished; the late Alexson Adit Henry, a medical assistant; Debra Moset, a nurse; and Jessie Paya Jok, a nurse, all of whom perished in the tragedy when the helicopter providing Flying Doctor Service medical services crashed in Sarawak. For the information of Mr Speaker and the Honourable Members, the helicopter used in this incident was about 35 years old. I have a TikTok video clip showing the pilot and medical assistant trying to fit the helicopter door before they took off. Imagine. Imagine this incident that happened, befalling the people who provided medical services to those in remote areas. If we do not take seriously the Auditor General's Report that we are debating today, that is what will happen to our heroes who will fight in littoral combat ships ten years from now. Such incidents of "sakau", I have such incidents, I will speak frankly here. There are Members of Parliament who have RM185 million at home. RM185 million. If that money were used to buy helicopters, how many helicopters could we buy for remote areas in Sabah and Sarawak? I live in Penang, but this is what I imagine, this is what people ask me. So, such "sakau" incidents did happen, and we should thank Datuk Seri Wan Suraya Wan Mohd Radzi, an Auditor General who had the courage to expose such "sakau" incidents. Compared with Madinah Mohamad, a former Auditor General who gave an interview at the Musyawarah Nasional. We know who was involved in the Musyawarah Nasional. She said there is not a single word "sakau" in the Tabung Haji Report. Imagine, Madinah Mohamad was a head, a former Auditor General, at the time of the Tabung Haji scandal. This is what will happen to our country. We lost a pilot, a medical officer, three nurses who sacrificed their lives, providing services to people in remote areas in Sabah and Sarawak. Do we not feel pity? But I am debating this matter because I know that the government of the Honourable Prime Minister is burdened with the responsibility to

...to correct our system. Meanwhile, we know there are elements trying to undermine the political stability of our nation. There are Members of Parliament and political parties that want to seize power. How can the government focus its attention on correcting these *sakau* incidents? We have seen recently the DAPAT Vista scandal, a company that manages eJamin. Hundreds of millions of Ringgit were generated by them and kept by them. This involves bail money alleged in court, involves the justice system, involves a person's rights. If the justice system, the place where we keep bail money, is not managed properly, imagine what would happen. And I also want to draw attention as Mr Speaker, as I debated yesterday, to the incident where we learned the National Registration Department may be involved in forging documents involving football players who are not Malaysian citizens. All of them are from abroad. Who has been implicated until now? I request, I demand that the National Audit Department uncover this matter. Who are the officials involved in forging the documents of football players who were not born in our country? These are matters we need to know. Imagine we know there are people who have lived in this country for 70, 80 years. The Registration Department says they are not fluent in Bahasa Malaysia and cannot be granted citizenship rights. These are white people, 10 people, 11 people, who wear football jerseys and play for Malaysia. But their identity cards were forged, their citizenship certificates were forged, their birth certificates were forged. Who are the people involved? Please uncover these matters so that we are safe and ensure that only Malaysian citizens hold citizenship rights in our nation. Thank you, I humbly ask for support.

Thank you, Honourable Jelutong. Next, Honourable Tanjong Karang, please proceed, Honourable Member.

Thank you, Mr Speaker. My highest appreciation is extended to the Auditor

General and all staff of the National Audit Department for their continuous commitment in producing reports that are transparent, professional and of high integrity. This LKAN 2/2026 report is not merely a routine audit document but a pillar of checks and balances that ensures public money is managed prudently. Tanjong Karang's main focus today highlights the strong rebuke in LKAN 2/2026 against the Ministry of Finance, particularly regarding the critical issue of loan arrears. This report reveals a very worrying reality where the Ministry of Finance faces accumulated loan arrears amounting to RM8.08 billion. More shocking, a large portion of these public funds has been left idle and has never been settled or collected since the 1981 decade. This shows a chronic weakness in the enforcement mechanism, debt monitoring and risk management of the ministry.

Based on the reports I have received, the annual collection performance is at a level that is very difficult to accept. The government is reportedly able to collect only about five percent of the target or the total loan arrears that should have been received. Mr Speaker, when collection is at such a minimal rate, where is the firmness of the ministry in protecting the nation's fiscal rights? Is there an attitude of washing its hands of the matter, or no serious legal and civil action taken against these chronic borrowers? Mr Speaker, the nation is struggling with financial constraints, the need for subsidies for the people, and efforts to reduce the fiscal deficit. It is unreasonable that at the same time billions of Ringgit of public money are simply stuck due to inefficiency in loan collection administration. Therefore, Tanjong Karang demands that the Ministry of Finance table a recovery plan, with permission, that is detailed in Parliament, including a list of legal actions or restrictions imposed on defaulting debtors. Rather than letting this recurring issue become a cancer that daily harms the nation's finances. Is *sakau* also happening here? That is, *penyakauan* done professionally. If not, why is it being kept quiet? Next, Tanjong Karang would like to touch on compliance and the financial statements of the states. Although the financial performance of several states

shows positive improvement, various issues of leakage, project delays and wastage in public procurement are still rampant. We demand transparent disciplinary action and effective surcharges against negligent officers or parties, not just empty warnings. Next, regarding strategic projects and defence. The audit report clearly shows that the nation's strategic project, such as the littoral combat ship (LCS), still faces very worrying delays. This problem not only threatens the nation's security and defence sovereignty but also burdens the people as administrative costs and project expenditure have to be increased due to weaknesses in project schedule management. Mr Speaker, finally, Tanjong Karang would like to put forward three main demands for improvement. First, the matter of strict accountability. The Public Accounts Committee (PAC) should expedite proceedings on the issues raised in this LKAN 2/2026 report without any compromise. Second, follow-up action. Every ministry and agency named in the report must table a compliance report within six months in Parliament. Third, legislative strengthening. Strengthen the Audit Act so that repeated rebukes no longer become a routine script every year without firm preventive penalties. Mr Speaker, the financial integrity of the nation is the last line of defence of a sovereign country. The people's money must be protected. Tanjong Karang takes note of and supports that this LKAN Number 2/2026 be debated thoroughly and requires follow-up action for the sake of administrative reform in the nation. Thank you.

Thank you, Honourable Tanjong Karang. Next, Honourable Beaufort. Please proceed, Honourable Member.

Bismillahirrahmanirrahim. Peace be upon you, and the mercy and blessings of Allah, and greetings of peace. Thank you, Mr Speaker, for the space and opportunity given

to Beaufort to participate in debating the Auditor General's Report Number 2 of 2026. I would like to focus on two matters that are very close to the people of Sabah, particularly in Beaufort, namely the implementation of the Pan Borneo Sabah Highway Phase 1E Project and the management of the Integrated River Basin Development Project. Mr Speaker, the audit report shows that out of 35 work packages of Pan-Borneo Sabah, namely Phase 1, only four packages have been completed as of 31 March 2026, while 31 packages are still under implementation. Of this total, nine packages are categorised as troubled projects. The contract cost has also increased from RM17.910 billion to RM18.960 billion. For Beaufort, this matter is not merely a figure in the audit report. It involves time, cost and benefits that should be enjoyed by the people. I would like to give special attention to WP01: Sindumin – Kampung Melalia and WP02: Kampung Melalia – Beaufort. WP01 has reached about 89.2 percent, while WP02 is about 63.3 percent. Based on the recovery plan, WP01 is targeted for completion in December 2026, while WP02 in May 2028. I appreciate the Ministry of Works' efforts to strengthen the monitoring and coordination of the Pan-Borneo Sabah Project, including site visits to WP01 and WP02 in early October 2026. However, my question is, what concrete steps will the ministry take to ensure WP02 does not experience further delays and can be completed earlier than May 2028? The people of Beaufort have been waiting for a long time. We need a clear completion date, monthly progress targets that can be monitored, and an accountability mechanism should the targets again be missed. Mr Speaker, I would also like to touch on the issue of variation orders, with permission, and project governance. The audit report raises the issue of large-value variation orders and approvals that exceed the authorised limit. This matter must be given serious attention because every change in scope, cost and implementation period ultimately has implications for public money. Likewise the issue of loss of project data. The audit report records the loss of tens of thousands of project information system files and some data has still not been successfully recovered. The question is, how can projects worth billions of Ringgit be monitored and audited effectively if the project's own records are not

complete? I hope the ministry will strengthen the digitalisation of data backup systems and access controls so that such matters do not recur. I also request the ministry to give attention to land acquisition and compensation payments, including ensuring that landowners in Beaufort who have not yet received compensation are given claim status, reasons for the delay and a clear settlement period. Mr Speaker, I would like to link the findings of this Auditor General's Report with an issue that is very close to the people of Beaufort, namely the recurring problem of floods. In this report, we see an integrated river basin development approach in the Sungai Golok that does not only build one structure but involves riverbanks, protective walls, water control structures and river improvements as a comprehensive solution. In my view, this approach is very relevant for Beaufort. Beaufort depends on the Padas River system and the people often face floods when prolonged heavy rain occurs in the upstream areas. The impact is not only on the people or residential houses but also affects access roads, schools, economic activities, agriculture and the people's sources of income. We actually already have an integrated river basin management plan or IRBM for the Padas River, completed in 2018, containing 24 strategies and 67 action programmes with an estimated cost of RM2.1 billion. Give me a little more time, Mr Speaker.

Satu minit.

The government has also informed that the RTB Padas River began in November 2024. Accordingly, I request that the implementation of the RTB Padas River be coordinated with the drainage system, Beaufort town development and flood control measures in the village areas so that everything moves under one integrated flood resilience framework. Mr Speaker, the audit findings provide an important lesson. The success of a project is not measured only by the amount of allocation or the projects approved but by the ability of the project to deliver real benefits to the people.

For Beaufort, the Pan Borneo issue and flood resilience are the main matters that need serious attention. For this reason, I request that the government provide a clear timeline so that the people not only know what is planned but can also know when the benefits can be enjoyed. Thank you.

Thank you, Honourable Beaufort. Okay, now our last debater, please proceed, Honourable Balik Pulau.

Thank you, Mr Speaker. Bismillahirrahmanirrahim. I stand to take part in the debate on the Auditor General's Report Series 2, Year 2026. Generally, for me, the Auditor General's Report is not merely a report on government expenditure; it is an important mechanism for us to see whether the people's money that is spent truly produces results and benefits for the people. Generally, when an audit is carried out, it has actions that need to be taken. It should not just remain as a report but all the recommendations, all the directives and requests in the audit must be acted upon. In this context, I would like to touch on the Pan Borneo Highway Project in Sabah. Because of insufficient time, I will only speak about the Pan Borneo Highway Project. Mr Speaker, this project involves an alignment of 706 kilometres and is divided into 35 work packages. Originally, this project was planned to be completed within 69 months, from April 2016 to 31 December 2021. However, as of 31 March 2026, after nearly 10 years, the project is still not fully completed. Out of 35 work packages, only four packages or 11.4 percent have been completed. The remaining 31 packages or 88.6 percent are still under implementation. What is more worrying, of these 31 packages, nine are categorised as troubled projects. 13 are behind schedule and only nine are ahead of schedule. For me, these figures are very worrying. The question is, after nearly a decade, why has most of the packages still not been completed? Is the problem in planning, contract management, contractor capability, coordination between agencies, or project monitoring?

Mr Speaker, we also need to look at the comparison with Sarawak. The Pan Borneo Sarawak Phase 1 involves an alignment of around 786 kilometres. That is further than the one in Sabah, and 11 work packages. As of 31 March 2026, 10 of those 11 packages have been fully completed. Meanwhile, the remaining one package, WP11, has reached 99.9 percent progress. This shows that almost the entire Pan Borneo Sarawak alignment has been completed and opened in stages to users. I understand the implementation challenges in Sabah and Sarawak are not necessarily the same, but this difference in performance still raises reasonable questions that we should answer. What did Sarawak do more effectively? And what practices can we learn from them to accelerate Pan Borneo Sabah? Is it in terms of planning, work package structure, inter-agency coordination, contract management or monitoring? I hope the Ministry of Works can make this comparison systematically and identify best practices that can be applied in Sabah. Mr Speaker, the second issue is cost. The total contract cost of the project has increased from 17.910 billion to 18.960 billion. This is the people's money, yes. For Phase 1A of Pan Borneo Sabah, the time cost is estimated at 11.323 billion, that is 987 million or 95 percent higher than the original ceiling cost of 10.336 billion. As of 31 March 2026, a total of 11.153 billion has been disbursed and 10.547 billion, 94.6 percent, has been spent. With figures this large, we not only need to ask how much has been spent, we need to ask what results the people have received from that expenditure? I understand that Sabah Members of Parliament raised the Pan Borneo Sabah matter because they are under pressure from questions from the people of the districts they represent. Because this delay is not only about road construction. Pan Borneo should be the economic driver of Sabah. Connecting urban and interior areas. Facilitating the movement of goods, opening access to markets, boosting the trade, agriculture, tourism and agro-tourism sectors. When this project is delayed, the economic benefits are also delayed for the people. So, we need to look not only at project costs but also at the opportunity cost of project delays. Mr Speaker, for me, one minute.

Satu minit.

I would like to put four questions to the government. First, what

proactive steps will the Federal Government take together with the Sabah State Government to ensure the remaining Pan Borneo packages can be completed according to the new schedule? Second, what is the actual cause of the delay for packages that are still behind and what action will be taken against those who fail to meet the targets, including the contractors appointed? Third, has the Ministry of Works made a systematic comparison between Sabah and Sarawak in terms of planning, contract management, agency coordination and monitoring? If so, what Sarawak best practices can be applied in Sabah? Fourth, how much longer must the people of Sabah wait to enjoy the economic benefits that are among the main justifications for building this Pan Borneo? And if the new target is again not achieved, who will be responsible? Mr Speaker, I am not raising these matters to blame any party. We all want to see Pan Borneo completed, Pan Borneo Sabah completed and providing benefits to the people. But after nearly 10 years with rising costs and most packages still not finished, the people have a right to clear answers, realistic schedules and clear accountability. Because ultimately, the success of a government project is not measured by how much money has been spent but by how many benefits finally reach the people. Thank you, Mr Speaker.

Thank you, Honourable Balik Pulau. With the debate by Honourable Balik Pulau just now, our debating session for today is complete. A total of 31 Honourable Members have debated and now it is the turn of the Honourable Ministers to respond. In front of me is a list of ministries. There are 16 ministries that will respond, and we will begin with the Ministry of Finance for 10 minutes. Please proceed.

Tuan Liew Chin TongDAP · PHDeputy Minister of Finance · Iskandar PuteriEN

Thank you, Madam Speaker. As the first ministry to wind up, I take this opportunity to record my thanks to all Honourable Members who took part in the debate on the Auditor General's Report Number 2, Year 2026 just now.

Tuan Liew Chin TongDAP · PHDeputy Minister of Finance · Iskandar PuteriEN

A total of 31 Honourable Members have debated various matters involving various ministries. The focus of my winding-up is on providing explanations on the issues relating to the Ministry of Finance raised in the Auditor General's Report and touched upon by nine Members in the debate session. All the views, criticisms and suggestions given by the Honourable Members are greatly appreciated. Madam Speaker, the Federal Government's Financial Statements for the year ended 31 December 2025 were given the certificate of the Auditor General with an unqualified opinion, with an emphasis of matter paragraph (other matters), with permission, an unmodified opinion. This means that the financial statements show a true and fair view, with permission, of the financial position of the Federal Government audited, in accordance with the accounting standards and the laws in force. However, the National Audit Department also raised several audit findings in its report covering a few key issues, for which the government needs to take appropriate action, including involving the Ministry of Finance directly. The three main matters relating to the Ministry of Finance that were identified and also drew the attention of the Honourable Members in the debate session are as follows.

Tuan Liew Chin TongDAP · PHDeputy Minister of Finance · Iskandar PuteriEN

(i) efforts to enhance action to collect arrears of various Accounts Receivable (ABT); (ii) the position and management of the Federal Government's debt; and (iii) questions regarding the position and statistics of arrears of loans recoverable by the Federal Government. Madam Speaker, the government has taken note of the position of the Accounts Receivable (ABT) of LHDN, or the Inland Revenue Board of Malaysia, and continuous action is being implemented to ensure tax arrears are managed systematically and effectively. Of the total ABT balance, RM23.145 billion or 57.8 per cent involves cases in legal proceedings, namely in court or deferment and appeals. Meanwhile, RM16.842 billion or 42.11 per cent are cases actively under collection and instalment action, including audit and investigation cases. This position shows that a large part of the ABT is subject to legal proceedings or deferment.

Tuan Liew Chin TongDAP · PHDeputy Minister of Finance · Iskandar PuteriEN

To control and reduce the ABT balance, LHDN is intensifying the management of current debts and revenue arrears through repeated digital reminders, proactive calls, CP38 automation, early issuance of demand letters, premises visits and instalment payment negotiations. For cases that have matured or are chronic, enforcement actions such as travel restrictions, caveats by registrars and appointment of agents are being enhanced according to case suitability. At the same time, an ABT management task force by LHDN has been established to monitor the debit balance, including from audit and investigation assessments, as a step to curb the formation of new arrears and optimise the national revenue collection. Madam Speaker, allow me to provide feedback on the issue raised regarding the position and statistics of arrears of loans of the Federal Government. For the information of the Honourable Members, the position of outstanding loan repayments as at 31 December 2025 recorded a total of RM8.084 billion. This amount comprises principal arrears totalling RM5.709 billion and interest arrears and late interest totalling RM2.375 billion. The percentage of these arrears stands at 15.67 per cent. This amount is manageable and has been decreasing compared to the average of 21 per cent for the period 2020 to 2022. These arrears are largely made up of loans for public basic infrastructure projects covering clean water supply projects, sewerage, public housing, low-cost public housing and public transport, and so on. The borrower category recording the highest loan arrears is companies at 62 per cent, followed by state governments at around 32 per cent. The government is always continuously striving to improve loan repayment capacity, particularly through, firstly, the restructuring process based on an assessment of the borrowers' financial capacity, current level of dependency and cash flow projections. This is to ensure borrowers are able to fulfil their financial obligations by reducing the total repayment commitment through extending the repayment period and without affecting the delivery of services to the people, because these are statutory bodies or companies under the government or state governments. Secondly, write-off action for loans will be considered based on the following criteria, namely after all loan recovery efforts, including legal action, have been taken against the borrower and have not yielded results

Tuan Liew Chin TongDAP · PHDeputy Minister of Finance · Iskandar PuteriEN

to the government, all exhaustive effort has been taken. Only loan interest is considered for write-off, and only companies certified as insolvent based on reports of the Companies Commission of Malaysia (SSM) and after obtaining the views of the Legal Division, Ministry of Finance. Thirdly, mandatory viability assessment and loan limits. The existing loan evaluation model is enhanced by introducing a mandatory viability or feasibility assessment before any approval is given. Loan approvals will be limited according to the actual repayment capacity if the borrower's capacity is limited, and the remaining project financing balance is proposed to be channelled in the form of grants. Assessment of social and commercial projects. The Ministry of Finance recommends to the Ministry of Economy that any projects of a social obligation nature be channelled through development allocations or DE in the form of grants rather than commercial loans. A mandatory condition of asset collateral for new loan applications involving state governments or companies Menteri Kewangan (Diperbadankan) [MKD], the government requires the submission of collateral such as land assets equivalent to the loan value to enable claims to be made in the event of default. Notice of Change of loan approval, Notice of Change (NOC) for loans approved in the current year but whose allocations have not been spent within the stipulated period, is proposed to the controlling ministries to redistribute loan allocations or restrictions through NOC with the approval of the Ministry of Economy and continuous engagement or consultation and legal action. The ministry is strengthening continuous consultation with borrowers so that outstanding loan repayments can be scheduled and restructured. Meanwhile, legal action is maintained as a last-resort solution considering that most borrowers are state governments, statutory bodies and companies implementing projects of a social nature for the benefit of the people and the nation. Madam Speaker, allow me to provide feedback on the issue raised regarding the position of debt management of the Federal Government. There are two or three more pages. My apologies. For the information of the Honourable Member, the government remains committed to implementing fiscal reform measures to

Tuan Liew Chin TongDAP · PHDeputy Minister of Finance · Iskandar PuteriEN

provide sustainable fiscal space, thereby ensuring prudent debt management in line with the Public Finance and Fiscal Responsibility Act 2023 or Act 850 and the MADANI Economy framework. Act 850 sets out fiscal objectives and targets that must be complied with, including a fiscal deficit target not exceeding three per cent of GDP and a debt level not exceeding 60 per cent of GDP in the medium term. The government's efforts to implement fiscal consolidation have successfully reduced the deficit rate consistently every year, from 5.5 per cent in 2022 to 3.7 per cent in 2025. The reduction in the deficit rate also means that new borrowings have decreased from RM100.3 billion in 2022 to RM75.6 billion in 2025, thereby slowing the growth rate of the Federal Government's debt from 10.2 per cent in 2022 to 5.9 per cent in 2025. As of end-2025, the Federal Government's debt has recorded RM1,320.8 billion or 65.2 per cent of GDP compared to 64.5 per cent of GDP at the end of 2024.

Tuan Liew Chin TongDAP · PHDeputy Minister of Finance · Iskandar PuteriEN

In ensuring that debt is always at a manageable level, the government remains disciplined and compliant with all statutory debt limits stipulated under the legislation relating to debt.

You may wind up, Honourable Member.

Tuan Liew Chin TongDAP · PHIskandar PuteriEN

Yes. Just a little, okay. These are important facts. Statutory debt as at end-2025, which includes the aggregate amount for the instruments of Malaysian Government Securities (MGS), Malaysian Government Investment Issues (MGII) and Malaysia Islamic Treasury Bills (MITB), stands at 63.9 per cent of GDP, which is still below the 65 per cent limit stipulated by the Loans (Local) Act 1959 and the Government Funding Act 1983. Offshore external loans amount to RM21.1 billion, well below the RM35 billion ceiling under the External Loans Act 1963. Malaysian Treasury Bills amount to RM4.5 billion, remaining below the RM10 billion limit under the Treasury Bills (Local) Act 1946. The government will continue to implement various fiscal reform measures to ensure the fiscal objectives under Act 850 can be achieved without affecting the welfare of the people. These include implementing gradual fiscal consolidation, optimising public expenditure, strengthening the sustainable foundation of government revenue and implementing institutional reform of the public service

Tuan Liew Chin TongDAP · PHIskandar PuteriEN

that supports and reinforces the national development agenda. Thank you, Speaker.

Thank you, Honourable Minister. I now invite the Ministry of Energy Transition and Water Transformation (PETRA) to proceed. Please proceed, Honourable Member, 12 minutes, okay, Honourable Member.

Dato’ Sri Haji Abdul Rahman bin Haji MohamadUMNO · BNDeputy Minister of Energy Transition and Water Transformation · LipisEN

Thank you, Honourable Speaker. First of all, I would like to record my highest appreciation and thanks to the Honourable Members who have debated the Auditor General's Report (LKAN) Number 2/2026. I would also like to emphasise that the tabling of the Auditor General's Report in the Dewan Rakyat is a practice of checks and balances in strengthening the accountability of governance and the effectiveness of government service delivery to the people. For the information of the Honourable Speaker, the Ministry of Energy Transition and Water Transformation (PETRA) is involved in two audit subjects under LKAN Number 2/2026, namely the management of the Sungai Golok, Kelantan Integrated River Basin Development Project (PLSB) and the management of the Coastal Shoreline Rehabilitation Programme. PETRA takes seriously the issues relating to the scope and field of duties of PETRA that were raised by the Honourable Members in today's debate. Honourable Speaker, allow me to answer and provide explanations on the issues raised in this LKAN debate session specifically. The Honourable Member for Rasah, Rantau Panjang, Tumpat and Jerantut raised the issue of the Sungai Golok PLSB, while the Honourable Member for Kuala Terengganu and Kuala Nerus raised the issue of coastal shoreline conservation. Allow me to answer the main issues under the LKAN. First, I would like to inform on the latest status of the implementation of the works for the phases of the Sungai Golok Integrated River Basin Development Project. The physical progress of Phase 1 is 73.01 per cent compared to 75.51 per cent scheduled for completion on 21 July 2027. Meanwhile, Phase 2 recorded physical progress of 3.16 per cent compared to 2.62 per cent scheduled, while Phase 3 achieved 24.18 per cent compared to 16.87 per cent scheduled. Both phases are ahead of their respective schedules and are targeted for completion within the contract period

Dato’ Sri Haji Abdul Rahman bin Haji MohamadUMNO · BNDeputy Minister of Energy Transition and Water Transformation · LipisEN

namely on 14 October 2028 for Phase 2 and 24 April 2029 for Phase 3. Phases 2 and 3 will complete the flood protection component under Phase 1. PETRA takes note of the audit finding regarding the increase in the contract value of the projects from RM198.202 million to RM601.20 million. This increase involves, among others, adjustments to scope based on technical requirements and current conditions throughout the implementation of the project, including the upgrading of Jalan Kesman to federal road standards, spillway structures, bridge construction and coordination of pump house design. The adjustment of scope and design was carried out to ensure the infrastructure meets the functional requirements of safety and long-term resilience, including taking into account extreme weather risks and climate change. The implementation of the project was also affected by on-site technical constraints including utility relocation, land acquisition and coordination of construction drawings. This approach is important to ensure residents, property and public infrastructure in areas exposed to flood risk continue to be protected. To address the weaknesses raised in LKAN Number 2/2026, the Ministry of Energy Transition and Water Transformation through the Department of Irrigation and Drainage (JPS) has taken and is taking follow-up action and project management improvements to ensure the flood protection objectives can be achieved. First, a taskforce at the JPS level has been established to monitor project progress, identify implementation issues and problems that arise, and ensure every audit criticism and audit recommendation is acted upon and resolved effectively. In fact, I myself will personally go down to see the current developments and progress of this project, and I welcome the Honourable Members to join me in the project site visit at the end of this week. Second, coordination at the state level has been strengthened through the establishment of a task team to expedite land acquisition for flood mitigation projects in Kelantan. This measure aims to ensure land issues are addressed earlier to facilitate the smooth implementation of works on site. Third, JPS has strengthened early planning and readiness checks of the project, including from the aspects of technical requirements, design and land investigation. These improvements aim to ensure these matters are finalised before physical work begins, thereby reducing the risks of scope changes, cost increases and project delays. Fourth, JPS has improved the terms of reference (TOR), appointment of consultants, including stipulating the obligation to comply with JPS directives during the home-office support phase. This measure clarifies the consultants' responsibilities in providing technical support and resolving issues throughout the project implementation. Apart from the implementation of the main components of the Sungai Golok PLSB, several short- and medium-term mitigation measures are being carried out to reduce flood risks while awaiting the completion of the entire project. First, dredging works of the Sungai Lemal–Lanchang to increase river capacity and accommodate excess water during heavy rain. Second, transformation of the function of Danau Tok Uban into rainwater control and flood retention in the upstream of Sungai Lemal–Lanchang. Third, procurement and installation of mobile flood barriers, flood barriers in high-risk areas as a temporary protection measure to reduce the entry of flood water into settlement areas. Fourth, dredging of the Sungai Golok estuary to facilitate the outflow of river water into the sea. Honourable Speaker, with regard to the Coastal Shoreline Rehabilitation Programme, I would like to inform on the latest status of the projects raised in LKAN Number 2/2026. For the Kuala Nerus, Terengganu Coastal Erosion Control Project, as at 17 September 2026, the physical progress reached 60.9 per cent compared to 60.7 per cent based on its implementation schedule, checked against the project completion date on 28— 2027. For the Marang Coastal Erosion Project, the notice of termination of the contractor's employment was issued on 9 July 2024. The implementation of the scope of this project is continued through the Rusila, Marang, Terengganu Coastal Erosion Control Project, which is expected to commence in March 2026–2028, with an implementation period of 45 months.

Dato’ Sri Haji Abdul Rahman bin Haji MohamadUMNO · BNDeputy Minister of Energy Transition and Water Transformation · LipisEN

finalised before physical work begins, thereby reducing the risk of scope changes, cost increases and project delays. Fourth, the JPS has improved the terms of reference (TOR) and the appointment of consultants, including specifying the obligation to comply with JPS directives during the home-office support phase. This measure clarifies the consultants' responsibilities in providing technical support and resolving issues throughout project implementation. Apart from the implementation of the main components of the PLSB Sungai Golok, several short- and medium-term mitigation measures are being taken to reduce the risk of flooding while awaiting completion of the entire project. First, excavation works at the Sungai Lemal–Lanchang to increase the river's capacity and accommodate excess water during heavy rain. Second, the transformation of the function of Danau Tok Uban into rainwater control and flood retention at the upstream of Sungai Lemal–Lanchang. Third, the procurement and installation of portable flood barriers, flood barriers, in high-risk areas as a temporary protective measure to reduce the entry of flood water into settlement areas. Fourth, dredging of the Sungai Golok river mouth to facilitate the outflow of river water to the sea. Honourable Mr Speaker, regarding the Coastal Rehabilitation Programme, I would like to inform the House of the latest status of the projects raised in the Auditor-General's Report (LKAN) Number 2/2026. For the Coastal Erosion Control Project at Pantai Kuala Nerus, Terengganu, as of 17 September 2026, the physical progress reached 60.9 percent compared with 60.7 percent based on its implementation schedule, check against the project completion date of 28— 2027. For the Marang Coastal Erosion Project, a notice of termination of the contractor's employment was issued on 9 July 2024. The implementation of the project's scope is continued through the Rusila, Marang, Terengganu Coastal Erosion Control Project, which is expected to begin in March 2026–2028, with an implementation period of 45 months.

Dato’ Sri Haji Abdul Rahman bin Haji MohamadUMNO · BNDeputy Minister of Energy Transition and Water Transformation · LipisEN

Delays caused by the contractor's failure and not qualifying for an extension of time, contractual action including the imposition of LAD will be taken in accordance with the contract terms.

Dato’ Sri Haji Abdul Rahman bin Haji MohamadUMNO · BNDeputy Minister of Energy Transition and Water Transformation · LipisEN

For specific questions of the Honourable Members regarding projects in their respective areas, answers will be provided separately. This takes into account the time constraints and the focus of this winding-up session on the issues raised in LKAN Bil. 2/2026. PETRA appreciates the role of the National Audit Department and the views of the Honourable Members. All criticisms will be used as a guide to improve governance to ensure public funds are managed prudently and to avoid recurrence of the same issues in the future. Thank you, Honourable Speaker.

Thank you, Honourable Deputy Minister. Next, I turn to the Ministry of Transport. Please proceed, Honourable Member.

Datuk Haji Hasbi bin Haji HabibollahPBB · GPSDeputy Minister of Transport · LimbangEN

Thank you, Speaker. Bismillahirrahmanirrahim, assalamualaikum warahmatullahi wabarakatuh. Mr Speaker, for the information, the Honourable Member for Jerantut and also the Honourable Member for Parit have raised the issue of the management of the Special Trust Account of the Marine Department of Malaysia. The Ministry of Transport takes note of and takes seriously the criticism of the National Audit Department regarding the payment of allowances and facilities amounting to RM2.55 million from the Light Dues Fund (KWDA) and the Marine Trade Centre Fund (KWPPL) which were found to not have a clear source of authority. MOT together with the Marine Department is taking action to clarify the source of authority, the approval mechanism and the governance of such payments in line with the recommendations of the National Audit Department. In understanding this allocation, it is also important for us to look at the history of the establishment and development of the Light Dues Board. The statutory basis of the Light Dues Board has existed since 1953 through the Malayan Federation Light Dues Ordinands No.24 of 1953, with permission. The ordinance came into force on 30 April 1953 and since then has established the Light Dues Board, Light Dues Fund and the administration of the fund by the board. After independence, this legislative framework was continued in 1958 through the Federal Constitution (Modification of Laws) (Ordinances and Proclamations) Order 1958 (L.N. 332/58), with reference to the High Commissioner in the ordinance adapted to the Minister responsible for merchant

Datuk Haji Hasbi bin Haji HabibollahPBB · GPSDeputy Minister of Transport · LimbangEN

shipping. In 1961, the Federation Light House (Amendment) Bill 1961 went through the Parliamentary process. The Dewan Rakyat passed it on 21 June 1961, and the Dewan Negara passed it on 26 June 1961 without amendment. The amendment was subsequently enacted as the Federation Light Deus (Amendment) Act 1961 (Act 21/1961) after receiving royal assent on 19 July 1961. Then, in 1981, the Ordinance of 1953 was revised and published as the Federation Light Dues Act 1953 [Act 250], with the revised text coming into force on 25 June 1981. However, this is a statutory continuation of the legal framework that had existed since 1953. Based on the legal view of the Ministry of Transport, although Act 250 does not expressly provide for the payment of allowances to the chairman and members of the Light Dues Board, there is a basis for considering expenditure that is directly related to the performance of the Board's statutory functions as administrative expenditure of the KWDA. However, that interpretation cannot be extended to payments that have no connection with the Board's statutory functions. The legal view also refers to the official record of the Federal Legislative Council dated 19 March 1953 during the second reading of the Federation Light House Bill 1953. In that debate, Mr R. B. Carey, Member of Works and Housing, explained that the provision and maintenance of navigational aids involved large costs. Among the expenditures stated at that time were maintenance and salaries, uniform allowances, and rations for lighthouse staff. In the same speech, he also explained that the bill proposed the introduction of Light Dues and the establishment of a fund to be administered by the Light Dues Board. Mr Speaker, I have to cut my explanation short. It's quite a bit. May I have another five minutes?

Five minutes? Three minutes, Honourable Member.

Based on that record, the Legal Advisory Unit (PUU) of the Ministry holds the view that the mention of salaries, allowances and facilities for lighthouse workers as part of the annual estimated expenditure relating to lighthouses may give rise to an inference that such expenditure is incurred expenses that are related.

In this regard, the Ministry takes into account that the chairman and members of the Light Dues Board carry out statutory responsibilities relating to the management of the KWDA and the provision of navigational aids. Nevertheless, the Ministry has received an audit comment that the mechanism and source of authority for payments need to be clarified. Accordingly, the Light Dues Board is conducting a comprehensive review of the types of allowances and facilities, including the functions performed. The applicable rates, prior approvals, and current needs will be reviewed, and Act 250 and related regulations will be examined to identify any amendments needed, if required. At the same time, the Ministry needs to consider the operational implications should payments relating to the KWDA be halted for an extended period. These include the continued operation of VTS, VTMIS, PUSKAU and PUSKOM, which operate on a 24-hour shift basis, maritime safety management, and the maintenance of navigational aids in the Straits of Malacca, where nearly more than 100,000 ships pass through the Straits of Malacca in a year. The Ministry also takes into account the responsibilities and liabilities borne by board members, and the importance of implementing strategic projects such as the Northern Shoal Beacon Strengthening Project. The LDA has already agreed to channel funds amounting to RM23.5 million to the National Security Council, Prime Minister's Department, should the relevant decisions or allocations be delayed, as the project could be delayed and stalled. As for the KWPPL, this fund is a statutory fund established under section 46(7) of the Merchant Shipping Ordinance 1952, or MSO 1952, and is administered under the Merchant Shipping (Central Mercantile Marine Fund) (CMMF) Rules 1984. The position of the KWPPL was also previously considered by the Cabinet in 1992 through the restructuring of the administration of the KWPPL's officers and staff. The KWPPL committee and the fund itself were decided by the Cabinet to be retained and to continue carrying out their functions as provided by law. I'll cut it short. Let's go to the end.

Terima kasih.

Following the audit comment, the Ministry does not reject the need to streamline the KWDA payment mechanism. To ensure there is no longer any room for differing interpretations, the Ministry, together with the AGC (JLM),

will clarify the legal basis, eligibility conditions, rates and approval mechanisms for every type of account and facility. If amendments to Act 250 or related regulations are necessary, they will be considered after a comprehensive review is carried out. In conclusion, the Ministry of Transport wishes to emphasise that the improvement measures being implemented do not amount to an admission that all payments made previously were without legal authority. Rather, the Ministry of Transport takes the audit comment seriously and is committed to streamlining, clarifying and strengthening the governance of the KWDA and KWPPL so that every future payment has a clear, orderly and auditable legal basis, policy, eligibility conditions, rates and approval mechanisms. At the same time, the Ministry of Transport will ensure that both funds continue to carry out their respective statutory functions and purposes in a transparent, accountable and effective manner. Thank you.

Thank you, Honourable Deputy Minister of Transport. Next, I would like to invite the Ministry of Housing and Local Government. Please proceed, Honourable Minister.

Tuan Nga Kor MingDAP · PHMinister of Housing and Local Government · Teluk IntanEN

Thank you, Mr Speaker. Greetings of peace, greetings of unity, and Malaysia MADANI greetings.

Tuan Nga Kor MingDAP · PHMinister of Housing and Local Government · Teluk IntanEN

First of all, allow me to record our highest appreciation to the National Audit Department for preparing the Auditor General's Report No. 2/2026. The PKPT Ministry welcomes the tabling of the Federal Government Financial Statements Report for 2025 and also all the activities of the ministry in this august House. The initiative to debate the Auditor General's Report in this august House clearly shows the continued commitment of the MADANI Government to strengthen governance based on the principles of transparency and accountability, as well as credible governance for the development of our beloved nation.

Tuan Nga Kor MingDAP · PHMinister of Housing and Local Government · Teluk IntanEN

KPKT is committed to upholding the principles of integrity and accountability in ensuring that every public expenditure is managed efficiently, prudently and in compliance with the prescribed fiscal controls. Accordingly, only three issues were raised in this Auditor General's Report, and all of them are long-standing problems that have now been resolved. However, even though these are longstanding problems, the MADANI Government does not intend to point fingers; rather, we are seeking ways to rectify and also prevent the same problems from recurring in the future. The first matter is the Kampung Selagon People's Housing Programme (PPR), Beaufort, Sabah. With regard to the issue that has been raised, for the information of Mr Speaker and also the Honourable Members, Sabah is the state with the highest number of PPR project implementations across Malaysia, and a total of 39 PPR projects have been approved by the government, involving 26,299 housing units. Of this total, 37 PPR projects involving 25,449 housing units have been successfully built. Next, in Sabah there are two projects involving 850 housing units that are still at the planning stage. Specifically regarding the PPR Taman Permai Selagon. This project was approved under the Tenth Malaysia Plan with a construction scope of 67 single-storey terraced housing units together with public facilities, at an original contract value of RM23.7 million. Construction work commenced on 21 December 2012 and was completed on 23 June 2017. However, Mr Speaker, this completed project could not be handed over or occupied due to the confirmation of several very critical technical issues. An investigation by KPKT through JKR Malaysia found a serious structural crack problem in one terraced block housing eight housing units. In addition, five other housing units in a separate block have also experienced moderate periodic cracking due to land subsidence, which has affected the stability and structural integrity of the entire building. To address this issue, the government appointed a second contractor in April 2022 for repair works involving the demolition and reconstruction of the severely affected housing units. However, even though the demolition work for the eight housing units has been completed, the land movement problem continued to occur. This has caused

Tuan Nga Kor MingDAP · PHMinister of Housing and Local Government · Teluk IntanEN

the work to be unable to be completed, and the rescue contractor had to be terminated through a settlement agreement on 11 March 2025. Mr Speaker, recognising that this structural failure is not merely ordinary damage, KPKT, with the technical cooperation of JKR Malaysia and JKR Sabah, has taken comprehensive proactive steps by carrying out forensic testing and geotechnical investigation over the period from October 2024 to May 2025. This lengthy review period was necessary to comprehensively analyse the soil profile and thereby identify the main causes, so that the Ministry can formulate a concrete and safe new direction. The findings of the geotechnical analysis revealed that the main cause of the structural failure was the uneven soil strata profile at the construction site. This condition worsened, and the presence of soft soil layers and high organic content directly triggered soil instability due to uneven settlement. The soil investigation findings were further strengthened through the implementation of structural integrity tests, which were carried out in two phases from August 2025 until May this year. The main phase of the comprehensive coverage test included the surrounding area and involved six PPR residential blocks, while the second phase covered business lots, business halls, a surau and two other residential blocks. Overall, the laboratory analysis from both phases of testing confirmed that the actual compressive strength of the concrete was uneven and failed to reach the design strength level. Based on these findings, the study is evaluating in detail how several proposed solutions and the appropriate technical approaches will be finalised in the near future. This careful step is taken meticulously to ensure that every decision made later is able to provide a thorough, effective and fair long-term solution. Mr Speaker, the MADANI Government through KPKT is always vigilant and concerned about the welfare of the nation's red heroes. This will be about the second issue, namely the reconstruction of the quarters of the Fire and Rescue Station, Semporna, Sabah. To note, the project to rebuild the quarters of the Fire and Rescue Station in Semporna, Sabah is a project valued at RM14.39 million, with an original contract period from 2 January 2020 to 9 December 2021. In this matter, five extensions of time have been granted, with a new completion date of 15 February 2025. The justification for approving these EoTs was, among other things, due to problems with cement supply and piling work at the site that required

Tuan Nga Kor MingDAP · PHMinister of Housing and Local Government · Teluk IntanEN

additional soil investigation work, as well as changes to the foundation design of the building. This project was terminated on 11 March 2025, with 25 per cent progress achieved, due to the contractor's financial incapacity, failure to carry out work according to the programme, and weaknesses in management and supervision. As of 13 February 2025, a total of RM2.83 million had been spent. For the information of this august House, this project has been re-tendered to appoint a rescue contractor. In addition, the ministry has considered the eGPA application to the Ministry of Finance to seek approval for open tender procurement and exemption from the requirement for a contractor's completion certificate, expected on 12 October 2026. The ministry expects the SST date to be in December this year as well. The final issue, Mr Speaker, is the construction project of the Fire Station and Quarters in Merotai, also in Sabah. Three projects, three issues, all in the state of Sabah, Mr Speaker. Next, this fire station construction project in Merotai involves RM6.85 million, with an original contract period from 25 November 2019 to 17 May 2021. Seven extensions of time have been granted, with a new completion date of 29 September 2024. The justifications for approving the EoTs included factors such as the movement control order, amendments to the sewerage plan design, and changes to the platform level. This project was terminated on 5 November 2025 with 99.6 per cent completed. The termination was due to the contractor's financial incapacity and failure to complete the work on schedule. A total of RM6.7 million has been spent. The contractor has also been fined LAD amounting to RM686,000. Mr Speaker, to ensure the continuity of a project that benefits and cares for the welfare of the red heroes, this project has been re-tendered to appoint a completion contractor, and the project was taken to the procurement meeting on 23 September 2026. The ministry has submitted the eGPA application to the MOF to seek approval for procurement. I expect the SST date to also be this year, in December. To conclude, KPKT is always open to receiving every criticism, view and suggestion from the Honourable Members who have touched on issues related to KPKT through the debate on the Auditor General's Report.

Tuan Nga Kor MingDAP · PHMinister of Housing and Local Government · Teluk IntanEN

This advisory document serves as a catalyst for the MADANI Government to continue strengthening, firmly reinforcing its resolve, and enhancing its spirit, so that the implementation of development policies grounded in the principle of integrity remains upheld. I must stress here that the issues raised in this Auditor General's Report are all old matters. They have dragged on since the previous government's administration. However, the MADANI Government through KPKT does not intend to point fingers; rather, we remain committed and proactive in pursuing the best solutions for the welfare of the people. This is our resolve, and this is the promise that we will continue to fulfil. This step is in line with the stance of the MADANI Government, which is determined to build a governance system that is clean from waste and immune from leakage. KPKT is determined to ensure that every project planned becomes clear proof of the trust of the people, and at the same time drives fiscal excellence with integrity. As the saying goes, "Remember before it happens, save before it runs out." Governance and prudent financial management are the main pillars of KPKT. To achieve this noble aim, the ministry will continue to tighten internal controls, strengthen compliance with financial procedures, and ensure that every ringgit of public expenditure returns fair value to the people.

Please wind up, Honourable Member. Sum up, Honourable Member.

Tuan Nga Kor MingDAP · PHTeluk IntanEN

Our goal is quite simple, which is to ensure that all agencies under the ministry obtain a clean certificate. As the proverb goes, "A round thing does not come rolling, a flat thing does not come floating." Public confidence in the competence and integrity of management can only be built through an uncompromising commitment. In conclusion, KPKT records its appreciation to the Auditor General for the audit that has been carried out. At the same time, I extend my thanks to the Honourable Members for their sharp views and very constructive comments. May this continued synergy become a firm pillar for sustained and integrity-based financial governance, in order to uphold the welfare of the people and raise the prosperity of the nation in line with the Malaysia MADANI Aspiration. Thank you.

Alright, thank you, Honourable Minister. Next, I would like to invite the Ministry of Foreign Affairs. Please proceed, Honourable Deputy Minister.

Dato Lukanisman bin Awang SauniPBB · GPSDeputy Minister of Foreign Affairs · SibutiEN

Thank you, Mr Speaker. Bismillahirrahmanirrahim. Assalamualaikum warahmatullahi wabarakatuh. Greetings of peace and Malaysia MADANI greetings. Mr Speaker, first of all, thank you, Mr Speaker, for giving me the opportunity to respond to matters relating to the Ministry of Foreign Affairs (KLN) during the winding-up session of the debate on the Auditor General's Report in this august House. For the information of the House, I will give a summary of the findings obtained by the LKAN. There are 10 issues raised, namely concerning staffing of positions, surprise inspection AP309, collection procedures, payment instructions, review of the Vote Book, asset registration, stock recording, permission to take movable assets out for maintenance, vehicle logbooks, and also fuel indent cards. I take this opportunity to record my highest appreciation and thanks to the Honourable Member for Kota Bharu, who is concerned about developments closely related to the Ministry of Foreign Affairs. The Honourable Member for Kota Bharu, in his speech, was of the view that the matters involving KLN raised in LKAN 2/2026 concerning the audit of Malaysian Representative Offices overseas are of a daily administrative nature and should appropriately be addressed through the audit unit within the ministry. The Honourable Member for Kota Bharu also sought views on the suitability of those matters being reported by the National Audit Department of Malaysia. The Auditor General's Report to Parliament should focus on matters that have strategic and national impact. In this regard, the Ministry of Foreign Affairs welcomes audit examinations from the National Audit Department. This step is appropriate as an instrument of checks and balances in ensuring that the management and financial governance of Malaysian Representative Offices overseas are more transparent, accountable, and compliant with current financial and procurement procedures and regulations in force, and that the ministry always takes improvement measures based on the said report.

Dato Lukanisman bin Awang SauniPBB · GPSDeputy Minister of Foreign Affairs · SibutiEN

Mr Speaker, before I conclude this report, I would also like to explain the issue of staffing positions at the Malaysian Diplomatic Missions abroad. Mr Speaker, the Ministry of Foreign Affairs has always paid serious attention to the audit observations regarding staffing positions at several Malaysian Diplomatic Missions abroad that still cannot be fully filled, such as in Jakarta and also Beijing. The Ministry is of the view that this issue needs to be viewed comprehensively, given that the placement of officers at Diplomatic Missions outside Malaysia is made by taking into account the existing financial allocations and human resources of the Ministry. This vacancy is caused by various factors, including the temporary freezing of recruitment for several schemes in the public service. The issue of manpower shortage is in fact also faced by all ministries and agencies, including the Ministry of Foreign Affairs. To face this challenge, the Ministry of Foreign Affairs must continue to optimise its existing manpower so as to ensure that all diplomatic and administrative functions can be carried out effectively. The planning of the placement of officers at Malaysian Diplomatic Missions abroad is made from time to time based on the interests of the service, taking into account the priorities of bilateral relations as well as the needs and direction of foreign policy. At the same time, the filling of positions abroad is also subject to the control and approval of central agencies such as the Public Service Department (JPA) and the Ministry of Finance, to ensure that it is in line with the public service remuneration policy and the financial capacity of the Government. In this regard, the Ministry is working closely with the central agencies in developing a restructuring plan for the Ministry of Foreign Affairs to further strengthen the level of service delivery and at the same time overcome the human resource issues faced. In conclusion, the Ministry takes seriously all matters that have been reported, regardless of the value of the issues raised. I once again thank all the Honourable Members for their views and concern on issues relating to the Ministry of Foreign Affairs. As the driver and implementer of foreign policy, the Ministry will ensure absolute compliance with every financial procedure rule in order to

Dato Lukanisman bin Awang SauniPBB · GPSDeputy Minister of Foreign Affairs · SibutiEN

ensure efficient, transparent and integrity-based governance. Our only goal is to ensure that every sen of allocation and every policy formulated truly benefits the well-being of the people. That is all, thank you.

Thank you, the Honourable Deputy Minister. Just on time. Next, I would like to invite the Ministry of Works. The floor is given to the Honourable Minister.

Dato Sri Alexander Nanta LinggiPBB · GPSMinister of Public Works · KapitEN

Thank you, Mr Speaker. First, I would like to take this opportunity to thank the Honourable Members who took part in the debate session on the Auditor General's Report No. 1 of 2026, which focused on audit observations of us, the Ministry of Works. Mr Speaker, before I proceed to answer the issues raised by the Honourable Members, allow me to request a little time first to provide an explanation regarding the issues raised in the Auditor General's Report. KKR takes note. Thank you for the observations given and also for providing appropriate feedback regarding the report. I was in this House since the first issue was debated by the Honourable Member for Kota Belud and have closely followed all the issues subsequently raised by the Honourable Members. Accordingly, the explanation that I will deliver is very important to me so that KKR can share the proactive actions that have been, are being and will be taken through various measures and strategies to resolve the problems mentioned and to carry out continuous improvements from time to time in order to overcome the weaknesses and find the best methods so that these shortcomings do not recur in the future. At the same time, I reject all assumptions that no improvements have been made, and I hope that my explanation shortly will also include answers to all the questions raised by the Honourable Members at the same time. And I also apologise if I do not have the opportunity to answer all the issues raised, and allow me to answer in writing all the issues that have been raised in this august House shortly. Mr Speaker, indeed a lot has been reported in the Auditor General's Report

Dato Sri Alexander Nanta LinggiPBB · GPSMinister of Public Works · KapitEN

regarding— or observations relating to the Ministry of Works. So, we have prepared a complete response. If I were to read all of that, I might take 40 minutes. Since I have been given only 10 minutes or I ask for a little more, I must choose which ones the Ministry of Works thinks need to be explained in this session, right now. So thank you, Mr Speaker, if I am given a little more time later. Mr Speaker, for the information of the House, out of the total – overall, the Ministry of Works takes seriously the observations raised in the Auditor General's Report and always ensures that corrective and follow-up actions are implemented on an ongoing basis. So the Ministry will continue to strengthen monitoring of the management relating to delays— that cause delays or problems to project implementation. So, the Ministry will also continue to carry out engagement sessions with stakeholders to ensure that matters still under action can be resolved and ensure that the interests of the Government remain protected.

Dato Sri Alexander Nanta LinggiPBB · GPSMinister of Public Works · KapitEN

Mr Speaker, regarding the issue that has been very popularly raised, namely the Pan Borneo Sabah Phase 1, yes. Objectively, the implementation of this project is a strategic initiative of the Federal Government to improve the existing network of Federal Roads for the benefit of road users and, at the same time, for the enjoyment of the people of Sabah. Mr Speaker, the implementation of the LPB Sabah project was initiated based on the decision of the Economic Council on 24 August 2015, which agreed to adopt the model, adopting the project delivery partner (PDP) model, yes. And subsequently the Cabinet Meeting on 23 October 2015 approved the implementation of Phase 1 of this project, which covers an alignment of approximately 706 kilometres. So, through the PDP agreement signed in April 2016 between the Federal Government, the Sabah State Government and Syarikat Borneo Highway PDP Sdn Bhd. So, BHPSB was appointed to manage and implement the development of Phase 1 project, which covers 35 work packages.

Dato Sri Alexander Nanta LinggiPBB · GPSMinister of Public Works · KapitEN

However, Mr Speaker, following the realignment and review of mega projects, a review in 2018, the Cabinet on 19 December 2018 agreed in principle to terminate the PDP agreement on the grounds of national interest or termination on national interest. So, on 24 July 2020, the Cabinet reconsidered the proposal for the implementation of the LPB Sabah project and agreed to the overall estimated implementation cost for the 15 work packages of LPB Sabah Phase 1 amounting to RM10.491 billion. So, after the PDP agreement was terminated, the Federal Government signed new contracts with 15 Phase 1A work package contractors to continue the implementation of the project conventionally in 2021. So, 11 work package contractors, or WPCs, were reappointed. Three WPCs went through the tender process and one WPC was re-tendered. So, for the information of the Honourable Members, the LPB Sabah Phase 1 project consists of 35 work packages and is divided into three project portions, namely LPB Phase 1A, 15 packages. Work package WP09, one package, and Phase 1B, 19 packages. The 15 Phase 1A work package contractors were appointed conventionally in 2021, while the remaining 20 work package contractors for WP09 and Phase 1B were appointed between February 2024 until January 2026. The packages under the WP09 and Phase 1B portions were approved in stages under the Twelfth Malaysia Plan based on the financial capacity of the Government at that time. So, why I am explaining this is because many may not understand. Let us say the total of 35 packages, so it is not that Mr Speaker, because we must take note that Phase 1B is late or later, yes, from 2024 until 2026 compared with 2015 for Phase 1A which was earlier. So it cannot be said to be too late, yes. So we must understand, yes. Phase 1A is different from Phase 1B. So, based on the Auditor General's Report, there are 13 findings relating to the LPB Sabah project concerning delays in project completion, project approvals and non-compliance with laws, regulations and guidelines, as follows, yes. Namely the delay in the completion of the overall LPB Sabah Phase 1 project and the increase in the project ceiling cost of Phase 1A, 15 work packages. Weaknesses in project planning, the project site was not fully prepared before the project began. And weaknesses in project implementation, there was no physical progress for the design changes of WP01 and WP02. Weaknesses in

Dato Sri Alexander Nanta LinggiPBB · GPSMinister of Public Works · KapitEN

project implementation, the status of completion of the remaining works of WP04 and WP10. So, findings through the project information system were ineffective. The value of work change orders exceeding the prescribed limit was not submitted for the approval of the Ministry of Finance, and utility relocation claims for late-completed work packages. Also, work commenced before the Environmental Impact Assessment (EIA) report was approved, as well as the preparation of the bill of quantities (BQ) for preliminary work items, and the late completion of contract documents. And the stipulation of the approval limit clause for Work Change Orders (APK) and the administration of the service contract for the LPB Sabah Phase 1A project information system. So, the Ministry appreciates all the findings contained in the report of the National Audit Department. These findings indirectly give us at the Ministry an opportunity to make improvements to the LPB Sabah project and, at the same time, serve as lessons learned for other Federal Government development projects. However, there are several matters that the Ministry wishes to explain to this august House. Mr Speaker, as I stated earlier, the LPB Sabah Phase 1 project with 35 work packages is divided into Phase 1A and Phase 1B, and indeed only four packages have been completed, with the remaining 31 work packages having physical progress status of 9.01 for Phase 1A, 37.5 per cent for WP09 and 23.96 per cent for Phase 1B. These are the project's progress. So, various intervention and proactive actions have been implemented by KKR to ensure improvements to the LPB Sabah project. Among these actions are, one, establishing a steering committee meeting or task force beginning November 2024. This meeting is co-chaired by the Secretary-General of KKR and the Permanent Secretary of KKRU Sabah. The task force meetings have been held two times in 2024, 11 times in 2025 and up to now nine times have been held in 2026. And I myself, Mr Speaker, have chaired this task force meeting two times. In addition, on-site visits by the Ministry's top management have also been held to ensure that performance on the ground is not merely reporting on paper and in meeting rooms. The TURPA or on-site visit programme was held to ensure that issues on the ground can be resolved promptly with the parties involved, such as the Department

Dato Sri Alexander Nanta LinggiPBB · GPSMinister of Public Works · KapitEN

of Land and Survey (JTU) Sabah and utility service provider companies. So, the TURPA Programme has been held three times by the Honourable Minister, myself with the Secretary-General, two times by my Deputy, the Deputy Minister, and six times by the Secretary-General together with the project implementation team since 2024. So, KKR also implemented the Malaysia Strategic Public Works Collaboration Programme starting February 2025 in Sarawak. Meanwhile, this year it was organised in July and 2026 in Sabah, yes. This collaboration programme, which is held annually, is attended by participants from the Ministry of Works, JKR Malaysia, JKR Sabah and JKR Sarawak. This programme is held with the aim of discussing key issues and the direction of national infrastructure development. The programme content focuses on best practices in projects, especially national mega projects, as well as the importance of digital integration in asset maintenance for the safety of the people. This programme is an effort by the Ministry to enhance the capacity of officers. Mr Speaker, there are various factors that cause delays in the completion of the Pan Borneo Sabah Highway project, among which are as follows. A change in the method of project implementation from PDP to conventional. So, the LPB Sabah project was taken over for implementation conventionally after the PDP implementation was terminated with effect from 22 September 2019. This termination caused delays in project implementation which slowed down other procurement processes that had to be complied with. And overall, 15 contractors for the LPB Sabah Phase 1A work packages were only completed, were awarded in 2021.

Dato Sri Alexander Nanta LinggiPBB · GPSMinister of Public Works · KapitEN

So, the second reason, namely the COVID-19 pandemic.

I will give the Honourable Member two more minutes, okay.

That is unfair, Mr Speaker. This mega project was not spared from the impact of the COVID-19 pandemic that struck the world. Various measures have been taken by the Government to address this issue, including enforcing the Movement Control Order (PKP) starting 18 March 2020. The spread of the pandemic and the implementation of the PKP affected the development sector and construction projects in Malaysia, including

the LPB Sabah project, such as project delays, shortages of manpower and raw materials, and disruptions to supply chains and logistics. [Deputy Speaker (Dato' Sri Dr. Ramli bin Dato' Mohd Nor) chaired the Meeting] And the third, namely the issue of land acquisition. This cannot be denied. So, the capacity of the Land and Survey Department (JTU) Sabah has only seven valuers (evaluers) for valuation work throughout the state of Sabah. Also, the issue of utility relocation. The readiness of utility companies for utility relocation and installation works has contributed to delays in works on site. There are also utilities that could not be relocated because the land acquisition issue has not been resolved. And also, contractor performance. The Ministry has identified that the unsatisfactory performance of contractors is one of the causes of the delay. JKR Sabah officers were directed to always carry out checks on site, conduct detailed checks of daily diaries, make adjustments between the parties involved, and ensure that the recovery plan agreed upon is fully complied with by the contractors. So, the Ministry takes seriously the issue of the delay of the LPB Sabah Phase 1A project. Meanwhile, for Phase 1B which began in April to October 2024, the Ministry and JKR Sabah have been closely monitoring to ensure the project can be implemented within the time and cost that have been set. So, Mr Speaker, if I were to read all of this, it may take another 10 minutes. How about that?

Deputy Speaker (Dato’ Sri Dr. Ramli bin Dato' Mohd Nor)EN

Honourable Minister, as long as I have not told you to stop, go on.

Shall I continue? Okay. So I have talked about the weaknesses and also the follow-up actions on how we address or make improvements. Mr Speaker, I will continue. Weakness in project implementation, yes. No physical progress for design changes. So, Mr Speaker, improvement measures were also implemented at the state level, yes. So, JKR Sabah, JTU Sabah and the local authorities (PBT) involved have held monthly adjustment meetings to ensure that the land acquisition issue is resolved

promptly. The JTU Sabah has also directed that site works may commence in line with state land management procedures for lots that have received offers, so that the issue of site unavailability can be minimised. That is said to be the problem. Mr Speaker, the ministry has identified several weaknesses at the project implementation level that have caused non-compliance with existing regulations, laws and guidelines. Accordingly, several improvement measures have also been taken, as follows― The Pan Borneo Highway Sabah Project Steering Committee meets every month, co-chaired by the Secretary-General of the Ministry of Works (KKR) Malaysia and the Permanent Secretary of KKRU. So, following the meeting between the Secretary-General of KKR and the Chief Minister of Sabah on 4 September 2026, the Chief Minister of Sabah recommended that the Steering Committee meetings be co-chaired by the Secretary-General of KKR and the State Secretary of Sabah to enhance the effectiveness of project implementation, particularly in managing the state government agencies involved. So, a special meeting of the Pan Borneo Highway at state level in Sabah, chaired by the State Secretary of Sabah, to coordinate issues between agencies in the state, and the Site Visit Programme (TURPA) by myself as Minister, my Deputy, the Deputy Minister, the Secretary-General of KKR and senior officers. Also, the collaborative programme that I mentioned at the earlier stage is very important for us to discuss and find ways in which we can make improvements. So, this collaboration has already run for two series― 2025 and 2026― between the Ministry of Works Malaysia, the Public Works Department Sabah (JKR Sabah), the Public Works Department Sarawak (JKR Sarawak) and also the Public Works Department Malaysia (JKR Malaysia), aimed at enhancing capacity and officers. Mr Speaker, the ministry has also taken action by ensuring that all officers involved receive training and courses in contract management and administration together with CIDB― Construction Industry Development Board― and CREaTE under JKR, as well as temporary placements or attachments at agencies under the Government of Malaysia under KKR, and also private companies such as Gamuda Berhad. This is to improve the service delivery system, especially in terms of contract management and administration. We give our officers the opportunity―

officers to learn about best practices from the organisations that I mentioned earlier. So, the results of the efforts carried out between the ministry and the Sabah State Government have had a positive impact on the overall progress of the project. So, Mr Speaker, I did not have the opportunity to answer what the Honourable Members asked. As I promised at the earlier stage, the answers or explanations will be provided in writing. Mr Speaker, with this, that is all for now for my winding-up speech on the Auditor General's remarks regarding KKR. And all proposals will be given due consideration by the ministry. Thank you.

Deputy Speaker (Dato’ Sri Dr. Ramli bin Dato' Mohd Nor)EN

Thank you, the Honourable Minister of Works. Next, I invite the Honourable Minister of Defence to speak.

Dato’ Seri Haji Mohamed Khaled bin NordinUMNO · BNMinister of Defence · Kota TinggiEN

Mr Speaker, the Ministry of Defence (MINDEF) takes seriously the findings of the Auditor General's Report regarding the management of the littoral combat ship (LCS) project, and thanks all Honourable Members who took part in debating this matter. The Ministry of Defence acknowledges that there were indeed delays which led to changes in the completion and delivery dates of LCS 1 in particular. In view of this, I would like to inform the House of the status and current progress relating to the matters raised in the Auditor General's Report and the subsequent debate. Firstly, the Auditor General's Report as at 25 June 2026 found that the physical delay rate of LCS 1 was 13.88 per cent, which is 85.47 per cent of the expected level of progress. For information, as at August, the level of progress has increased to 86.39 per cent, which is 13.61 per cent less than the target. This means the percentage of the delay has been reduced by 0.27 per cent. Likewise, for the overall project, it stands at 80.13 per cent compared with 78.99 per cent at the time the Auditor General's Report was prepared. It shows a delay of 9.14 per cent.

Dato’ Seri Haji Mohamed Khaled bin NordinUMNO · BNMinister of Defence · Kota TinggiEN

Next, the Auditor General's Report also states that the project is expected to experience delays in completing several components for LCS 1 and 2, in particular cabling or cable installation, installation and testing of equipment, and works relating to accommodation spaces, panels and ship catering facilities. Delays also involve piping and cabling works. The delay in these works has a cascading effect on subsequent activities, including setting to work, that is, the process of switching on, testing and ensuring the ship's systems can function, as well as trial and commissioning, or testing and commissioning of the ship, including the harbour acceptance test and sea acceptance test.

Dato’ Seri Haji Mohamed Khaled bin NordinUMNO · BNMinister of Defence · Kota TinggiEN

Likewise, the findings of the Auditor General's Report also state that the contract documents for Integrated Logistic Support and Trial Aids have not yet been finalised, even though more than four months have passed since the Letter of Acceptance was signed on 5 August 2025. I would like to inform you that the contract for Integrated Logistic Support and Trial Aids, which provides the authority for all activities and tests on the ship, was signed on 26 August 2026. Therefore, all support, training and the like can now commence. Next, with regard to the procurement of 3P medium calibre gun ammunition and the integrated decoy launching system (IDLS), which have not yet been finalised.

Dato’ Speaker.

For information, the proposals for these two items are in the process of direct negotiation. And next, also in the matter of...

Dato’ Sri Ikmal Hisham bin Abdul AzizBERSATU · PNTanah MerahEN

Dato' Speaker, may I interject?

If I give way to one, the others must also be given way. My time is also limited. The Honourable Member has plenty of other time. Next is the procurement contract for the surface-to-air missile, which has not yet been finalised. We would like to inform you that the Letter of Acceptance has already been signed, and the contract documents are expected to be finalised in mid-October 2026. Based on all the issues and the expected delays that I have stated earlier, which are cascading, I have been informed by the contractor LUNAS that they cannot fulfil their original commitments and guarantee that LCS1 could be delivered in December 2026. Instead, LUNAS

has given a new date that LCS1 is expected to be delivered in April 2027, which is roughly six months from now. On the part of the Ministry of Defence, representing the Malaysian Armed Forces and the Royal Malaysian Navy (TLDM) in particular, and certainly all the Honourable Members present here, we are very saddened, disappointed and uncomfortable with the delays and the performance of the LCS construction entrusted to LUNAS. We must understand that the Ministry of Defence is the client, the customer. It is not the contractor. We do not build the ship. The change of completion date and this delay are things that will certainly affect the readiness of the Malaysian Armed Forces and also national defence. As the buyer, of course the ministry very much expects the LCS to be delivered. And if the new date is April 2027, we hope LUNAS will have no further excuses and delays. Mr Speaker, the ministry acknowledges that acceptance in April 2027 will be without the naval strike missile system. For that reason, the Auditor General's Report has projected that the delay in completing LCS1 could extend until December 2035. That projection was made by taking into account the estimated process and period required for the supply of the NSM, which was previously cancelled unlawfully by the Government of Norway. We are well aware that without this unilateral cancellation, the delivery of the LCS ship would have taken place on the new date, April 2027. I would like to state that the period given, or stated in the Auditor General's Report, which takes eight years from 2026, is based on the existing contract, under which Norway was in fact granted an extension of time for delivery. But if we look for alternatives as recommended by Putatan, if we look at the missile purchases that we have made, are making and will make from LIG Korea, from Roketsan Turkey or from MBDA France, the time taken for delivery is only three years. So, we are weighing all of this and we will ensure that the delivery and installation period is not too long, unlike the Norway contract, which took up to eight years because Norway was granted an extension of time for certain reasons, as there is a component in the Norwegian missile that required approval from America, and they had to wait two years, three years, and then COVID-19 and so on. So,

you must understand, for that reason the projection of completing the LCS by December 2035 is something we believe is inaccurate and untrue. Another matter that I wish to clarify slightly is that although this LCS ship does not have NSM, the LCS that we will receive later will not be entirely without any weapon systems. The LCS will still be equipped with several other types of weapon systems. Among them are surface-to-air missiles, and deep-sea surface-to-sea missiles to attack or deal with any threats from submarines. We also have an electromagnetic warfare system to thwart any attacks that may be carried out. And also a combat management system that integrates all these capabilities with the ship's radar and detection systems. And at the same time, if there is a threat from any other enemy ship, we can still carry out integrated operations with the Royal Malaysian Air Force. In the absence of NSM, which is a surface-to-surface missile, let us say a ship 100 kilometres away that we assume has ill intentions towards our country, through detection carried out by the ship, we can inform the air force to carry out an attack on the ship that we consider a threat. Mr Speaker, on the part of the Ministry of Defence, we have never taken this matter lightly. And one matter, the Honourable Member for Tanah Merah mentioned the LAD. We have indeed issued a LAD notice to LUNAS to show our seriousness, and we do not compromise on what has been done by— the delays caused by LUNAS. And the debate by the Honourable Member questioning which government approved LUNAS's allocation. It was done by the government in which the Honourable Member was the Deputy Minister of Defence. So, the Honourable Member is quick to forget, the Honourable Member was part of those who made the decision previously. So, the ministry will take all steps and mechanisms to monitor the implementation of the LCS Project. Finally, what I can say, Mr Speaker, is that the Ministry of Defence and the Ministry of Finance, as the ministry to which LUNAS, the contractor, belongs, certainly do not want any continuing delays in this project. I believe that with the cooperation and

commitment of the Ministry of Finance, this time LUNAS will not change the delivery date again, and finally, the handover to the–– the ship to the Ministry of Defence will definitely take place in April 2027. So, I believe the Ministry of Finance will also take steps to safeguard the good name of the Ministry of Finance, because LUNAS belongs to the Ministry of Finance. Thank you.

Deputy Speaker (Dato’ Sri Dr. Ramli bin Dato’ Mohd Nor)EN

Thank you, the Honourable Minister of Defence. Next, I invite the Minister of Education to speak.

Tuan Wong Kah WohDAP · PHDeputy Minister of Education · TaipingEN

Thank you, Dato' Yang di-Pertua. Peace be upon you, and I would like to thank the Honourable Member for Sri Gading, who directly touched on matters relating to KPM directly, and three other Honourable Members, namely the Honourable Member for Betong, Kuala Krau and also Tampin, who took part in this debate and touched on issues relating to KPM in general. Overall, from the debate, KPM's matters relate to two main themes, namely number one, Accounts Receivable of Contractors' Advance Payments that could not be collected, and accounts receivable of Contractors' Advance Payments that were not reported. For the information of the Honourable Members, the amount of Accounts Receivable of Contractors' Advance Payments not collected at KPM involves companies that are now categorised into several categories, namely there are companies that have been dissolved, wound up, and some that are still active. KPM takes note of the observation raised regarding the need for more prompt action to recover the outstanding balance of Contractors' Advance Payments. With regard to the collection action issue raised, which involves three dissolved companies valued at RM1.91 million, KPM would like to explain that the amount cannot be collected because the companies no longer have the capacity to be subjected to legal action in respect of their respective liabilities, as the companies have already been dissolved. However, out of this amount, one company is now at the final stage of calculating the income cost, while

Tuan Wong Kah WohDAP · PHDeputy Minister of Education · TaipingEN

two other companies are under action and review by the legal advisers. Next, for the 11 companies that have been wound up, with a total value of RM20.79 million, KPM would like to inform you that the winding-up process of these companies took place in the period from 2009 to 2020. To protect the interests of the government, KPM has taken action by submitting claims to the Malaysian Insolvency Department (JIM) for 10 companies in the period from 2013 to 2026. Meanwhile, one other company is still under follow-up action by KPM. In view of this, KPM is committed to ensuring that all processes relating to claims are carried out in a more orderly and thorough manner, including submitting proof of debt forms to the Malaysian Insolvency Department for all companies involved, as well as obtaining confirmation of the status of dividend distribution if any remains. This is important to ensure that every available avenue to recover government funds can be fully utilised, while safeguarding the interests of the government and strengthening governance and accountability in public financial management. With regard to the amount of Accounts Receivable of Contractors' Advance Payments involving two companies that are still active, with a total value of RM5.43 million, KPM would like to explain that one company, involving the amount of RM3.78 million, was given a notice of termination more than 10 years ago. Meanwhile, the other company, involving RM1.65 million, was given a notice of termination in less than five years. At present, one case is under action and review by the legal advisers, while the other is at the final stage of calculating the termination cost. KPM takes this matter seriously and will take appropriate follow-up action based on the facts of the case and legal advice, including civil action or the issuance of claim letters against companies that are still active if there is any breach of contract, and subject to the terms of the contract. At the same time, KPM is strengthening development project management through improvements to work procedures, more specific and systematic monitoring, and stricter compliance with financial regulations and the contract conditions in force. As a way forward, KPM will continue to enhance the competency of officers through training and courses related to project management. At the same time, monitoring

Tuan Wong Kah WohDAP · PHDeputy Minister of Education · TaipingEN

of the validity period, bonds, contract advance payments, collection status and project progress will be enhanced. In this regard, the status of contract advance payments will also be made a standing agenda item at the Ministry's Development Action Committee Meeting (JKTPK), which sits and meets twice a year, to ensure that follow-up actions can be monitored continuously. In addition, KPM will strengthen internal review and monitoring mechanisms on a regular basis to ensure that all matters relating to contract advance payments comply with all procedures, circulars and contract conditions stipulated. In conclusion, KPM openly accepts all the observations, suggestions and views raised by the Honourable Members and as in the Auditor General's Report, and KPM is committed to taking appropriate improvement actions. The planned strengthening measures will be implemented and will ensure that development project management and public finance are carried out more efficiently, with integrity and accountability. Thank you, Dato' Yang di-Pertua.

Deputy Speaker (Dato’ Sri Dr. Ramli bin Dato’ Mohd Nor)EN

Thank you, the Honourable Minister. Next, I invite the Minister of Health to speak.

Dato Hajjah Hanifah Hajar TaibPBB · GPSDeputy Minister of Health · MukahEN

Assalamualaikum warahmatullahi wabarakatuh and peace be upon you. Dato' Sri Yang di-Pertua, first of all I would like to thank the Honourable Members for Kuala Nerus and Jerlun, who touched on health issues in the debate on the Auditor General's Report. Two matters were raised, namely firstly the reasons for the occurrence of Accounts Receivable (ABT) under the Ministry of Health (KKM), and secondly, the extent to which coordination between KKM, the Ministry of Home Affairs (KDN) and other enforcement agencies has been strengthened. Dato' Sri Yang di-Pertua, KKM takes both of these issues seriously, particularly those involving non-citizen patients, where more than 80 per cent are contributed by undocumented migrants (PATI) or stateless persons. I would like to emphasise that KKM must always ensure that treatment services are provided to all patients on humanitarian grounds

Dato Hajjah Hanifah Hajar TaibPBB · GPSDeputy Minister of Health · MukahEN

especially those that threaten life. This is in line with the Declaration of Geneva Hippocratic Oath and the Alma-Ata Declaration 1978. Although the issue of arrears and ABT is among the financial matters that require serious attention, the Ministry of Health (KKM) has shown an overall downward trend in ABT revenue, namely an estimate from RM359 million in 2024 to RM336 million in 2025, involving a reduction of RM23 million or 6.4 per cent. Dato' Sri Mr Speaker, the cause of non-citizen patients' unpaid medical bills is not solely due to weaknesses in the collection process, but is also influenced by financial constraints, lack of insurance coverage, patients who leave facilities without settling payment, and incomplete or inaccurate identity and contact information, which makes it difficult for KKM to trace patients and carry out follow-up action for collection. To address this, KKM health facilities have implemented several collection actions. Among them are issuing three staged reminder letters, issuing demand notices or legal notices, contacting the embassy of the country of origin or the nearest next of kin, making claims against employers, and cooperating with non-governmental organisations to help settle bills for patients who have insufficient funds or are unable to pay. To address the issue of arrears, KKM is strengthening the collect before discharge approach through the collection of deposits or payment during treatment, expanding cashless payment channels, and enhancing ABT monitoring through the Financial and Accounts Management Committee and the ABT Monitoring Committee at ministry level. KKM is also strengthening cooperation with employers, insurance companies and NGOs, as well as increasing bank guarantee values for employers and private companies in line with the increase in treatment costs. For refugees and asylum seekers registered through the Refugee Registration Document (DPP), KKM proposes a protection mechanism or compulsory health insurance contribution to ensure treatment costs are covered and to reduce the formation of new arrears. Mr Speaker, KKM is of the view that a long-term solution to the issue of unpaid medical bills of non-citizen patients requires a cross-ministry and cross-agency approach. Cooperation between agencies through a whole-of-government approach, particularly involving the Immigration Department of Malaysia, the Ministry of Home Affairs and the Ministry of Foreign Affairs, is needed as a cross-ministry mechanism to address the issue of unpaid bills of non-citizen patients more comprehensively and effectively, including mechanisms for verifying identity documents.

Dato Hajjah Hanifah Hajar TaibPBB · GPSDeputy Minister of Health · MukahEN

Immigration Department of Malaysia, Ministry of Home Affairs and Ministry of Foreign Affairs are needed as a cross-ministry mechanism to address the issue of unpaid bills of non-citizen patients more comprehensively and effectively, including mechanisms for verifying identity documents.

Dato Hajjah Hanifah Hajar TaibPBB · GPSDeputy Minister of Health · MukahEN

Mr Speaker, KKM will streamline and continuously improve the mechanisms for collecting revenue and ABT, while enforcing stricter financial controls at all levels of health facilities. At the same time, strategic and cross-agency cooperation with ministries and stakeholders will continue to be expanded to address emerging issues comprehensively and sustainably. KKM hopes that the relevant ministries and government agencies can continue to strengthen enforcement and control actions regarding the entry and management of foreign nationals, particularly involving undocumented immigrants (PATI) and refugees. These measures are important to ensure the sustainability of the national health service system for the benefit of all Malaysians. Thank you.

Deputy Speaker (Dato’ Sri Dr. Ramli bin Dato’ Mohd Nor)EN

Thank you, Honourable Minister. Next, I invite the Minister in the Prime Minister's Department for Sabah and Sarawak.

Datuk Ts. Mustapha SakmudPKR · PHMinister in the Prime Minister's Department (Sabah and Sarawak) · SepanggarEN

Thank you, Dato' Sri Mr Speaker. I would like to record my appreciation to the Honourable Members who have taken part in the debate on the Report of the Auditor General, particularly on matters touching on the powers and responsibilities of the Public Service Department (JPA) and the Implementation Coordination Unit (ICU) of the Prime Minister's Department. The Government notes and takes seriously all the observations, views and recommendations put forward by the Auditor General. Audit observations of this kind are an important mechanism to ensure that financial management, governance, service delivery and implementation of government programmes are always at the best possible level. Dato' Sri Mr Speaker, I would like to touch on matters relating to Accounts Receivable (ABT) and Revenue of the Public Service Department (JPA) as raised in the Report of the Auditor General No. 2 of 2026. For information,

Datuk Ts. Mustapha SakmudPKR · PHMinister in the Prime Minister's Department (Sabah and Sarawak) · SepanggarEN

this august House, the total of various ABT revenue of JPA has increased by 12 per cent, equivalent to RM44.3 million in 2025 compared with the previous year. The increase in ABT for compensation is a consequence of JPA's continuous enforcement actions against recipients of scholarships and loans who breach the terms of agreements, including academic weakness, withdrawal from studies, disciplinary issues and other breaches of agreed conditions. In 2025, the number of compensation payers increased by 26 per cent, namely 816 persons compared with the previous year. This consequently contributes to the increase in ABT when compensation claims are recorded. Accordingly, the increase in ABT for compensation should be viewed as part of the effectiveness of JPA's enforcement actions in ensuring compliance with agreements, and not merely as reflecting weaknesses in debt collection. Dato' Mr Speaker, compensation repayments are generally made on a scheduled and instalment basis, taking into account the financial capacity of the obligor and the prevailing regulations. Therefore, settlement of the outstanding ABT compensation balance does not necessarily cause the total ABT to decline significantly each year. Since new ABT continuously arises when cases of agreement breaches requiring compensation payments occur, while ABT decreases gradually in line with the stipulated repayment schedule. In this context, the increase in ABT for compensation should be viewed comprehensively as among the indicators that agreement enforcement actions are being carried out continuously and effectively. In addition, it shows that cases of agreement breaches have been identified, compensation claims have been established and follow-up collection actions are being carried out. Dato' Mr Speaker, nevertheless, the Government does not take the issue of ABT and JPA lightly, and JPA constantly implements improvement measures to ensure compensation ABT is collected systematically and according to schedule, while minimising the risk of arrears and non-compliance with payments. Among the measures implemented are streamlining the period and follow-up collection actions against obligors who have payment liabilities, including issuing reminder notices, warning notices and legal procedure notices to obligors who fail to comply with payment requirements. For suitable cases, legal action is also taken to protect the interests of the Government and ensure payment liabilities can be

Datuk Ts. Mustapha SakmudPKR · PHMinister in the Prime Minister's Department (Sabah and Sarawak) · SepanggarEN

restored. At the same time, various payment channels are provided to facilitate obligors in making repayments and to improve compliance with the stipulated schedule. JPA also strengthens strategic cooperation with related agencies including the Attorney General's Chambers, the National Registration Department, and the Inland Revenue Board of Malaysia (LHDN), particularly in supporting efforts to trace obligors, collect arrears and carry out enforcement actions. Dato' Mr Speaker, positive developments can also be seen through the increase in the number of consistent payers, namely from 1,255 persons in 2024 to 1,697 persons in 2025, or an increase of 35.2 per cent, equivalent to 442 persons. This increase indicates the stability of ABT collection and obligors' compliance with the stipulated repayment schedule. The Government will continue to strengthen the ABT management approach to ensure every government claim is managed and collected appropriately, while providing obligors with reasonable room to settle liabilities based on their capacity and the prevailing regulations. JPA will also improve monitoring and follow-up mechanisms so that arrears can be identified earlier and appropriate action taken without delay. The Government's objective is to ensure that every revenue that should rightly be received can be collected optimally and continuously without compromising the principle of fairness to the obligor's capacity, as well as compliance with the prevailing regulations. Dato' Mr Speaker, I now turn to issues involving the Implementation Coordination Unit (ICU). First, I would like to record my appreciation to the Honourable Members who have raised questions and provided views on the management and monitoring of the implementation of Federal Government development projects, particularly as raised in the LKAN 2026. The Government takes seriously the Auditor General's observations and recommendations concerning implementation performance. Development projects under the RMKe-12. The Government is committed to ensuring every development allocation is managed effectively and that projects are completed within the stipulated period and provide benefits to the people. For this purpose, Directive Number One of 2023, the mechanism for coordination, implementation and development of the nation, sets out a multi-tiered monitoring mechanism at the Federal, ministry, state, district or division level. This

Datuk Ts. Mustapha SakmudPKR · PHMinister in the Prime Minister's Department (Sabah and Sarawak) · SepanggarEN

mechanism enables the progress of projects to be monitored periodically. Issues are identified earlier and intervention actions are taken immediately. In addition, the Reboot Recovery Plan for Problematic Physical Projects sessions are also being implemented to focus on projects experiencing delays or categorised as troubled projects. Special Meetings on Coordination and Monitoring of Development Project Programmes are also held as a platform for monitoring projects, particularly in Sabah and Sarawak. From the aspect of data-based monitoring, the MyProjek system is the main database for the implementation and monitoring of Federal development programmes or projects. Updating of status and consistency by ministries and implementing agencies enables earlier detection of issues and more effective intervention actions. The Government is now also implementing improvements through MyProjek 2.0 to strengthen the management of development programmes and projects so that they are more integrated, efficient and high-impact for the continuity of RMKe-13. Ministries and agencies need to strengthen risk management and carry out closer and more continuous monitoring. For projects experiencing delays, recovery plans must be prepared based on comprehensive assessments covering contractor capacity, financial position, manpower and equipment, supply of materials, technical issues and utility sites, as well as project management. Dato' Mr Speaker, ultimately the Government will continue to strengthen monitoring and intervention mechanisms to ensure development projects are implemented according to schedule, allocations are spent effectively, and the benefits of development can be enjoyed by the people promptly. Orderly and effective implementation of development projects not only ensures the best value from every ringgit of government allocation, but also contributes to improved learning performance, development and the achievement of the national development agenda.

Datuk Ts. Mustapha SakmudPKR · PHMinister in the Prime Minister's Department (Sabah and Sarawak) · SepanggarEN

In conclusion, Dato' Mr Speaker, the Government accepts all the observations and recommendations of the Auditor General as an important check-and-balance mechanism in strengthening governance, improving management efficiency and enhancing the delivery of public services.

Datuk Ts. Mustapha SakmudPKR · PHMinister in the Prime Minister's Department (Sabah and Sarawak) · SepanggarEN

With the explanations that have been given, I hope this august House can see that the Government is always committed to ensuring that every ringgit of public money is managed with integrity, every project is implemented effectively, and every development effort ultimately translates into tangible benefits for the people. Thank you.

Deputy Speaker (Dato’ Sri Dr. Ramli bin Dato’ Mohd Nor)EN

Thank you, Honourable Minister. The last ministry. I invite the Minister in the Prime Minister's Department (Law and Institutional Reform).

Tuan M. Kulasegaran a/l V. MurugesonDAP · PHDeputy Minister in the Prime Minister's Department (Law and Institutional Reform) · Ipoh BaratEN

Thank you, Dato' Mr Speaker. On behalf of the MADANI Government and the National Audit Department, I take this opportunity to thank all the Honourable Members who have taken part in today's debate and touched on matters relating to the National Audit Department, particularly to answer four Members of Parliament: Honourable Rasah, Honourable Kota Bharu, Honourable Betong and Honourable Jelutong. Is he here? Oh, he is here. Honourable Kota Bharu raised the matter of performance auditing being a core function of the National Audit Department. The answer is that the number of reports tabled in the LKAN, the Report of the Auditor General, is not a measure of the effectiveness of an audit; rather, the focus should be more on the impact of findings, the scope coverage, the complexity of issues and the depth of scrutiny, deep dive, such as the Report of the Auditor General on the audit of the management of the Pan Borneo Highway Project in Sabah and Sarawak. Also, the Strategic Plan of the National Audit Department 2026-2030 also places emphasis on higher-impact audits that are relevant to current issues and add value to the people and the nation. The e-SelfAudit system audit for 2025 of 1,856 gazetted companies has been reported in the Report of the Auditor General 1/2026 and tabled in the Dewan Rakyat on 23 February 2026. In 2026, the e-Audit system audit continues. Reporting for the e-SelfAudit audit for 2026 will be

Tuan M. Kulasegaran a/l V. MurugesonDAP · PHDeputy Minister in the Prime Minister's Department (Law and Institutional Reform) · Ipoh BaratEN

in the Report of the Auditor General 1/2027, scheduled for February or March 2027. This involves 851 entities at the Federal Government level and 1,005 state government entities. Audits of Malaysian representative offices overseas by the National Audit Department are different from audits carried out by internal audit units in the relevant ministries. Audits by the National Audit Department are carried out based on the mandate of the Auditor General under paragraph 5(1)(a) of the Audit Act 1957 to examine, investigate and audit the accounts of Federal accounting officers. Meanwhile, audits by internal audit units are based on Treasury Circular PS 3.1, namely the implementation of internal audit in Federal ministries or departments and state governments. The results of audits carried out by the National Audit Department will be reported in the Report of the Auditor General and tabled and debated in Parliament, while audits conducted by internal audit units are reported at ministry level only. UJSB was audited by the National Audit Department through the e-SelfAudit system in 2025, and the Auditor General's certificate and views were issued to UJSB on 23 February 2026. The assessment of the company's financial performance was made based on the audited financial statements for 2022/2023 that were reported in the Report of the Auditor General 2026. Honourable Rasah raised several matters. Among them, requesting that the National Audit Department explain matters concerning MyEG, the Legal Profession Qualifying Board and three collective management organisations such as Music Authors Copyright Protection Berhad (MACP) and Recording Performers Malaysia Berhad (RPM). The Intellectual Property Corporation of Malaysia (MyIPO) does not have the power to monitor CMOs, particularly regarding the collection formula used. These are the views of Honourable Rasah. The answer. The National Audit Department audits the financial statements of MyIPO and the Legal Profession Qualifying Board (LPQB) on an annual basis. The scope of the audit includes verification of fees, levies and royalties collected by both agencies in accordance with the prevailing regulations. Meanwhile, the review of revenue collection by MyEG is carried out in the audit of the Federal Government's financial statements every year. The National Audit Department will review proposals for other entities to be audited based on the Audit Act 1957.

Tuan M. Kulasegaran a/l V. MurugesonDAP · PHDeputy Minister in the Prime Minister's Department (Law and Institutional Reform) · Ipoh BaratEN

Honourable Betong raised the matter of RM2.5 million paid from the Dius Api Trust Fund without proper legal authority, and asked whether the Government will review the trust account and other trust accounts. Every payment must have a clear legal basis. The National Audit Department has recommended that the Ministry of Finance review all letters of undertaking and trust directives, particularly regarding payments made without a valid legal basis, covering allowances and facilities for members of the Trust Account Committee. The public can access a clear and real-time audit follow-up report through the Auditor General's online dashboard, the Auditor General's Dashboard (AGD). It is also summarised through the Malaysian Government portal MyGoverment at http://www.malaysia.gov.my. For the period 2024 to 30 September 2026, the impact of audit follow-up is RM921.45 million in revenue from repayments of revenue collection and penalty collection. Honourable Jelutong― is Jelutong here? Honourable Jelutong raised the matter of the eJaminan system used for paying bail money in court. The Government notes the issues concerning the e-Jamin system raised by the Honourable Member, the Public Accounts Committee and also the Report of the Auditor General debated today. First, I would like to emphasise that the use of this system is well received by all levels of society in this country. The eJamin system saves people's time and allows bail payments in court to be made in less than half an hour, compared with the previous estimate of about five hours when done physically at the bank. However, we cannot deny that there are some shortcomings in the implementation of this system. Among other things, in terms of contracts and investment of the bail money. I believe the Public Accounts Committee's report has examined this matter comprehensively and need not be repeated here.

Tuan M. Kulasegaran a/l V. MurugesonDAP · PHDeputy Minister in the Prime Minister's Department (Law and Institutional Reform) · Ipoh BaratEN

I would like to inform the Honourable Member and–– that these issues–– Mr Speaker–– Honourable Member and Mr Speaker, that these issues are under the Government's attention and are being studied to find the best solution to ensure the efficient delivery of digital services to the people is not affected and, at the same time, good governance is observed.

Tuan M. Kulasegaran a/l V. MurugesonDAP · PHDeputy Minister in the Prime Minister's Department (Law and Institutional Reform) · Ipoh BaratEN

efficient to the people is not affected and, at the same time, good governance is observed. That is all for everyone...

Honourable Member, just a little,

Belum balik?

Not yet gone home, Honourable Member. Jelutong is always here, Honourable Member. Mr Speaker, what the Public Accounts Committee has revealed is that the money that was collected, or the money that was deposited into these accounts by the guarantors who stood surety for the accused in court, has already been used by DAPAT Vista. If I am not mistaken, they have made investments using this money and obtained profits of RM4 million to RM5 million every year. The question is, what action will be taken against the company? Because this money that was collected has been invested. Just imagine, if any loss occurs in the investment, then who will bear it? And my question is, why is that portal, or the e-Jamin system, not used by the government or initiated by the government itself? Where does the Accountant General's Department keep that money in the Consolidated Fund so that we can secure this money? For the information of the Speaker, who has–– has experience in court, the bail money may be RM5,000, or RM6,000. But there are times when the family uses money, pawns jewellery to find the money and deposits it to guarantee the accused. Imagine if we allow this to happen. This matter has already been revealed now. So, my questions are, firstly, no contract has been signed even though this system has been used. I understand that for more or less –– for more than 10 years in operation, sorry, five years have been in operation. There is no contract or memorandum of understanding between the government and DAPAT Vista, which operates this. Secondly, the money that has been used and the profits that have been obtained by them. So, we thank the Public Accounts Committee

of the Public Accounts Committee. I greatly welcome the government's openness because we are willing to disclose this matter so that it becomes known. Indeed, I, as a lawyer, lawyers welcome the use of this system because I have given an example. If on a Friday someone is charged in court, just imagine being brought to court and there are two magistrates on sick leave. Only one magistrate in court, say in the outlying areas, for example in Rawang and so on. And when an accused is brought up on charges, it is already 11.30, 12.00. Bail is set at RM5,000. So, the family needs –– under the old system, they had to rush to the bank to open an account, obtain the money and return to court before 3.00. Otherwise, the accused would be taken to the nearest prison. The e-Jamin system certainly makes things easier. But what are the government's recommendations to improve this system? Whether my proposal, a system pioneered by the government itself, the Accountant General's Department and the Ministry of Finance. We terminate the services of DAPAT Vista. Otherwise, secondly, an agreement is signed between DAPAT Vista so that we provide a guarantee if anything happens, will the government then bear the risk? This is my opinion on the matter. Thank you, Mr Speaker.

Mr Speaker, I thank the Honourable Member for his views, which serve as a reprimand. But before I go into the issues raised, there are two matters we need to understand. Number one, I agree that to my knowledge there is no contract between the e-Jamin company and the government or the Registrar-General. And second, they invested the money and so on. But I must advise the Honourable Member that so far, when audits are carried out and so on, there has been no misappropriation of money. We need to understand. Although, Honourable Member, as of the year 2025, the number of bail cases was 81,667, and the total amount of money collected was RM255,198,405. There was no misappropriation. But Honourable Member, we also need to understand, when this was started, this process was started in 2020, this is like a stock gap measure that was carried out. But it seems it has been running for a very long time.

The Honourable Member may recall about a year or two ago, when suddenly this company was stopped, there was a total chaos, a whole issue among lawyers across the country, to the point that they made complaints to us to continue. Because the old system was very troublesome for everyone and this system needed to be carried out. So after that, government reinstated the issue. But there is no reason not to sign a contract so that the terms are more open, there is accountability, there is transparency and so on. And I believe that matter, to my knowledge, is being refined by the relevant departments and it will be submitted to the Cabinet shortly for their confirmation or views. Honourable Member, let us not forget either, the PAC has put forward three options to resolve this matter. One–– these three options are: (i) the government buys the eJamin system directly from DAPAT Vista Malaysia Sdn. Bhd.; (ii) the government subscribes to the services and products of the eJamin system from DAPAT Vista; and (iii) the company provides maintenance and operation of the system with an estimated total cost of RM80 million for a period of five years before the system is handed over to the government. But the final decision by the Ministry of Finance on 22 October 2025 is as follows. The Secretary-General of MOF finally rejected all three of these commercial proposals. MOF decided to maintain the status quo of the existing system at no cost to the government through a formal agreement with a structured trustee bank. Honourable Member for Jelutong also needs to understand, all the money held by this company is trust–– there are trust issues in this. Trust, there is entrustment involved. But what is more important, Honourable Member, I agree that we need to expedite an agreement so that the terms can be known by the people and there is accountability and all parties can know the matter, and let us not say there is misappropriation. As far as I am informed, so far there is no such thing. Thank you. Is there anything else, Honourable Member? No.

Alright, Honourable Member. I thank all the Members of Parliament who have remained in the House up to now, including the Speaker and the Secretary and so on. These are sincere answers given by the National Audit Department. If there are other matters which I have overlooked, those matters may be raised with me or written to me and I will obtain answers and give them to the relevant parties. Thank you, Dato' Mr Speaker.

Deputy Speaker (Dato' Sri Dr. Ramli bin Dato' Mohd Nor)EN

Thank you, Honourable Minister. Before I close the House, Honourable Member for Jelutong, just to ponder. Honourable Member, is it a public fund? Is that bail money a public fund? Pardon? It's a public fund.

Yes, it's a public fund, Mr Speaker.

Deputy Speaker (Dato’ Sri Dr. Ramli bin Dato’ Mohd Nor)

If it is invested without the consent of the owner, is it pecah amanah?

[Speaking without using the microphone] Dato' Mr Speaker, I cannot give a specific view on this matter. Personally I believe so. But that is subject to the views of the Attorney General on the matter. I don't want to speak on their behalf. I don't want to jump the gun.

Deputy Speaker (Dato’ Sri Dr. Ramli bin Dato’ Mohd Nor)

Yes.

But as I said, I — this is if we look at the Honourable Member, formerly a prosecutor. If we look at this through the e-Jamin system, with permission, "...eJamin, bail money deposited is held in trust by DAPAT Vista Sdn. Bhd. on behalf of the guarantor until the decision of the case trial is made depending on the court's decision, the bail money will either be returned to the guarantor or forfeited and subsequently placed into the government account until it becomes government revenue". The element of trust is that. That is a specific view.

Deputy Speaker (Dato’ Sri Dr. Ramli bin Dato’ Mohd Nor)

What about the profit, Yang Berhormat Jelutong?

Very interesting Yang Berhormat.

Deputy Speaker (Dato’ Sri Dr. Ramli bin Dato’ Mohd Nor)

It belongs to whom?

Mr Speaker, for lawyers, if a sum of money is held by a lawyer on behalf of his client and that money is used without the client's knowledge, without instruction, without permission, and from that money we obtain interest, then it constitutes a...

Deputy Speaker (Dato’ Sri Dr. Ramli bin Dato’ Mohd Nor)

Section 409 of the Penal Code.

...breach of trust, and may also be subject to disciplinary action by the Bar Council. That is why I question, when this money is collected and placed into an account, the company has a responsibility as a trustee to hold that money. They use the money, invest it and obtain interest. So, isn't that an error? That is my question, Mr Speaker. Thank you, Mr Speaker.

Deputy Speaker (Dato’ Sri Dr. Ramli bin Dato’ Mohd Nor)

Tapi apa-apa sekali pun Yang Berhormat Menteri, I leave it to the good judgment of— this is my personal point of view, it’s not taken into consideration.

Correct, correct. I would like to add a little to clear up some confusion here. Honourable Member, we have forgotten that there is a system developed by that company. Who will pay for that system? Who will pay for its operation? So this is something we need to think about. There is no fee to the government, no fee to those matters. So, this is something we need to think about, Mr Speaker. As for what the Honourable Member said about lawyers, as a lawyer we know that when the amount, when I was in practice Dato' Mr Speaker, when the amount is more than 5,000, it is compulsory for the lawyer to keep it in fixed deposit. Thank you, Mr Speaker.

Deputy Speaker (Dato’ Sri Dr. Ramli bin Dato’ Mohd Nor)

Baik Yang Berhormat Menteri, I think that there is lot of legality involvement whether it is trusted fund or whether the money belongs to the public, to be confirmed. Whether the investment is legal, may a lot of practice to be taken into consideration. Baik, Yang Berhormat-Yang Berhormat. Ahli-ahli Yang Berhormat, sekarang saya kemukakan masalah kepada Majlis bagi diputuskan. Masalahnya ialah bahawa

Deputy Speaker (Dato’ Sri Dr. Ramli bin Dato’ Mohd Nor)EN

the motion as proposed by the Honourable Minister in the Prime Minister's Department at item 1 in the Order Paper, and the motions shall be agreed to. [The question was put and agreed to]

Deputy Speaker (Dato’ Sri Dr. Ramli bin Dato’ Mohd Nor)EN

Honourable Members, today's sitting of the House is adjourned until 10 a.m. on Thursday, 8 October 2026.

[The House adjourned at 6.44 p.m.]