Selangor · 12 November 2019

14th Assembly, 2nd session, 3rd meeting · 390 turns · 41,115 words · official PDF ↗ · Digital Hansard ↗

314 of 390 turns machine-translated from Malay (Claude Haiku 5.5), marked EN. The original is the record.

ExperimentalSelangor publishes one PDF per sitting day; recent ones are drafts (Draf Penyata Rasmi). Full written answers are published for 2018-19 only.

(Opening)

Secretary of the HouseEN

Good morning and greetings. The Order of Business for the Third Meeting of the Second Session of the Fourteenth Selangor State Legislative Assembly on 12 November 2019 began with a prayer.

Assistant Secretary of the House

Doa.

Oral QuestionsQuestions

Secretary of the HouseEN

The next item on the Order of Business. Questions.

SpeakerEN

Greetings. Good morning. I invite the Honourable Member for Teratai. Absent.

Tuan Shatiri bin MansorPKR · PHKota DamansaraEN

Can I ask on behalf of Teratai? I request to ask a question.

SpeakerEN

I will not allow it. Next, the Honourable Member for Bukit Melawati. Absent. Next, the Honourable Member for Banting.

Tuan Lau Weng SanDAP · PHBantingEN

Thank you, Mr Speaker. My question is 116.

Oral Questions — 116. Labohan Dagang Water Treatment PlantQuestions

Tuan Lau Weng SanDAP · PHBantingEN

116. To ask the Y.A.B. Dato' Menteri Besar:-

a)

What is the full capacity and current capacity of the Labohan Dagang Water Treatment Plant, and which service areas will water from this WTP be supplied to?

Tuan Ir. Izham bin HashimAMANAH · PHPandan IndahEN

Thank you, Honourable Banting. My battery has just been recharged. Mr Speaker, the Honourable Member for Banting wishes to know the full capacity and current capacity of the Labohan Dagang water treatment plant, and which service areas water from this WTP will be supplied to. The First Phase of the Labohan Dagang Water Treatment Plant was built with a treated water production capacity of 200 million litres a day.

Of this total of 200 million litres a day, the distribution of 56 million litres a day from the Labohan Dagang WTP will first be implemented using the existing distribution system to the areas of Banting, Jugra, Sungai Buaya, Kelanang, Kanchong Darat, Kampung Sungai Lang and Kampung Sungai Kelambu. This distribution will be implemented

in the near future once UPEN hands over the Labohan Dagang WTP to Pengurusan Air Selangor.

The remaining 144 million litres a day will then be distributed after UPEN completes the new pipeline alignment from the New Jugra Pond to the existing main pipe at Pekan Banting and Sijangkang (Jalan Klang Banting). The current status of these works is that UPEN is carrying out the work. End.

Speaker

Sabak.

My question is 117.

Oral Questions — 117. Progress of Anjung Utara ImplementationQuestions

117. To ask the Y.A.B. Dato' Menteri Besar:-

a)

What is the progress in implementing the cluster for the northern wing?

b)

The sub-question has been disallowed.

Tuan Amirudin bin ShariPKR · PHMenteri Besar · Sungai TuaEN

In the name of Allah, the Most Gracious, the Most Merciful. Thank you, Sabak, and also Mr Speaker. The cluster for the northern wing comprises 2 clusters, namely the Agriculture Cluster and the Eco-Tourism Cluster, involving the districts of Kuala Selangor, Sabak Bernam and Hulu Selangor. For the Agriculture Cluster, which is coordinated by the UPEN Sectoral Section, one (1) Technical Committee has been set up to discuss further the action plan to be implemented in the districts involved. Among the plans in the cluster are increasing the production of crops for animal feed such as maize grain, and exploring new crops for animal feed such as 6 hectares of HBG Sorghum in Sungai Panjang, Sabak Bernam, to reduce the number of animal feed imports.

In addition, the State Government also plans to introduce a roselle planting project and a contract farming project on 100 acres of land in Sungai Air Tawar, Sabak Bernam, for local market and export purposes. Furthermore, the State Government, in an effort to introduce Lemon Myrtle cultivation in Sungai Tengi, Kuala Selangor, by the private sector on 120 acres of land, which is the first project of its kind in Malaysia and the largest ever to be granted approval.

As for the Eco-Tourism Cluster in Hulu Selangor, the Local Authority Section (SPBT), UPEN as cluster coordinator, has set up one (1) more technical committee to formulate policy and planning related to eco-tourism in this state. Among the efforts already implemented is the launch of the Selangor Tourism Refinement Programme (P3S), which aims to improve the level of safety and services of the state's tourism industry, especially products within the eco-tourism cluster. The programme, which was launched on 8 July 2019 at Taman Tasik Millenium, Kuala Kubu Bharu, comprises four (4) Pilot Projects, namely:

i) P3S Homestay Pilot Project; ii) P3S Adventure Sports Pilot Project; iii) P3S Jetty & Boat Pilot Project; and iv) P3S Commercial Accommodation Activities in Residential Buildings Pilot Project.

As for part b, regarding the reform of the Sabak Bernam District Council in an effort to drive development in rural areas, especially in the district of Sabak Bernam, the State Government has set up the Sabak Bernam Economic Development Committee, which is currently drafting the direction and studying several physical and non-physical development proposals by the Sabak Bernam District Council. Through these physical and non-physical developments, the Committee hopes to boost the local community's economy in general, and several development plans have been drawn up.

First, to establish an industrial centre, a higher education centre and Sabak Bernam agriculture. Second, to promote district tourism activities. Third, to encourage sports activities using the facilities of the Sabak Bernam District Council. Fourth, to implement a fish collection centre and others including mentarang. Fifth, to provide licence permits that are easier and less bureaucratic. Sixth, publicity and public announcements of sites with potential to generate the economy. Seventh, restrictions on transactions for persons with outstanding compound arrears at all counters of the District Council. A campaign to pay compounds with discounts. Tenth, recovery of stale compounds through legal action to reduce arrears of revenue from compounds. Eleventh, implementing participation during enforcement operations, and twelfth, strengthening enforcement to reduce leakage of charges relating to licences and so on.

For Honourable Sabak Bernam, the Sabak Bernam District Council needs to implement several of these focus areas as preparation for us when the WCE is completed, as the new expressway alignment crossing the State of Selangor from Banting and passing through Sabak Bernam all the way to Bagan Datok. We believe that with the preparations proposed, we can directly take advantage of the overflow of vehicles and traffic movements that occur, especially in the area, once the expressway is completed. Thank you.

Soalan tambahan.

SpeakerEN

Yes, Sabak, you have the floor.

Only a stepchild feels like a stepchild. In Sabak Bernam, we have felt neglected for a long time. I want to ask, of the RM19 billion in investment that came into Selangor, I want to ask how many ringgit landed in Sabak Bernam. Not how many millions. How many ringgit landed in Sabak Bernam. Thank you.

Tuan Amirudin bin ShariPKR · PHMenteri Besar · Sungai TuaEN

Thank you, Sabak Bernam. That is why, when we say there are no industrial areas or industrial sites and so on, in fact there are efforts. For example, some of our subsidiary companies once built factories or an industrial area in Sabak Bernam, but unfortunately, after the construction was done, there were no takers, or no one who took up the opportunity to invest in that area.

Therefore, what the State Government has done is to prepare space, prepare areas and prepare those facilities. As for the figures, I feel that you have already strayed from this question, but I will try to get how much of the RM19 billion that was said to have come in went mostly to the existing industrial sites and factory areas in the State of Selangor. But if I want to know how much went to Sabak Bernam, I am not sure. But if we say there is none at all, that cannot be right, because in the end the economic cycle moves quite widely. It does not stop only at the factory site. Certainly there are downstream industries. Certainly there are support service industries and so on. The State Government tries to link these, and we launched SELDEC. SELDEC is to link and connect the small industries there, such as snack food and keropok manufacturing and so on, to be marketed directly in urban areas, especially in Shah Alam, Petaling Jaya, Subang, and even Kuala Lumpur. That is what I can answer for now. Thank you.

SpeakerEN

Sungai Air Tawar.

Tuan Rizam bin IsmailUMNO · BNSungai Air TawarEN

Thank you, Honourable Mr Speaker. My question concerns this wing: are there efforts by the State Government to bring in investors, or long-term plans to build factories in the DUN Sungai Air Tawar, considering that in the DUN Sungai Air Tawar there are already factory and industrial sites that were built previously, but until now there has been no plan from the State Government to build factories or industries in the DUN Sungai Air Tawar.

Tuan Amirudin bin ShariPKR · PHMenteri Besar · Sungai TuaEN

Thank you. Our planning looks at the level of districts and developed localities, so we do not look specifically at one place. That is why I mentioned earlier that we have an attempt to build an industrial area, and the factories are low-cost factories. Unfortunately, I see that the figures show no one has taken them up or wanted to develop there, so I asked the Honourable Pandan Indah, the Honourable Batu Tiga and the Honourable Kota Kemuning to sit together, look at and develop these potentials. The State Government sees the WCE as one important catalyst for development in Sabak Bernam, but if we are not prepared, we will get nothing, and instead it will overflow outside the State of Selangor, such as to Bagan Datok and so on.

Therefore, we will look at these sites, including the industrial sites that have been gazetted or zoned, and we are ready to receive the overflow when everything is completed and in good order. That is why this cluster was established to look at the existing potential, so we have started several projects, mostly agricultural projects, but at this time we want to ensure that the projects use the latest technology, and the use of the latest technology is cleaner, more precise, more pre-size, meaning it is more

attractive to young people to settle in the village or locality that the Honourable Member raised, and we avoid mass migration to urban areas which causes a shortage of human resources in the areas concerned. Thank you.

Tuan Harumaini bin Haji OmarBERSATU · PHBatang KaliEN

Honourable Speaker.

SpeakerEN

Yes, Batang Kali.

Tuan Harumaini bin Haji OmarBERSATU · PHBatang KaliEN

Thank you, Honourable Mr Speaker. It was also mentioned earlier that the northern wing involves Hulu Selangor. As was also mentioned by the Most Honourable Member on 8 July this year, a launch was made in Kuala Kubu Baru. I feel that adventure sports in Kuala Kubu Baru, as we saw yesterday, have very high potential in the Kuala Kubu area. Did the Most Honourable Member allocate a specific budget to boost the adventure sports that we have all witnessed together? Thank you.

Tuan Amirudin bin ShariPKR · PHMenteri Besar · Sungai TuaEN

Thank you, Batang Kali. What I meant by the P3S registration earlier is to regulate or organise their registration. It is very unfortunate that if we measure our income from the tourism sector in the past, it was only measured at RM20 million, but the figure may be twice that, or at least three-quarters more than the figure it should be, because several activities such as Inap Desa and Inap Dusun. In the Hulu Selangor area there are Inap Dusun, and along the road to Batang Kali and Genting I believe there are several areas that have been developed but are not registered, not registered as legitimate institutions, or as institutions that can generate revenue for the state, and are not captured in the registered lists of tourists staying and so on. That is why the refinement of P3S data carried out by the Standing Tourism Committee under Selat Klang can help, to some extent, efforts to generate revenue for the state, including the registration of these adventure sports activities. It is no longer a matter of allocation, Honourable Member. For me, at this time, the programme already exists and the activities are already running. The question is how the government can focus on what can be assisted, especially infrastructure, facilities, networking and databases, or lists of data on the programmes and activities that are running. Thank you.

Speaker

Batang Kali.

Tuan Harumaini bin Haji OmarBERSATU · PHBatang KaliEN

Thank you, Mr Speaker. My question is 118.

Oral Questions — 118. Officer Exchange Scheme Between Local AuthoritiesQuestions

Tuan Harumaini bin Haji OmarBERSATU · PHBatang KaliEN

118. To ask the Y.A.B. Dato' Menteri Besar:-

a) Does the government intend to implement this scheme for senior-level officers, as this could increase productivity and also add to their experience?

Tuan Ng Sze HanDAP · PHKinraraEN

Thank you, Mr Speaker. At present, the appointment of senior management of the PBT, namely the Datuk Bandar, Yang Dipertua, Deputy Datuk Bandar, Deputy Yang Dipertua and Secretary, is based on the Local Government Act 1976 (Act 171), through approval by the State Authority, namely the Selangor State Government Executive Council (MMKN), and Service Circular No. 12 of 2008, Policy and Procedures for Secondment, Temporary Exchange and Permanent Exchange of Appointments. Secondment or temporary exchange is one of the methods of appointing serving officers that can be used by an agency to obtain the services of experienced, skilled, competent officers who suit the agency's requirements to fill vacant or closed posts.

Basically, the State Government does not set any mechanism or schedule for carrying out the exchange of senior management from one PBT to another PBT, and it is subject to current needs in line with the provisions of the law in force. As for PBT officers other than senior management, movement or exchange of officers is only carried out within each PBT according to that PBT's needs.

For information also, the Federal Government through the Ministry of Housing and Local Government (KPKT) is studying and examining the feasibility of establishing the Local Authority Service Commission (SPPBT). If the establishment of SPPBT is implemented, the exchange of officers, including senior management between PBTs, is expected to be implementable, and at the same time could provide career advancement opportunities for PBT officers and staff. Thank you.

Tuan Mohd Shaid bin RosliBERSATU · PHJeram

Soalan tambahan.

Speaker

Pelabuhan Klang.

Tuan Azmizam bin Zaman HuriPKR · PHPelabuhan KlangEN

Thank you, Honourable Mr Speaker. My question concerns the exchange of officers in local authorities mentioned earlier by the Honourable EXCO Member, according to the needs of each respective PBT, meaning officers are not transferred between PBTs because their job offer letters are for that PBT. My question is whether the State Government monitors the exchange of officers within PBTs, given that some PBTs transfer their officers not according to the needs that should apply, for example, if an officer's expertise is in the field of law, they should be placed in the Legal Department, not in a different department, which makes that department inefficient, and for example, if an officer is skilled in or whose expertise is needed in the Landscape Department, but they are placed in another department other than the officer's skills. What is the State Government's view?

Tuan Ng Sze HanDAP · PHKinraraEN

Thank you, Pelabuhan Klang. The internal transfer of officers in each PBT is the power of the Yang Dipertua or the power of the Datuk Bandar,

if there is an exchange that is appropriate or not in line with the qualifications, with permission, that the officer has, then I think a complaint can be submitted to the State Government for investigation. Thank you.

Tuan Mohd Shaid bin RosliBERSATU · PHJeram

Soalan tambahan.

Speaker

Jeram.

Tuan Mohd Shaid bin RosliBERSATU · PHJeramEN

Thank you, Mr Speaker. As said by the Honourable EXCO Member earlier, regarding officers not being able to be transferred to different councils, does the government intend to enact that law? That is the first. The second is whether a proposal or request from an ADUN for the exchange of an officer can be considered. This is because we find that some officers, not all of them, yes, do not cooperate. When we call them to resolve a problem, it is not the YDP or the Datuk Bandar, the officer sends a representative who cannot make decisions, so this will complicate the resolution of the people's problems, so...

Speaker

Soalan-soalan terus.

Tuan Mohd Shaid bin RosliBERSATU · PHJeramEN

That's it, question 1 is done, question 2.

Speaker

Jangan dualah.

Tuan Mohd Shaid bin RosliBERSATU · PHJeramEN

Both questions are done, so can the ADUN request the State Government to transfer that officer. Thank you.

Tuan Ng Sze HanDAP · PHKinraraEN

Thank you, Jeram. For the first question, as I have already answered, KPKT is in the process of establishing a commission, namely the Local Authority Service Commission, and after this commission is established, we can lawfully carry out the transfer of officers from one PBT to another PBT. For the second question, I think there is no problem if anyone wants to propose the transfer or promotion of an officer, but for PBTs, the power remains under the Yang Dipertua or the Datuk Bandar themselves. The proposal can be made, but the decision will be made by the YDP and the Datuk Bandar. Thank you.

Speaker

Batang Kali.

Tuan Harumaini bin Haji OmarBERSATU · PHBatang KaliEN

Honourable Mr Speaker, this question is originally my question, but I gave the opportunity to Meru and Jeram. The question is whether the government intends, while waiting for the KPKT Commission to enact the law, we do not know when, so does the government intend to hold a swap between PBTs, for example, this is an example. For example, between the PBT of Sabak and Hulu Selangor..

HOUSE: Agree.

Tuan Harumaini bin Haji OmarBERSATU · PHBatang KaliEN

A bit louder, can you be a bit louder, agree?

HOUSE: Yes.

Tuan Harumaini bin Haji OmarBERSATU · PHBatang KaliEN

Perhaps a swap can be made between the director there and the director of the Hulu Selangor PBT. Perhaps a swap can also be made with other PBTs, so this would give the parties concerned an opportunity to improve their skills or perhaps be promoted and so on, rather than them always looking at the same faces every day, so perhaps the government can consider it. Thank you.

Tuan Amirudin bin ShariPKR · PHMenteri Besar · Sungai TuaEN

Thank you for involving the service. Let me explain so that it is clear. First, we must see that these local authorities (PBT) are a government in their own right. They appoint, they select, and the reason the system is indeed circular there, an attempt at a swap, we have done before, but there are 3 conditions. The first condition is that the person to be transferred agrees to transfer, the second is that the council that wishes to receive the replacement agrees, and the third is that the party releasing them agrees. When all three conditions are met, the exchange takes place. If all three conditions are not met, it means an exchange or swap as proposed by Batang Kali cannot take place, and we have done it in 2009, 2010 and so on, and there was an effect too. The effect is that the vacancies left by those posts cannot be filled as long as the substantive duties there, for example at level 44 or 52, while the person is on loan, so the level 52 vacancy cannot be filled by new officers and so on. So we must understand the basic structure of this government, and I hope that in truth we cannot do it ourselves, we will wait to see whether the Ministry of Housing and Local Government (KPKT) does it or not. If not, we will do it at our own state level so that at the very least local councils can exchange. But if KPKT does it, it is actually even better, because it is not from Sabak to PJ, not from Petaling Jaya to Subang Jaya, but from Petaling Jaya it suddenly reaches Raub, from Raub it can reach Tuaran, and from Tuaran it can land in Sabak Bernam later. That is its effect, and I think it is worthwhile and we must support it and must speed up this effort. Thank you.

Tuan Mohd Sany bin HamzanAMANAH · PHTaman TemplerEN

Taman Templer, just a little bit.

Speaker

Taman Templer.

Tuan Mohd Sany bin HamzanAMANAH · PHTaman TemplerEN

Thank you, Mr Speaker. I would like to ask the State Government whether the State Government intends to appoint the YDP and the Datuk Bandar from among politicians, because currently they are from the PTD. That is my question, thank you.

Tuan Ng Sze HanDAP · PHKinraraEN

Thank you. In fact, the appointment of politicians as YDP or Datuk Bandar can be carried out if we wish to appoint them, but there are many matters that we need to consider, such as management experience, because managing a local authority is not easy, it involves much of the experience that is required. In conclusion, the answer is yes, if we wish to implement it, thank you.

SpeakerEN

The next question, Hulu Bernam. Yes, Sungai Panjang.

Dato’ Mohd Imran bin TamrinUMNO · BNSungai PanjangEN

With the permission of Mr Speaker, I would like to use Standing Order 24 (2) to take the Hulu Bernam question as my question.

SpeakerEN

Yes, I allow it, please proceed.

Oral Questions — 118. Foreign InvestmentQuestions

Datuk Rosni binti SoharUMNO · BNHulu BernamEN

118. To ask the Y.A.B. Dato' Menteri Besar:-

a) State the programmes and efforts that have been carried out to promote the State of Selangor overseas in an effort to attract investors?

b) State the total cost incurred by INVEST Selangor during the effort to seek investors up to September 2019?

c) State the total amount of foreign investment successfully brought in in 2019?

Dato’ Teng Chang KhimDAP · PHBandar Baru KlangEN

Mr Speaker, I request to answer this question together with question 285 raised by Sungai Air Tawar. Mr Speaker, there were 16 programmes carried out to promote the State of Selangor overseas to attract investment for 2019, among them:-

1. Promotional Facilitation Mission to Hong Kong 2. Investment Promotion Mission and Working Visit to Gulfood Dubai 3. Promotional Facilitation Mission to Taipei, Taiwan 4. Annual Investment Meeting (AIM) in Dubai 5. Technical Working Visit to South Korea 6. HKTDC International ICT Expo Hong Kong 7. Korea Cosmetic Ingredient & Technology Exhibition, Kintex, Goyang-Si, Korea (The CI Korea 2019) 8. Investment Facilitation Mission to Japan (The World Food & Beverages Great Expo / Premium Food Show 2019) Tokyo, Japan 9. Investment Facilitation Mission and Booth Selangor Engagement at the Hofex Programme, Hong Kong 10. Selangor Promotion Mission to the ASEAN Business Conference (SABC) in Jakarta, Indonesia 11. Selangor International Business Summit Promotion Mission to Vietnam and the Philippines 12. Visit to Airbus and Launch of the Smart Radome Workshop in Sepang 13. Selangor International Business Summit Promotion Mission to Jakarta

14. Investment Facilitation Mission to France and the United Kingdom and Participation in the International Paris Airshow 15. Investment Facilitation Mission to Korea in conjunction with the Halal Trade Expo Korea

16. Investment Promotion and Facilitation Mission to China (Chongqing, Shenzhen & Qingdao)

Mr Speaker, in principle the State Government of Selangor has no objection to any delegation representing the State Government travelling overseas on official business. The total cost spent for 2018 up to the present in 2019 for the business of attracting investment to the State of Selangor is RM33.09 million, which cost covers various programmes such as overseas investment facilitation missions, dialogue sessions, engagement sessions or engagement with permission, organising and participating in exhibitions locally and overseas, as well as the production of promotional materials. Based on the promotion and facilitation programmes carried out by Invest Selangor, it received 36 proposed investment projects with a potential investment value totalling RM12 billion for 2018 and 29 proposed projects with a potential investment value of RM14.8 billion for the period January to September 2019. However, in 2018 a total of 241 manufacturing projects with an investment value totalling RM18.95 billion were approved to be located in the State of Selangor, while for the period January to June 2019, 132 manufacturing projects with an investment value totalling RM5.97 billion were approved. In conclusion, the State Government of Selangor through Invest Selangor has spent only 0.13% of the investment revenue approved for 2018 to June 2019, which totals RM24.92 billion.

Soalan tambahan.

Speaker

Meru.

Thank you, Honourable Mr Speaker. I would like to ask the Honourable EXCO, earlier we saw a lot about investment, the expos that the State Government goes to. Is there any opportunity for the ADUNs to join? (House laughs) So that we too can get information, because so far we only get information in the House.

Dato’ Teng Chang KhimDAP · PHBandar Baru KlangEN

We will look at it when necessary, yes, because although I have sixteen (16) programmes overseas, I myself do not follow all of them. They are only led by the CEO of Invest Selangor, only by the Director at Invest Selangor, so it is not that I join all of them. Let us see, I too do not go to all of them. And even those we go to, in terms of investment, when we invite investment, it cannot succeed just once, it must be repeated again and again. It means we meet investors and then must do follow-ups, follow-ups and so on. Sometimes we need two to three years to convince the investor to come. So, perhaps for expos that may provide successful exposure to the ADUNs, the State Government can consider it, yes, just consider it.

SpeakerEN

Sungai Air Tawar.

Tuan Rizam bin IsmailUMNO · BNSungai Air TawarEN

Thank you, Honourable Speaker. First, I would like to congratulate on the many investments that are going to come in. May I also know, because apart from the investments that are going to come in, are there investments that had already come in but are no longer here today? That is, they have left. How many investments in the State of Selangor that once existed have relocated to other states and perhaps also to other countries?

Dato’ Teng Chang KhimDAP · PHBandar Baru KlangEN

Yes, Mr Speaker. We have no record of investors who came and then left Selangor or Malaysia. But, in general, this matter is not serious. Usually in the manufacturing sector, in particular, those who leave, especially in the electronics field and so on, they leave for certain reasons. The first is that the products they make no longer have a market. So the factory has to close. For example, video cameras. Nowadays nobody uses video cameras. We all use handphones. So there is no longer a market, it closes. And second, when there is competition, competition from new countries, countries that have newly entered the industry such as Vietnam and so on, where they offer cheaper land, offer workers with lower wages, then we cannot prevent them from leaving our state. And also, perhaps that is a good thing, because we no longer invite labour-intensive investments that need many low-skilled workers, so we focus more on industries that bring high technology, especially in this era of Industrial 4.0. We focus more on manufacturing industries that need skilled and highly educated workers.

Speaker

Permatang.

Thank you, Mr Speaker, my question is No. 120.

Oral Questions — 120. Single MothersQuestions

120. To ask the Y.A.B. Dato' Menteri Besar:-

a)

What is the total number of single mothers who have been successfully helped by being given employment or business opportunities?

b)

What method is used to ensure every assistance disbursed reaches the single mothers?

c)

How does the State Government identify the status of single mothers who do not register?

Puan Dr. Siti Mariah binti MahmudAMANAH · PHSeri SerdangEN

Thank you, Honourable Permatang. Alright, Honourable Permatang asked about the number of single mothers and matters related to them. For the information of the Honourable Members, the Government, through the Selangor State Department of Social Welfare (JKM), disburses welfare assistance to target groups who are in need and eligible. One of the Department's target groups is poor families, including single mothers who are in need.

There are single mothers identified as productive and having the potential to improve family socio-economic status who need to be helped by the Department by implementing the 2 Years Exit Programme, or 2YEP, through the Federal Assistance Scheme. The programme was first implemented in 2016 involving welfare recipients of JKM, including persons with disabilities, senior citizens and poor families.

For the information of the Honourable Members, this Department has injected funds as initial capital, namely the Launch Grant Assistance for clients to run small businesses. Based on records, 750 single mothers receiving assistance at JKM Selangor State were involved with monthly assistance allocations under the Federal Assistance Scheme totalling RM218,600.00. The Department identified 75 single mothers who were potential and productive in advancing themselves, but only 24 succeeded in improving family socio-economic status through the 2YEP programme. The achievement for the category of successful single mothers is 32% for the period 2016 to 2018. Hijrah has also provided loans to 2,800 single mothers, yes, in the State of Selangor. For the information of the Honourable Members, the Selangor State Department of Social Welfare disburses welfare assistance monthly to target groups through the district Social Welfare Offices. The Department uses the e-Bantuan JKM system and integration with the IGFMAS system for the process of application, reporting, investigation, approval, voucher generation, certification and monthly assistance payment. Assistance recipients receive the aid money, which is credited to the account through Electronic Fund Transfer, or EFT.

Honourable Permatang, for the time being, the State Government has three (3) single mother databases under the Selangor State Department of Social Welfare, the Department for Women's Development (JPW) and Yayasan Anak Warisan Selangor, which were gathered through voluntary registration of single mothers at the State Assembly Service Centre. The State Government is now in the process of studying the best mechanism to merge these three databases under one system so that cross-checking and updating can be carried out effectively so that there are no cases of repeated or missing names. However, the main challenge in collecting data on these single mothers is updating the records because their latest marital status can change at any time. The figures that we know now: single mothers who receive JKM assistance, 750 persons; YAWAS, those recorded, registered up to August 2019, 18,974 persons; JPW, this has not been updated for 10 years, 14,000 persons; and those who borrowed from Hijrah, 2,800 persons. However, these are not absolute figures because there is overlap and changes in information from time to time. Thank you.

Speaker

Bukit Gasing.

Tuan Rajiv A/L RishyakaranDAP · PHBukit GasingEN

Thank you. For single mothers who are not divorced, or who cannot afford a divorce, or whose husbands left them without divorce, do they receive the same assistance as other single mothers?

Puan Dr. Siti Mariah binti MahmudAMANAH · PHSeri SerdangEN

Ok, thank you. This question is very important. It is indeed a dilemma for us. For them we call them either "ibu tinggal" (abandoned mothers), where there is a husband but the husband is missing. And there is another one, "ibu tunggul" (stump mothers).

(House laughs). Ok, these "ibu tunggul", their husband is sometimes there and sometimes not. Like chocolate chips, yes. And sometimes he comes back, sorry, I said..

Tuan Rajiv A/L RishyakaranDAP · PHBukit Gasing

Suami tunggul.

Speaker

Kasihan kasihan.

Puan Dr. Siti Mariah binti MahmudAMANAH · PHSeri SerdangEN

Sometimes he comes back and only adds to the population, yes. So our problem in helping them, Honourable Members, is for JKM assistance, documentation must be there. JKM must ensure she is truly a single mother, yes. And if there is no record, like an "ibu tinggal" whose husband is not there but there is no record, she has to make a police report, for example that her husband has been missing for several years, for instance, and obtains support from either the Village Head or so on. And for cases like this we consider them, but Honourable Members, there are funds at hand, yes, perhaps we can help them when they are in need, and it is indeed a dilemma for us, yes, the mothers. Sometimes single mothers whose husbands have died find it easier for their children to receive assistance because they are orphans, but "ibu tinggal" who have children do not receive adequate maintenance from their husbands, and their children cannot be categorised as orphans. That is all, Honourable Members, thank you.

Tuan Harumaini bin Haji OmarBERSATU · PHBatang KaliEN

Honourable Speaker.

Speaker

Batang Kali.

Tuan Harumaini bin Haji OmarBERSATU · PHBatang KaliEN

Thank you, Honourable Mr Speaker. I congratulate the relevant EXCO because there are many single mothers in my constituency, with many categories. Those under 30 are still okay. (House laughs). I see Mr Speaker is smiling too. There are those under 40 and so on. What I want to mention here is how Honourable Speaker has run a KISS programme, for example, Honourable Speaker has sent..

Speaker

Yang Berhormat.

Tuan Harumaini bin Haji OmarBERSATU · PHBatang KaliEN

Has already sent these single mothers for an incentive training in which I was directly involved. The question now is whether Honourable Speaker intends to establish a single mothers' plaza, for example, in a strategic location so that they can, their abilities can be brought out by marketing their market.

HOUSE:

A single mothers' plaza, yes?

Tuan Harumaini bin Haji OmarBERSATU · PHBatang KaliEN

Yes, a single mothers' plaza, so thank you, Honourable Mr Speaker.

Puan Dr. Siti Mariah binti MahmudAMANAH · PHSeri SerdangEN

Ok, Batang Kali. This is a proposal that we must really examine carefully, because some single mothers do not like being labelled as single mothers, yes, because of the stigma in society. All the State Government's programmes actually do not marginalise them. For all programmes, if they qualify according to the criteria set by IPR, the IPR criteria of the programme, they can receive assistance. Yes, they can, how shall I say, apply. Yes, creating a database is good, but to get this database for them to register themselves, among them is through PKM, all of it, but single mothers often ask, why register, what is it for, what will we get from it? They want to know what we will give them in the form of programmes. So, I suggest that what was mentioned earlier by Honourable Speaker should also be done by all ADUNs who have identified them. Give them suggestions of the existing programmes. Under my programme as well, under STANCO Women's Empowerment now, among the programmes we will carry out a pilot project this year is work from home for KISS participants. These are poor people who receive KISS but not all of them are single mothers, yes. So, I very strongly encourage it, and if we will, actually our plan from last year but we did not have time to do it, is a Town Hall with single mothers to hear directly from them how we can help them specifically. But I ask all Honourable Members not to ask me to create data to find partners for them. (House laughs).

Speaker

Pandamaran.

Tuan Leong Tuck CheeDAP · PHPandamaranEN

Thank you, Mr Speaker. My question is 121. Thank you.

Oral Questions — 121. Use of Plastic BagsQuestions

Tuan Leong Tuck CheeDAP · PHPandamaranEN

121. To ask the Y.A.B. Dato' Menteri Besar:-

a)

Please state the steps that have been taken by the State Government to make the Selangor Plastic Bag Free campaign a success.

b)

Has the State Government ever taken action against operators who give away plastic bags free of charge?

Tuan Hee Loy SianPKR · PHKajangEN

Thank you, Mr Speaker. The State Government, through twelve (12) Local Authorities (PBT), has implemented various programmes related to the Plastic-Free Campaign across the State of Selangor. Among the programmes implemented annually at every PBT are the Consumerism Roadshow Carnival and the Sustainable Ramadan Bazaar Programme, whose main focus is to promote and intensify the Plastic-Free Campaign as well as consumerism campaigns and other environment-related campaigns.

The PBT also actively carries out continuous promotion through campaign publicity via digital broadcasts, advertising boards or billboards, banners, and hanging displays around the PBT's administrative areas.

The State Government has also taken steps to ban free plastic bags and the use of polystyrene on every day beginning 1 January 2017. A charge of twenty (20) sen for each use of a plastic bag is imposed by traders at business premises that provide plastic bags, particularly on a large scale to consumers, such as at hypermarkets, supermarts, minimarkets and so on. Through this campaign, the charge on the use of such plastic bags is intended to create awareness among consumers of the dangers of plastic bags to the environment and health.

In addition, the State Government also works together with various government agencies, including the Ministry of Domestic Trade and Consumer Affairs (KPDNHEP) of the State of Selangor, educational institutions (schools and universities), as well as associations or NGOs to make the programmes related to the Plastic-Free Campaign a success. For example, the organisation of the Selangor Student Consumerism Carnival together with KPDNHEP Selangor, and the "No Plastic Awareness Campaign" programme together with the Selangor and Kuala Lumpur Hawkers and Small Traders Association.

The State Government also formulates policies and State Government directives applicable to the public and the government agencies involved, through the distribution of State Government circulars that have been verified and approved by the State Executive Council of Selangor, as follows:

i. Circular Letter on the Proposal to Reduce the Use of Plastic Bags and Polystyrene in the State of Selangor dated 2 August 2016; and

ii. Circular Letter on the Implementation of the Campaign to Avoid Single-use Plastics in Ministries, Federal and State Government Agencies dated 28 June 2019.

These policies and campaigns that have been held are in line with the action plan outlined in the Roadmap Towards Zero Single-use Plastics 2018-2030 launched by the Ministry of Energy, Science, Technology, Environment and Climate Change (MESTECC) on 17 October 2018. To answer the second question, has the State Government ever taken action against operators who provide free plastic bags?

The State Government, through the PBT, has imposed a condition prohibiting the provision of free plastic bags to customers in the Licensing and Permit Conditions for traders. Accordingly, the PBT has issued warning notices or directives to traders found to be giving free plastic bags to buyers. So, we do not impose enforcement, we do not issue summonses; we only give them soft education, but we have not put licence conditions so that

they can comply with our directives. The State Government will also carry out continuous monitoring through the PBT to ensure this campaign is implemented well and in line with the established policies. That is all.

Speaker

Kampung Tunku.

Puan Lim Yi WeiDAP · PHKampung TunkuEN

Thank you, Mr Speaker. My supplementary question is this: those who work late at the office at night rely on GrabFood and Foodpanda as lifesavers, but I see that many restaurants under GrabFood or Foodpanda deliver their food in plastic bags and also use plastic forks and spoons. So, does the State Government have any plans to engage, with permission, suppliers such as GrabFood and Foodpanda on the issue of plastic bag use, thank you.

Tuan Hee Loy SianPKR · PHKajangEN

Thank you, Kampung Tunku. At this time we plan to hold a dialogue not only with bubble tea traders but also involving the GrabFood operators mentioned by Kampung Tunku. We are currently arranging dates so that we can hold a meeting with these players who run fast food or GrabFood activities as mentioned earlier. Thank you.

Soalan tambahan.

Speaker

Ijok.

Thank you, Honourable Member, Mr Speaker. Ijok has 2 questions, No. 1.

Speaker

1 sahaja.

Okay, in the past we usually used paper bags. Now, if we go to the supermarket, there are no paper bags, but they encourage us to use plastic. What efforts is the State Government of Selangor making to require dry goods to be packed in paper bags, except that wet goods may be packed in plastic? This is a start to reducing plastic use.

Tuan Hee Loy SianPKR · PHKajangEN

Thank you for the question raised by Honourable Ijok. To Honourable Ijok, it is not that we are leaving it to the traders. Some traders do use paper bags, but paper bags have two problems. The first is that their cost is quite high. The second is that if the Honourable Member for Bukit Lancang does not like using paper bags, because using paper bags means trees have to be felled to make paper, that is a problem.

I disagree. In the past we used paper bags, because we could recycle them. In my view, the efforts that always try to force plastic bags to be prepared are because they want to charge 20 sen, and I would like to ask Ijok: where does the 20 sen go?

Tuan Hee Loy SianPKR · PHKajangEN

In answer to the question raised by Honourable Ijok, apart from paper bags, we do encourage them to bring recycled bags, and we also encourage operators to provide paper bags. Second, we encourage education on this problem, which is important. We are running a campaign to educate the people of the State of Selangor so that we avoid the use of plastic bags or single-use plastic bags.

To answer the question of where the 20 sen goes: for the time being it still remains with the traders who collect it. Unfortunately, we find that this effort has not succeeded, because although we encourage them, after collecting the 20 sen they should use this money for CSR, such as planting trees, or providing free recycled bags to consumers. But some did and some did not. That is why we have set, starting 1 January 2020, subject to the approval of the EXCO paper which we will table tomorrow, whether to accept that the 20 sen will be collected by the PBT. We have already drafted this plan, where the PBT will collect the 20 sen from us. We give this opportunity to the traders. That is all.

Speaker

Pandamaran.

Tuan Leong Tuck CheeDAP · PHPandamaranEN

Thank you, Mr Speaker. My question to Honourable EXCO is: when will the State Government enforce action against operators or traders who are stubborn, defiant, and continue to give out free plastic bags? We see that many operators or small traders are still giving out free plastic bags. Thank you.

Tuan Hee Loy SianPKR · PHKajangEN

Be patient. Honourable Pandamaran, for the time being we are taking a soft approach, providing education, teaching. Our focus is on our programmes in schools. Now we want to teach our children, our pupils, to avoid plastic bags. So this is a long-term effort, so we hope you will be patient. If we follow our target, we will be earlier than the Federal Government. The Federal Government has set 2030, 10 years from now, while Selangor has set 5 years from now, that is 2025. If there is a replacement, where there is an alternative to these plastic bags, namely in terms of price and quantity, we will implement it 5 years earlier than the Federal Government.

SpeakerEN

Sungai Air Tawar.

Tuan Rizam bin IsmailUMNO · BNSungai Air TawarEN

Thank you, Honourable Member, Mr Speaker. In particular, I strongly agree with the question raised by Honourable Ijok earlier. My supplementary question concerns any operators or shops that have changed from using plastic to possibly using paper bags: will consumers still be charged for the paper bags that replace the plastic ones?

Tuan Hee Loy SianPKR · PHKajangEN

Thank you, Sungai Air Tawar. Since when has the opposition been so agreeable to our campaign? I still remember that when we held this campaign, the State UMNO Chairman said we would give out plastic bags for free if we won the State Government of Selangor. I still remember, sorry, I must say this is a consumer struggle..

Tuan Rizam bin IsmailUMNO · BNSungai Air TawarEN

I agree that plastic bags should be replaced, but what worries me is the consumer's use. These consumers are like being forced to pay for plastic bags. If we run an anti-plastic bag campaign, we should replace plastic bags with other alternatives, but consumers feel bound, with no other alternative. This means that when buying goods, they must pay for plastic bags, yet shops do not give them a choice. There should be options other than plastic bags so that they do not have to pay. This applies to most places, including night markets and morning markets.

Tuan Hee Loy SianPKR · PHKajangEN

To the Leader of the Opposition, since you support our campaign, I hope you will not raise the issue of giving plastic bags for free in the campaign, such as the Election Manifesto that was said last year. We have alternatives: we encourage consumers to bring recycled bags if they do not want plastic bags. If they still want them, then before that, take 5, take 1, it is enough to pay 20 sen, and this will be reduced in the future. So I encourage people to bring not only recycled bags but also containers if they want takeaway food (tapau) or to buy food and wet goods. That is what the State Government of Selangor is working on. That is all.

Speaker

Pelabuhan Kelang.

Tuan Azmizam bin Zaman HuriPKR · PHPelabuhan KlangEN

Thank you, Mr Speaker, the Pelabuhan Klang question No. 122.

Oral Questions — 122. Rumah SelangorkuQuestions

Tuan Azmizam bin Zaman HuriPKR · PHPelabuhan KlangEN

122. To ask the Y.A.B. Dato' Menteri Besar:-

a)

What is the government's record of action so far against owners who have sub-let their Rumah Selangorku to third parties from 2017 until now?

b)

Has the State Government found the best solution to prevent this from happening again?

c)

What are the next steps against them?

Puan Haniza binti Mohamed TalhaPKR · PHLembah JayaEN

Thank you, Honourable Member for Pelabuhan Klang. Pelabuhan Klang asked about action against owners who sub-let Rumah SelangorKu to third parties. For the Honourable Member's information, the Selangor Housing and Property Board (LPHS) will take action by conducting on-site investigations for every complaint submitted in relation to the issue of renting out Rumah Selangorku (RSKU), in order to verify the complaint, in line with the functions and powers provided under Section 6 of the Selangor Housing and Property Board Enactment 2001 in implementing the directive of the State Authority.

So, based on the records so far, a total of 6 site visits covering 19 units of Rumah SelangorKu have been carried out for the purpose of investigation at the locations involved, as follows:

- Putra Apartments, Taman Putra Prima Puchong (2 units) - Azaria Apartments, Bandar Parkland in Klang, the largest number (10 units) - Gapura Bayu Apartments, Jade Hill Kajang (1 unit) - De Palma Apartments, Setia Alam (2 units) - De Kiara Apartments, Setia Alam (2 units); and - Trifolis Apartments, Bandar Bukit Tinggi, Klang (2 units), raised earlier by Banting, Bandar Bukit Tinggi Klang (2 units)

So the Board went to conduct investigations, and 6 RSKU units at Azaria Apartments, Bandar Parkland were administratively removed by the Board from the units rented out to foreigners. Furthermore, if it is found that there are implications arising from the renting out by the owners of the Rumah Selangorku, which cause other ancillary offences such as unapproved alterations, followed by illegal wiring, overcrowded occupancy exceeding the limit, and also nuisance, whether noise or discomfort, feelings of insecurity and so on, based on the provisions under the Local Government Act 1971, which is the Act, and also the Street, Drainage and Building Act 1974, which is Act (133), the matter will be referred to the Building Commissioner's Department (COB) and the relevant Local Authority for action. Apart from that, the developers who built Rumah Selangorku, the Joint Management Body (JMB) and the Management Corporation (JMC) are advised to take control measures through house rules permitted under the Third Schedule of the Strata Regulations 2013, under maintenance and management, and the Strata Management Act, Act (757), specifically to protect the interests and ensure the level of safety, comfort and well-being of owners and occupants there.

To curb this problem, we also receive the concerns and worries that RSKU units are being rented out. The Selangor Housing and Property Board has taken several actions. The first is to conduct investigations and re-examine the offering process to the buyers of RSKU. Second, to issue notices to obtain statements from buyers who rent out their units. Third, to carry out coordination with other parties such as COB and PBT. And fourth, to be involved in integrated operations together with the local authorities. So we, together with the Local Authority, go together to examine the units that have been rented out. Fifth, directing the developers who built Rumah Selangorku to make by-laws under the Third Schedule of the Strata Regulations 2013 so that they can control access card use for entry into the residential area and also for those occupying RSKU units. Furthermore, to draft additional by-laws to be applied by all Rumah Selangorku, covering provisions for punitive action including fines against offenders who commit offences under these by-laws, to ensure they comply with the Rumah Selangorku conditions that do not allow renting out to third parties. And finally, to carry out coordination

in managing rental complaints and joint enforcement with the Local Authorities, and now we are in the process of issuing an RSKU management manual, in which we have listed matters or steps that can be taken to control the renting out of these units. That is all. Thank you.

Tuan Azmizam bin Zaman HuriPKR · PHPelabuhan Klang

Soalan tambahan.

Speaker

Pelabuhan Klang.

Tuan Azmizam bin Zaman HuriPKR · PHPelabuhan KlangEN

Thank you, Honourable Member, Mr Speaker. I would like to ask Honourable Lembah Jaya about Rumah Selangorku. Does the State Government intend to hold a one-day course for those who have successfully obtained Rumah Selangorku, before the keys are handed over? This means that until they attend the one-day course, because when they want to live in these apartments there are many restrictions: you cannot keep animals, you cannot keep chickens, you must form a JMB, parking is one lot and two lots to one house. So a course is needed. Once they qualify for the course, they cannot say they did not know, this is what they did not know. After one day of training, only then are the keys handed over. This is best, so they understand that living in an apartment is not the same as living in a terrace house.

Puan Haniza binti Mohamed TalhaPKR · PHLembah JayaEN

Thank you, Pelabuhan Klang. Pelabuhan Klang's thinking is the same as the thinking of the Selangor Housing and Property Board. This is because we have also included the matters that Pelabuhan Klang mentioned earlier in the RSKU Management Manual, and we have placed that responsibility on the developers who will hand over the keys; before handing over the keys, they will hold a briefing session. As for how these units are managed after occupation, as Pelabuhan Klang mentioned earlier, animals, pets and so on may not be kept. Renting out the unit is also not permitted, and they must also look after the shared areas. Common property. So all of this is in the manual. God willing, there will be no obstacles, and this manual will be issued and can be used by the end of this year. Not only for RSKU but also for other apartments managed by JMB. I also see this as a more systematic approach compared with before.

Speaker

Teratai.

Tuan Lai Wai ChongDAP · PHTerataiEN

Thank you, Mr Speaker. What is the way for the public to lodge a complaint about the renting out of Rumah Selangorku, other than by lodging a complaint with the ADUN and Parliamentary Service Centres?

Puan Haniza binti Mohamed TalhaPKR · PHLembah JayaEN

Thank you, Honourable Teratai. In fact, they can lodge a complaint directly with LPHS. It does not need to be in writing or online; they can also use the LPHS email, because we always follow up on any suggestions, complaints and so on. And if the ADUN Service Centre or the Parliamentary Service Centre receives any complaints, they can directly forward them to LPHS so that investigation action can be carried out. Thank you.

Dato’ Mohd Imran bin TamrinUMNO · BNSungai Panjang

Soalan tambahan.

Speaker

Sungai Panjang.

Dato’ Mohd Imran bin TamrinUMNO · BNSungai PanjangEN

Thank you, Honourable Member, Mr Speaker. Regarding Rumah Selangorku, we have heard various problems earlier. Apart from the government, with permission, being right on with the existing Acts, the Local Government Act, the Street, Drainage and Building Act, and also the house rules under this strata Act, is there a government plan to establish a specific law for regulating Rumah Selangorku, because many more Rumah Selangorku are being offered and built by the government. Thank you.

Puan Haniza binti Mohamed TalhaPKR · PHLembah JayaEN

Thank you, Sungai Panjang. This matter is indeed under our discussion. In fact, we want to obtain views from various parties who previously also imposed such conditions. That means it is not permitted to rent out the unit for a certain period and so on, and what matters and obstacles there are for them to implement this, and how they overcome them. Alongside this, there is also a proposal to establish or enact an enactment that can be used for the State of Selangor specifically for RSKU. Thank you.

Speaker

Sungai Pelek.

Tuan Ronnie Liu Tian KhiewDAP · PHSungai PelekEN

Thank you. My question is 123.

Oral Questions — 123. Urban Poverty ProblemsQuestions

Tuan Ronnie Liu Tian KhiewDAP · PHSungai PelekEN

123. To ask the Y.A.B. Dato' Menteri Besar:-

a)

What assistance programmes has the state government planned for the M40 category, particularly for those in urban areas, given that many of them appear to have been overlooked in terms of assistance, whether from the state or the federal government?

b)

Will the government consider lowering the age requirement for applications for the Rumah Prihatin?

Tuan Amirudin bin ShariPKR · PHMenteri Besar · Sungai TuaEN

Thank you, Honourable Sungai Pelek. The title is poor urban dwellers, but the question is about M40. Nonetheless, I will try to explain, though it is a bit of a mix-up. If we speak of poor urban dwellers, they still belong to the B40 group. Yesterday I already explained the B40 matter; I believe it was the question of the Honourable Sijangkang, and yesterday I answered the question of the Honourable Rawang, namely what programmes under the M40 receive support from the State Government. Among them are Selangor housing, among them educational programmes, and we also include the IPT gift, which we have raised from RM3,000.00 to RM5,000.00, and there are other programmes, among them the Rumah Selangorku programme, which reaches up to RM150,000.00 and RM200,000.00. Eligible recipients are those among them with an income of RM10,000.00 and below, and these are included in the M40 group. However, we can also see the Hijrah programme as an example.

The form of assistance provided is among non-income frameworks. Income is at an initial figure. But to receive a loan of RM50,000.00, we look at their business returns. If we look at the micro entrepreneur fund programme, which provides assistance of up to RM30,000.00, we also look at their income rate, namely the rate of micro industry, which is between RM300,000.00 or RM250,000.00 up to RM500,000.00 over one business cycle. So this shows that the M40 group is always and still within the value of support provided, but based on the sustainable development goals, those who need to be helped are those at the bottom, or below, especially senior citizens, children, the poor and persons with disabilities. Focus is given by the State Government and followed by some support for the M40 group. The programme organised by Sitex for Application 100 is not focused on the B40 group but rather on M40 groups. Thank you.

Speaker

Hulu Kelang.

Tuan Haji Saari bin SungibAMANAH · PHHulu KelangEN

Mr Speaker, question number 124.

Oral Questions — 124. Status of New Relocation Site for Susur Ukay Perdana TradersQuestions

Tuan Haji Saari bin SungibAMANAH · PHHulu KelangEN

124. To ask the Y.A.B. Dato' Menteri Besar:-

a)

By answering my question, does the statement that "the State Government, the Gombak District and Land Office and the MPAj never promised to provide new accommodation for traders" mean that the State Government's guarantee contained in the Selangor State Assembly Hansard, 9 Nov 2017, p. 19, has been cancelled?

Tuan Ng Sze HanDAP · PHKinraraEN

Thank you, Honourable Hulu Kelang. The Honourable Hulu Kelang asked what the actual status is of the new relocation site for the traders along Ukay Perdana. Mr Speaker, the current status of the new relocation site for the traders along Ukay Perdana is as follows. First, the application for gazettement of the stall site has been approved by the Honourable Dato' Menteri Besar of Selangor on 19 September 2019, and it is in the process of preparing the approved plan by the Selangor Department of Survey and Mapping Malaysia (JUPEM Selangor). Second, every gazette of the allocation and this site will be made after the PBT Gombak receives the approved plan for the said site from JUPEM Selangor. Third, MPAj may build the stalls and subsequently rent them to the traders concerned after the gazette notice is printed by Percetakan Nasional Berhad. Thank you.

Speaker

Hulu Kelang.

Tuan Haji Saari bin SungibAMANAH · PHHulu KelangEN

Mr Speaker, Honourable EXCO Member, thank you for the Dato' Menteri Besar's decision, but that is not my question. My question is actually the written question that was answered earlier by the Menteri Besar. The Gombak District and Land Office and the MPAj never promised to provide a new place for the business site. So I asked because in the relevant Hansard page it states that the guarantee from the State Government is to give them a new site. My purpose is to correct the error and the contradiction in these two answers. Please read the question again. That is my intention. I want to correct it.

Tuan Ng Sze HanDAP · PHKinraraEN

I still do not see the question from the Honourable Member, because I think I have already answered it, since the site will be prepared and gazetted soon.

Tuan Haji Saari bin SungibAMANAH · PHHulu KelangEN

My question is: by answering my question that the State Government, PTD Gombak and the MPAj never promised to provide new accommodation for traders, does this mean that the State Government's guarantee contained in the Selangor State Assembly Hansard, 9 November 2013, page 19, has been cancelled? And to help my government, I asked this question in writing with more detail. It was answered with the same question.

Tuan Ng Sze HanDAP · PHKinraraEN

In the Honourable Member's question, the Honourable Member asked what the actual status is of the new relocation site for the traders along Ukay Perdana. Is this your question, Honourable Member? What is the actual status? So the answer I gave just now has explained the current status.

Tuan Haji Saari bin SungibAMANAH · PHHulu KelangEN

But for me, there is no acknowledgement of the error. That is my purpose. My purpose is not to weaken the government, but to ensure that the Dato' Menteri Besar, the guarantee statement is in the Hansard stated by the former Dato' Menteri Besar of Bukit Antarabangsa. Then the second answer, that there was no State Government guarantee and it never promised to provide new accommodation, was answered by Sungai Tua. So I do not like there to be contradictions in the Hansard, which is why I asked two questions. One in writing and one orally, to ensure it is fair to the government to answer both questions. What I want is a statement of apology for the error that was made.

Tuan Ng Sze HanDAP · PHKinraraEN

Honourable Member, I think there is a problem regarding the Hansard. Later I will discuss with Mr Speaker to correct it. Thank you.

Tuan Haji Saari bin SungibAMANAH · PHHulu Kelang

Terima kasih.

SpeakerEN

Question no. 125 from the Honourable Jeram has already been answered together with question 59, so there is no need to stand up, okay.

Tuan Mohd Shaid bin RosliBERSATU · PHJeramEN

There is an additional question.

SpeakerEN

None. Tanjung Sepat. Tanjung Sepat. Just joking.

Tuan Borhan bin Aman ShahPKR · PHTanjong SepatEN

Thank you, Mr Speaker, my question is 126.

Oral Questions — 126. Yayasan Selangor IncomeQuestions

Tuan Borhan bin Aman ShahPKR · PHTanjong SepatEN

126. To ask the Y.A.B. Dato' Menteri Besar:-

a)

Please state the income of Yayasan Selangor for the 5-year period from 2014 until now.

b)

What caused this problem, and what is the management of the Foundation's proposal to increase the income of Yayasan Selangor?

Tuan Amirudin bin ShariPKR · PHMenteri Besar · Sungai TuaEN

I have already answered this together with the Port Klang question. Port Klang and also Ijok. But interestingly, the Port Klang question and the Tanjung Sepat question are the same. Not one word, not even one letter, differs. So I have to investigate this. (Laughter). That is correct. Not a single full stop or letter differs between the two questions.

SpeakerEN

Thank you, the Honourable Sungai Tua. That means there is a copycat issue. Who copied whom, I will investigate. I will investigate. Next, Sungai Burung, absent. Bandar Utama.

Puan Jamaliah binti JamaluddinDAP · PHBandar UtamaEN

Thank you, Mr Speaker, my question is 128.

Oral Questions — 128. Method of Delivering Contributions under Skim Mesra Usia Emas (SMUE)Questions

Puan Jamaliah binti JamaluddinDAP · PHBandar UtamaEN

128. To ask the Y.A.B. Dato' Menteri Besar:-

a)

Will the State Government improve the method of delivering SMUE contributions to Selangor's senior citizens? For example, allowing senior citizens to obtain shopping vouchers throughout the year and not only in the birthday month, so that no one is left behind.

Puan Dr. Siti Mariah binti MahmudAMANAH · PHSeri SerdangEN

Thank you, Honourable Bandar Utama. The Honourable Bandar Utama is asking about the improvements to the SMUE Contribution to Selangor's Senior Citizens. For the information of Honourable Members, among the objectives of the Jom Shopping SMUE Programme, which is carried out according to the members' birth month, are as follows. First, to celebrate the birthdays of SMUE Members as well as being one of the family activities that can strengthen relationships. Second, to encourage applications among eligible senior citizens and OKU to register for SMUE, given that assistance is provided during their lifetime and according to the birth month of SMUE Members. Third, delivery according to the birth month of SMUE Members is easier to implement, given that it is provided in stages. Fourth, to facilitate monitoring and management of the distribution of shopping vouchers at the level of the Organiser, Supermarkets as well as the State Assemblyperson Service Centre (Pusat Khidmat DUN). The State Government is of the view that distributing vouchers according to birth month will facilitate many parties, especially YAWAS as the Implementing Agency and the State Assemblyperson Service Centres, in preparing estimates and making earlier preparations for each Jom Shopping Programme to be implemented.

Puan Jamaliah binti JamaluddinDAP · PHBandar UtamaEN

Mr Speaker, additional question.

Speaker

Bandar Utama.

Puan Jamaliah binti JamaluddinDAP · PHBandar UtamaEN

Thank you, Mr Speaker, thank you Honourable EXCO Member for answering part of my question. In the previous debate, Bandar Utama had already given several views on the SMUE issue, and one of the most important issues is when the service centres are unable to handle the numbers of several hundred applicants each month, because we have constraints where we cannot contact each of them, or some of them do not have a mobile phone number, so we cannot send SMS and so on. As a result, many senior citizens who initially felt happy about this programme and thankful to the Selangor State Government eventually felt unhappy and worried when they did not receive the Jom Shopping Vouchers that had been promised, due to technical problems like this. So I would like to ask the Honourable EXCO Member whether we will carry out, improve the quality of this service, or whether we will change any SOP or guidelines to speed up and ensure that this programme can be run smoothly. Thank you.

Puan Dr. Siti Mariah binti MahmudAMANAH · PHSeri SerdangEN

Thank you, Honourable Bandar Utama. Actually, we have discussed the mechanism a lot and we have only just started. I think this month will be the second month, the second time we are implementing this Jom Shopping. Indeed, the first time there were many, and indeed all the Service Centres could not contact them because the phone numbers they used had expired. So we are now asking the senior citizens or their heirs to update, with permission, update their phone numbers, updating their phone numbers, and this can help us, not only once they have updated, the PKM can contact them but YAWAS can also blast about this matter. We are trying to fix this later because we have only just begun, Honourable Member, this is only the second time, so we need further feedback, and we will continue to study it, and I am ready to receive the feedback of all Honourable Members so that we can improve the implementation of this Golden Age Friendly Scheme.

Soalan Tambahan.

Speaker

Kuang.

Tuan Sallehudin bin AmiruddinBERSATU · PHKuangEN

The SMUE was originally quite strongly opposed by many people, or by the public as a whole, when we changed this programme, but since it began we have seen one positive thing, very positive, because for those who are over 60 years old, when they receive a contribution of RM100 for Jom Shopping, this enjoyment is clearly visible, meeting friends at the Shopping Complex and so on, but the burden has fallen on the State Assembly and our offices, because every month we have to attend to the demands and carry out those tasks. Does the Honourable EXCO have another method, perhaps? My proposal is that we implement it every 3 months. Every 3 months we hold one SMUE and gather the recipients over a 3-month period, so that in a year we have 4 times. That is the proposal, thank you.

Puan Dr. Siti Mariah binti MahmudAMANAH · PHSeri SerdangEN

Honourable Member, if we do it every 3 months it means each time there will be more people, but if we plan how we are going to do it, and I do recommend that it is now being studied, the date should not be just on one day but perhaps throughout the month. But there is a slight technical problem in management, because after each shopping session the UPEN officer has to close the account because payment has to be made to the shop or supermarket. So I accept this proposal, we will study it in our discussions later, and I would just like to say that in running this programme, the Honourable Member mentioned staffing, how the process is handled by staff and so on. I think if we plan at the start, we may need perhaps 10 people to help us, and indeed there is provision in the implementation of the programme, and we can give a small allowance to our volunteers to help us carry it out. If we do not do this, Honourable Member, we actually have a good opportunity to meet senior citizens. They actually give very good feedback because they can socialise, and I hope we can be patient a little longer so that we can see its effectiveness.

Tuan Harumaini bin Haji OmarBERSATU · PHBatang Kali

Yang Berhormat.

Speaker

Ijok.

Thank you, Honourable Mr Speaker. In terms of managing and operating this new programme, I think all the service centres have problems because we have to use more staff, and this uses up costs and also the way to make it effective. Ijok would like to ask whether the Selangor State Government has a proposal to return to the old scheme but reduce the amount we give from RM2,500.00 to RM1,000.00 or RMRM1,500.00, because in terms of political mileage I think the old way is better than the current way, that's all.

Puan Dr. Siti Mariah binti MahmudAMANAH · PHSeri SerdangEN

Honourable Ijok, we have only just begun the alignment, so we cannot, within a period of less than a few months, return to the old programme. Moreover, I have already stated before that if we do it this way, it is indeed the senior citizens who benefit. Although we see RM100 as something we may feel is a little, for senior citizens who do not have cash in hand, they really appreciate it. And if we talk about political mileage, I think with senior citizens the political mileage is also higher, because in the coming years the number of senior citizens will increase and they will also become voters. However, we will consider what has been proposed, but I think if we want to change within a few months, we have only just started, so not any more, Honourable Member, I am speaking frankly, that is really the case.

Speaker

Rawang.

Tuan Chua Wei KiatPKR · PHRawangEN

Thank you, Mr Speaker, my question is question 129.

Oral Questions — 129. Water Supply PollutionQuestions

Tuan Chua Wei KiatPKR · PHRawangEN

129. To ask the Y.A.B. Dato' Menteri Besar:-

a)

State the causes and areas where water pollution has occurred that has affected the water supply since 2008.

b)

What steps has the government taken to ensure that water supply disruptions caused by pollution of raw water sources can be reduced?

Tuan Hee Loy SianPKR · PHKajangEN

Thank you, Honourable Rawang, who asked about the issue of water pollution and also the steps taken by the State Government. Mr Speaker, from 2008 to 2019, raw water pollution incidents have caused Water Treatment Plants in Selangor to be forced to stop operations 744 times, and this has affected the supply of treated water to consumers. The causes of water pollution are due to the following matters. First, oil and diesel spills, 35 cases; second, discharge of influent from factories in industrial areas and also sewage plants entering raw water sources, 51 cases; third, the presence of high levels of ammonia and also manga, that is manganese, in raw water, 19 cases; fourth, increased turbidity of raw water during heavy rain due to uncontrolled earthworks, which is the largest number, 599 cases; and fifth, other causes of pollution such as floating materials and high pH, 44 cases. The areas where pollution occurred are the upstream areas of rivers and raw water sources before the plant's intake, namely Sungai Selangor, Sungai Langat, Sungai Semenyih, Sungai Selisik, Ampang Intake, Sungai Bernam and Sungai Gombak. It is the responsibility of the State Government to ensure that water sources in Selangor are always clean and safe for use, and various efforts have been taken to balance rapid development with the protection of water resources. Regular monitoring has been carried out by the Board together with relevant agencies to ensure that water sources and their catchment areas are protected in terms of quality and quantity. Integrated enforcement and firm legal action are also continuously carried out, including investigation, notices, reduction of compounds, including prosecution in court. In addition, continuous monitoring and enforcement work on other pollution issues is carried out through committees that have been established by, first, the River Basin Management Committee chaired by the Honourable EXCO for Infrastructure and Public Needs; second, the River Basin Task Force for the Klang River Basin, Langat River Basin, Selangor River Basin chaired by the Director of the Selangor Water Management Authority, namely LUAS; third, the Selangor State Water Source Pollution Emergency Committee chaired by the EXCO for Environment, namely myself, thank you.

SpeakerEN

Kuala Kubu Baru is not present. Morib.

Tuan Hasnul bin BaharuddinAMANAH · PHMoribEN

Thank you, Mr Speaker, my question is number 131.

Oral Questions — 131. Upgrading and Widening of Main RoadsQuestions

Tuan Hasnul bin BaharuddinAMANAH · PHMoribEN

131. To ask the Y.A.B. Dato' Menteri Besar:-

a)

Does the State Government plan to upgrade and widen the main road to Pantai Kelanang, which is one of the main tourism recreation centres in Kuala Langat, in this year's budget?

b)

The sub-question has been rejected.

Tuan Ir. Izham bin HashimAMANAH · PHPandan IndahEN

Thank you, the Honourable Morib. Mr Speaker, Morib would like to ask about the State Government's plan to upgrade and widen the main road to Pantai Kelanang, which is one of the main tourist recreation centres in Kuala Langat. For the information of the Honourable Member, the State Office or State Government currently has no plan to upgrade and widen the main road to Pantai Kelanang, namely the road to the jetty and Jalan Cakerawala. However, we will propose that a study be carried out first. A study first on the need for the application to upgrade the main road to Pantai Kelanang so that it can become one of the main tourist recreation centres in Kuala Langat. So we will include it in the plan. Thank you.

Speaker

Ya Morib.

Tuan Hasnul bin BaharuddinAMANAH · PHMoribEN

Mr Speaker, a supplementary question. There are several access roads to Pantai Kelanang, but the main one passes through a village area, so we hope the Public Works Department (JKR) can look into widening these roads to ensure the safety of users, whether the villagers themselves or members of the public. Thank you.

Tuan Ir. Izham bin HashimAMANAH · PHPandan IndahEN

Thank you, the Honourable Member. I have in fact travelled this road several times and it is indeed narrow. I admit there is a need, and we will ask the Public Works Department (JKR) to carry out a study and give it priority, and it will also be given attention for implementation in the near future. Thank you.

SpeakerEN

Thank you, the Honourable EXCO for Pandan Indah. Honourable Members, the time now shows 11.30 a.m., and I therefore adjourn the Question Time session for the next business. Before the next business, for the information of Honourable Members, this morning the Selangor State Legislative Assembly (DUN) received a visit from 131 students of Sekolah Agama Menengah Bestari Subang Jaya (SAMBESJ), led by their accompanying teacher, Puan Noraziah binti Arshad. Welcome to the Selangor State Legislative Assembly. Secretary, please proceed.

Continuation of Motion No. 20/2019 - Motion on Development Formation 2020Motion

Secretary of the HouseEN

Next Order of the Meeting, continuation of motion number 20/2019 - Motion on the Development Formation 2020.

SpeakerEN

Yes, I invite the continuation from Hulu Kelang.

Tuan Haji Saari bin SungibAMANAH · PHHulu KelangEN

Thank you, the Honourable Member. Mr Speaker, Honourable Members, yesterday I touched on page 158, PK 17, Supply 011701, relating to Kem Tun Ghafar Baba. Kem Tun Ghafar Baba has existed since the 1980s as an open training site for youths, which the government operated. But now I understand it is under the EXCO for Education, and under education it has been well repaired. With what I stated yesterday, it has existed in Hulu Klang and has been allocated a large amount to rehabilitate the facilities. A place used for training at national standard, Selangor standard. I expect that if it is synergised. To combine and link synergy means 1+2=3. 1+2=2. Synergy means (with permission) making that strength grow larger, it makes that strength benefit all the people of the State of Selangor. And I stated yesterday, Kampung Kamensah with world-class activities such as X-tv, there are more than 100 units with 4 operators running there. Then rugged activities, forest activities, waterfall activities, activities that can lead to good adventure. There, I also want to state that there is the National Zoo. The National Zoo is a national attraction, this needs consensus. Consensus between the State Government and the Federal Government. Between the Minister of Tourism and the minister, the EXCO for Tourism with Selangor. If this synergy can be strengthened, we build a lot of strength because there are many high-quality places there, and so we hope it will become an attraction not only at the Selangor level but also at the world level.

Mr Speaker, I would like to explain here that the development we want to carry out, which is approved through the Bill, through the motion and the Supply Bill, makes the State of Selangor a developed state. Cost efficient and effective. With little expenditure we manage the revenue well. (Arabic) several times we repeat as said before. Here I want to remind that this development has indeed been commanded by His Majesty the Sultan of Selangor, separate from Maqasid Syariah. All development carried out in Selangor must be based on and guided by Maqasid Syariah. Maqasid Syariah

in English can be said to be management by objective (with permission), that is the thinking of Peter Drucker, or if we want to use Stephen R. Covey, in having the end in mind. So this is a very good approach if all our civil servants follow this method, it has an approach with management or objective, in having the end in mind, a goal set at the end of achievement, not started today. What I want to explain here is, what do we want? What we want is wealth, prosperity, well-being, blessing, happiness and so on. In my view, all development that is achieved is to produce a well-being generation, balance, which is said not to be a trigger of problems but on the contrary. Part of problem solving (with permission). So how is this to be done? I propose that in our Maqasid Syariah model, with the end we achieve this, rahmatan lilalamin. Rahmatan lilalamin means a mercy to all the worlds. A mercy to all the worlds, without religion, without race, without ethnicity, everyone obtains happiness as a result of social concern and the government making it into a good project. Thus I want to emphasise here that, there are 5 steps by which we can develop the movement of our state development by achieving maqasid syariah and achieving rahmatan lilalamin. Ensuring we do not start any problem, trigger any problem and leave problems be. Second, helping every person to help other people to solve problems. Third, helping meet the needs of life, the conditions of life, the conditions of a government's administration. Fourth, improving the quality of services until achieving well-being (tahsin) perfection. Fifth, we become a mercy to all the worlds. We humans become a mercy to all the worlds are those who are not arrogant, kulu'an kabiro, and not proud, greedy, but sincere humans without racism and religious bias. That is all, I have conveyed. Thank you.

SpeakerEN

Thank you, the Honourable Hulu Kelang. I invite the Honourable Sungai Kandis.

Tuan Mohd Zawawi bin Ahmad MughniPKR · PHSungai KandisEN

Assalamualaikum Warahmatullahi Wabarakatuh and good morning. Thank you, Honourable Chairman, for giving Sungai Kandis the opportunity to also take part in debating the Supply Budget 2020. Page 98. PK 1414010 – International Book Translation Programme. I want to strengthen and also continue my debate during the Management Supply on this Book Translation Programme, which I see as an International Book Translation Programme that has succeeded in transforming a government into a great government in the era of the Abbasid Caliphate and the Andalusian Caliphate. This programme has transferred technology (with permission), transferred knowledge. So now we need knowledge and also findings from abroad to make the development of the State of Selangor balanced. What was mentioned in the budget the other day, al-umran, is a term of Ibn Khaldun which I think needs to be given attention, but when Ibn Khaldun produced the book Al Muqaddimah, how many among the people of the State of Selangor, let alone its leaders, have read the book Al Muqaddimah? Therefore, translating these great international works needs to be strengthened and expanded from thoughts that invite open thinking, thinking that is more merciful in nature. Like the thinking of Sheikh Raissouni, Sheikh Abdullah bin Bayyah, Sheikh Al Qaradawi, who invite society to be open

to views, especially in jurisprudence (fekah). We see today the tendency of society towards radical, extreme and takfiri thinking, easily labelling other people as apostates (kufur), even though this matter is ijtihadi, an opinion of the leaders. Therefore, with the large number of publications of these translated books, they can be channelled to leaders, especially the members of the House. Yes. Thank you.

Tuan Ronnie Liu Tian KhiewDAP · PHSungai PelekEN

Thank you, Mr Speaker,

What is Sungai Kandis's view that leaders from the government and also from the opposition invite all the people to focus on open thinking and new knowledge, modern technology and also economic activities so that we no longer focus on the issues of race and religion. What is the view?

Tuan Mohd Zawawi bin Ahmad MughniPKR · PHSungai KandisEN

Thank you, Sungai Pelek, who raised this issue, because I agree with the view of Sungai Pelek, who invites the community in the State of Selangor to focus on the development of the State of Selangor and no longer to raise views that are racist, hatred towards races, hatred towards religion, because of the experiences undergone by other countries, to the point of war breaking out between the people of the community themselves. I want to share the experience of my friend in Yugoslavia when I studied before. There were students from a country named Yugoslavia, there were three ethnic groups, namely Bosnia, Serbia and Qudsia. They had different cultures, different religions and beliefs. What happened is that this conflict eventually led to war, and Yugoslavia was wiped off the map of the world. And this is! The high price that had to be paid by society as a result of the stigma of hatred between races, hatred between religions that could not be contained. Therefore, my proposal is that these books be widely disseminated to leaders, Members of the House, at the level of civil servants, at the grassroots level of MPKK and mosque supervisors (nazir), so that they can appreciate them, and further, my proposal is that the publication of these books not merely be placed on bookshelves but be discussed, made into seminars, and there be book exposure programmes so that the contents of these books can be spread at the grassroots level.

And further, I see under PK 003 page 187, I noticed an allocation of RM450 000.00, interesting, this is for building village development. Last year Sungai Kandis applied to the Selangor State Library to build a library in the Sungai Kandis DUN area. And I am very sure, I think this budget is indeed for Sungai Kandis, because (laughter) because we have prayed and hoped very much that this library will be built quickly.

HOUSE: Even a prayer for need (solat hajat) was performed.

Tuan Mohd Zawawi bin Ahmad MughniPKR · PHSungai KandisEN

Because the population in our area is very dense and they need reading materials and a place for young people to spend their time in a conducive environment. Yes. Thank you, Templer.

Next, relating to infrastructure. I have listened to friends from many areas who complain about infrastructure. So this country is rapidly developing, so we understand the need to upgrade and add infrastructure in our country, and Sungai Kandis is not left behind. However, I refer to the projects implemented on

PK 404003 page 221 – Upgrading Jalan Kampung Lombong amounting to RM600 000.000. 0404402 - Upgrading Jalan Klang from the Junction of Route FT 003 Kampung Jenjarom to Jalan Kebun amounting to RM200 000.00 and also PK 1 page 229, item 01304 Flood Mitigation Project at Sungai Aur amounting to RM5 million. What Sungai Kandis wants to raise is the coordination of development work, because these two projects, these three projects, face the problem of relocating utilities. Beneath it there are gas pipelines, there are telecommunication lines, there are water pipes. So, does the Government not have a mechanism, a committee that can coordinate this development? To the extent that the State Government had to incur additional expenditure of RM500 thousand, RM600 thousand, only for purposes that should not have happened if the utility relocation works had been carried out at the early stage. And what happened is that residents of the affected areas had to face difficulties because of the extension of time, delayed by up to a year while waiting for budget approval and so on. So, what happened here, there should be a mechanism that can coordinate the implementation of this.

Sungai Kandis thanks for the projects that have been implemented in the Sungai Kandis DUN, and I think next year, God willing, the Sungai Kandis DUN will submit development programmes, and this year we only got. We got nothing. (Laughter) So if we did not get anything, at least one library is fine. And I also want to touch on PK13, this is not related to the Sungai Kandis DUN but is related to the museum. As much as RM1 million. We see that the Selangor State Museum has been closed for a long time, perhaps some people have not even noticed. Perhaps because this museum is not an interesting one, as it contains only inanimate objects, old things, but it is there that our future generations can learn their national identity, get to know the glorious history of the State of Selangor, get to know the history of the Selangor Sultanate. But when this museum is closed, students and tourists cannot get to know the State of Selangor, the greatness of the State of Selangor, and I believe that with this RM1 million budget, the opening of the Selangor State Museum can be expedited. And also other museums, because we see other countries, developed countries. They take such great care of these museums because it is there they preserve their national heritage, keep things that can restore the spirit of development of the sons and daughters of the state. This is because we do not want to see that in future, the generation we leave behind will not know who has contributed to developing this State of Selangor. There was a time when young generations like me did not even know who the ADUN was, who their People's Representative was. Let alone know the EXCO members of the State Government. So awareness of the government and civilisation of the State of Selangor must be recorded and made into an education programme for our children in school, so that they can make the State of Selangor even more outstanding 10 years from now. That is all as the debate of Sungai Kandis and in support of the budget that has been tabled. Thank you.

Deputy SpeakerEN

Thank you, Sungai Kandis. I invite Taman Templer.

Tuan Mohd Sany bin HamzanAMANAH · PHTaman TemplerEN

Assalamualaikum wbt, salam sejahtera. Thank you to the Deputy Speaker for allowing me to raise issues relating to the matter in Taman Templer. I would like to raise matters relating to PK7, page 196, which is the upgrading of sports infrastructure. In the previous sitting, I raised matters relating to upgrading facilities, especially the football field in Kampung Melayu Rawang, Batu 16. For the information of the State Government, the upgrading project has not yet taken place. So we hope the State Government will be serious about looking into upgrading the football field in Kampung Melayu Rawang, Batu 16. Next, PK9, project code 09002, Local Authority Public Facilities. Here I also want to convey the wishes and request of the community, especially residents of Bandar Baru Selayang, who want a hall where they can hold programmes and activities, especially for the young. I hope for a hall. If it could become a reality or a statement of intent. A hall that can accommodate 4 badminton courts inside, apart from this hall, which can later be used by the community to hold feasts, celebrations and so on.

Likewise, with project code 09003, matters relating to transportation. I also want to convey the wishes of the residents and the community in the Templer State Constituency, namely that they want the commuter line to be extended, because we know that for the Gombak District this commuter line stops only at Batu Caves. We hope the State Government can discuss with the Federal Government, especially the Ministry of Transport, so that this commuter line can be extended to Bandar Baru Selayang, to ease the travel of the community and residents there who commute to work in Kuala Lumpur.

Likewise, I would like to raise, on page 199, project code 16019, Water Pipe Replacement Project. I have also raised this matter in previous sittings, relating to the pipes that often burst, especially in Kampung Selayang Baru. Today it bursts, today it is repaired, and it bursts again. We do not know what materials they use to repair the pipes. That is the first point. The second point is that after the tar road patching is completed, sometimes it becomes very bumpy, and sometimes it sinks. This too must be looked into by the State Government regarding the repair of burst pipes. Likewise, regarding the problem of frequent floods in Selayang Baru, especially on Jalan 60, we know that the State Government has allocated as much as RM5 million to upgrade a tributary of Sungai Udang. The allocation of 5 million ringgit to upgrade the tributary of Sungai Udang for the first phase has been completed, but the problem is the second phase. This second phase has stalled due to land acquisition. So I very much hope that the State Government can look into the land acquisition process, because it can solve the problem of flash floods that frequently occur in Selayang Baru. I would also like to express my many thanks to the Honourable EXCO member from Pandan Indah, who went down to Taman Templer to inspect the progress of projects in Taman Templer. Next, I want to raise the matter of the road upgrading project from Selayang to Rawang, especially at the hill slope at Taman Aman Sierra. Because there, not only during peak hours, even outside peak hours, traffic congestion often occurs. Therefore we hope the State Government can quickly approve the allocation to upgrade the road from Selayang to Rawang from 2 lanes to 4 lanes. Likewise, there is the matter of lighting, namely the lamps that should be installed along the road from Selayang to Rawang itself.

Next, the matter of the influx of foreign workers, especially at Pasar Borong Selayang. We know Pasar Borong Selayang, the name is only Pasar Borong Selayang, but the geographical location of Pasar Borong Selayang is actually within the Federal Territory of Kuala Lumpur, and we hope for cooperation from the State Government to discuss, perhaps with Kuala Lumpur City Hall (DBKL), with the Ministry of Federal Territories, with Immigration, with the Police, in order to overcome the problem of the excessive influx of foreign workers, especially in the area of Pasar Borong Selayang itself.

Finally, the matter of building a new mosque. If we look at the presentation of the budget, the government's budget was previously called "bajet", and "bajet" is a word from the white man's language, but thank God the Pakatan Harapan Government has changed it back to "Belanjawan". Previously it was called "bajet" for the information of Jeram. But now the Pakatan Harapan Government has upheld the Malay language itself. The Belanjawan, as presented by the Honourable Dato' Menteri Besar, states that next year two mosques will be built. One in Sungai Buloh and the second in Kuang. I hope for assistance from the State Government to help with the matter of building a mosque in Kampung Selayang Pandang in the Taman Templer State Constituency. And finally, I would like to record my immeasurable and infinite thanks to the Most Honourable Dato' Menteri Besar for kindly making time to visit the victims of the storm that occurred in July last year in Taman Templer. Thank you, Mr Deputy Speaker.

Deputy SpeakerEN

Thank you, Templer. I invite Bandar Utama.

Puan Jamaliah binti JamaluddinDAP · PHBandar UtamaEN

Thank you, Madam Deputy Speaker, for giving Bandar Utama the opportunity to debate the motion on the 2019 development allocation. Here Bandar Utama only wishes to raise 2 matters. The first matter: Vote PO1, page 196, project code PK7 07001 under the Young Generation Development Programme. Bandar Utama is moved to debate the allocation given to PeBT, because in this sitting we can also see that many ADUNs or Honourable Members have given views on PeBT, and their main focus is the effectiveness of PeBT under the State Government of Selangor. So I have heard many voices from the Honourable Members, and Bandar Utama also wishes to give Bandar Utama's views, because I feel PeBT is not all problems. In the Bandar Utama area, we are actually very satisfied with the performance of PeBT, because PeBT is actually a very good programme in Bandar Utama for leading and empowering young people under the State Government of Selangor. First of all, I feel PeBT is something the State Government of Selangor should be proud of, because only in the State of Selangor do we have the special Local Youth Mover (Penggerak Belia Tempatan) to train our young people. This programme is very envied in other states because they do not have a programme like this. And I feel that when some of the Honourable Members raise the issue of the effectiveness of PeBT, sometimes I feel that all of us, the Honourable Members, also have a responsibility towards PeBT, because whatever type of programme or activity to be carried out by PeBT requires the approval and signature of the ADUN. So I feel that if there is an ADUN who does not agree with the programme or activity carried out by PeBT, the ADUN can actually choose not to sign or can discuss with the PeBT first. So let us not discredit this PeBT, because this PeBT, as said by the Menteri Besar, has helped us a great deal to shape young people to become leaders, some of whom have become Councillors, and some have become State Assemblymen. However, I agree that we need improvements to this PeBT because...

Tuan Mohd Najwan bin HalimiPKR · PHKota AnggerikEN

Bandar Utama, may I interject briefly?

Puan Jamaliah binti JamaluddinDAP · PHBandar Utama

Dipersilakan.

Deputy SpeakerEN

Kota Anggerik, you are invited to speak.

Tuan Mohd Najwan bin HalimiPKR · PHKota AnggerikEN

Thank you, my colleague Bandar Utama, for the opportunity. I just want to share a question with Bandar Utama. First, I agree with his view on the importance of PeBT as a pillar for the effectiveness of youth development programmes in the State of Selangor. I want to ask Bandar Utama's view. Does Bandar Utama agree, because as it is now there is an age limit. Previously we used the youth age limit of 35 years, but I see that in Selangor, PeBT was implemented earlier than the Federal Government. As it is now, at the Federal level they still use an age limit of 30 years, whereas at the State of Selangor level it was implemented much earlier. This means that now, if someone in PeBT is over 30 years old, they are no longer eligible to be appointed as PeBT. What is the Honourable Member's view, whether there should be a follow-up programme for former PeBTs, or as people call them, ex-PeBTs? What is the next step? (with permission). What are their plans after this, because what I see is that after completing their service period with PeBT, most of them have no direction, so there is nothing, they do not know what to do, something like that. Does the Honourable Member agree that we propose to the State Government that it utilise the skills and talents of these former PeBTs so that they can contribute and provide the appropriate service and role to the State Government even though they no longer hold a position? Thank you.

Deputy SpeakerEN

Bandar Utama, please.

Puan Jamaliah binti JamaluddinDAP · PHBandar UtamaEN

Thank you, Honourable Member, for the good question. I feel the main objective of the Local Youth Mover (Penggerak Belia Tempatan, PeBT) is for us to empower our young people, that is the main goal, and if I am not mistaken, recently some people have raised the issue that PeBT has political intent, where PeBT is only a position given for political purposes. I strongly disagree with that statement, because PeBT is proven to be a programme, for us, to educate young people to become leaders, and as the Honourable Member said just now, not everyone who has gone through the PeBT programme is given a position or appointment. Some become Councillors, some become ADUNs, but there are also those who do not have any position or are not given any position in the Government, and this means it is not political intent, because if it were political intent, it would mean all PeBT members would receive positions afterwards. So I feel we have not deviated from the main objective, in which we actually want to train young people, not to give positions after training these young

people. The main objective is to ensure that these young people have leadership capacity, so that under the State Government of Selangor we have more young people who can step forward and lead. That is the main objective, not the giving of positions.

Mohon laluan.

Deputy SpeakerEN

Kuang wishes to interject. Please, Kuang.

Tuan Sallehudin bin AmiruddinBERSATU · PHKuangEN

Thank you, Bandar Utama. I want to ask about the effectiveness of this Local Youth Mover (PeBT). If we look at the budget provided, it is not very large, but I believe that PeBT was originally created for the needs of the State of Selangor only. My understanding is that it was to mobilise youth in the State of Selangor, but today we have governed up to the Central Government. Is there a proposal for this PeBT engagement to be expanded further, at various levels, including other local youth who become movers, for example like Belia 4B, or they could deal directly with the Ministry of Youth and Sports under the new Minister? If we do not expand PeBT, we see its scope is quite small, quite small, quite small, and with that small allocation I believe it is unable to move things forward better. I ask that this engagement be made larger, going directly to the central level. Thank you.

Deputy SpeakerEN

Bandar Utama, please. Be brief.

Puan Jamaliah binti JamaluddinDAP · PHBandar UtamaEN

Okay, I will be brief. On that matter, I feel the Honourable Member can discuss it with the Honourable EXCO member later, after we leave the meeting. But what I want to say is that we can make improvements to PeBT to raise the performance, quality and productivity of PeBT, but we cannot discredit PeBT, which is a very good mechanism; it is only a question of how we use PeBT to train our young people. So Bandar Utama also wishes to state that Bandar Utama also hopes the Honourable EXCO member will later advise PeBT to cooperate with the ADUNs, because the ADUN is a Representative of the People who has been elected by the people. So if there are PeBTs who truly do not perform or do not carry out their duties, I feel the Representatives of the People and ADUNs should be given space to provide feedback and suggestions on PeBT. Here I will digress slightly, although the topic is not related to PeBT, but it concerns the impact or effect of PeBT, where if PeBT is, because the PeBT number is based on the number of Councillors under the Local Government, and I can see there are difficulties if PeBT is under many different ADUNs. The different Honourable Members, because perhaps they only cooperate with one ADUN and do not cooperate with all ADUNs. So that is an issue that the Honourable EXCO member may consider later, because if PeBT works only with certain ADUNs and does not meet with the ADUN who is also under the same place or area handled by that PeBT. This means that the ADUN cannot train that PeBT or cannot cooperate to run programmes. So I hope the Honourable EXCO member will consider that, and I also feel that we should actually carry out redelineation to ensure that the Local Government is aligned with the redelineation of the State Government. I can see my time is not very much, so I will stop there. Finally, I want to thank you for allowing Bandar Utama to voice opinions, and I support the motion with this allocation.

Deputy SpeakerEN

Thank you, Bandar Utama. I invite Sentosa.

Tuan Gunarajah A/L R GeorgePKR · PHSentosaEN

Thank you, Madam Deputy Speaker. I would like to draw attention to code 181010, page 200, the Free Water Supply Programme. Sentosa would like to ask whether Air Selangor has any plans, through a CSR programme, that could help, because there are many low-cost apartments, right? We here are trying to spend a sum of money to provide free water, but water is being wasted in low-cost apartment areas because they do not have an active JMB that can help solve the problem of many leaking water pipes in the inner areas. But who can help? So if possible, Air Selangor's CSR programme could help them resolve this matter, and the water used in certain apartments and flats could be billed. So, a CSR programme is very necessary, and with an approved allocation, perhaps Air Selangor can help. Second, can the State Government or Air Selangor provide free water to hostels, orphanages and perhaps homes for the elderly, where many NGOs running these centres face problems with paying bills and so on. Second, Honourable Madam Deputy Speaker, concerning code 18009, page 200, the Golden Age Friendly Scheme Programme. Earlier, in the explanation given by the EXCO, the Honourable Member said that a programme had indeed been run and introduced, and that it may take time for us to know whether this programme will succeed or not. But I only want to ask about the programme at the Sentosa State Assembly office, where many more people still come to register because they too need RM100 and so on in conjunction with birthdays. But my question concerns last year, when we approved a budget for the Golden Age Friendly Scheme. Why was this programme stopped in April this year? Was the money exhausted against the budget, or was the money insufficient, or not? That is the question I want to ask. And in the Golden Age Friendly Scheme form, it must be stated that the State Government has the right to change, amend or stop a programme, and must give notice. Perhaps the SMUE is a death-benefit (khairat kematian) programme and not a Golden Age Friendly programme, so it should be given a sufficient period, namely one year, before any such programme is stopped. This is a question: perhaps the State Government has certain problems that could be explained.

Third, concerning Code PK13, Education on Customs, Language, Arts, Culture and Heritage. Does the State Government have any intention, plan, or has it considered building an Indian Cultural Centre? In 2012, the former Menteri Besar announced that a Cultural Centre would be built along the Klang River, and I do not know whether an allocation was set aside or not. But does the State Government intend to build a Cultural Centre specifically for the Malay, Chinese and Indian communities, which could help and preserve, develop customs, culture and language so that they can continue, and so on. The construction of a Cultural Centre is important so that our customs and culture remain, while continuing to grow and develop in step with the progress of the Nation. That is my third question or clarification.

The fourth, and perhaps the last, concerns PK9, page 196, code 90005, Local Government. Where we allocate many programmes for the Safe City Programme, CCTV and so on. Our main CCTV is the Royal Malaysia Police (PDRM), and we need the assistance of PDRM. I want to ask whether we can help PDRM, because we know that the previous Federal Government did not give full attention to facilities and so on. There are many shortcomings in DUN Sentosa too; we need a police station, but the existing police station is outdated and needs renovation, so the police who are to be on duty do not have a comfortable place, right? Could the State Government help the stations that need renovation for the comfort of our PDRM personnel in the State of Selangor?

Finally, the Environmental Programme, Code 12003. Programme: we indeed spend a lot to hold Environmental Awareness Programmes and to raise awareness from school benches and so on. Does the State Government have any plan to buy back plastic bottles that usually end up in the sea? If we could give value to plastic bottles, like 'scrap metal', with permission, these plastic bottles could be collected by a group, which could be a business we can set up for several people to earn a side income, where these bottles could be collected from where they are thrown into drains and end up in the sea, and so on. We might be able to hold a JV programme with big plastic manufacturers in the State of Selangor. Sentosa seeks clarification, and I would like to thank Deputy Speaker for giving me the opportunity. Thank you.

Deputy SpeakerEN

Thank you, Sentosa. I invite Sungai Panjang.

Tuan Mohd Shaid bin RosliBERSATU · PHJeramEN

Ever since I criticised this woman, I have not been given any chance at all. This is discrimination, isn't it?

Dato’ Mohd Imran bin TamrinUMNO · BNSungai PanjangEN

Bismillahirrahmanirrahim, Assalamualaikum warahmatullahi wabarakatuh, and also Salam Sejahtera. Thank you, Honourable Deputy Speaker. I hope the Honourable Member for Jeram is patient. I will not take long; there are just a few matters I wish to raise in the debate on development expenditure. The first is Vote P01, the Office of the Menteri Besar and State Secretary, and I would like to refer to PK4, which is social matters. In the policy speech of the Right Honourable Menteri Besar when tabling the 2020 Budget, there was mention of a programme to be free from social ills, particularly the drug problem. As we are well aware, this drug social problem has two main matters that need to be focused on. The first is enforcement. How do we curb drug peddlers so that action can be taken that is very firm and also appropriate? And in the Sabak Bernam district, first of all I wish to extend congratulations to the Sabak Bernam District Police Headquarters (IPD), which has so far frequently carried out operations related to eradicating this drug problem. But when we look at social problems, especially, we need to look at those who are caught up in the drug [trap], in terms of these addicts, so that they receive support from society and also from the community, even though the allocation set out in the policy speech is RM1 million. I feel this is not sufficient and needs to be increased with other programmes so that they do not return to becoming drug addicts. And I also feel this is suitable for the policy that I believe is being, or is in the process of being, introduced at the federal level, in which, with permission, the government wishes to 'decriminalise' or not make the problem of drug addiction a criminal offence, [i.e.] decriminalising addiction. So we at the state level must make a programme or provide support for these people. And those who are charged in court and so on are not all placed in a rehabilitation centre (pusat serenti). And there are also those who are granted bail and so on for a period of two, three or four years; these people are in society and they must be given attention and also support from a social aspect, perhaps through cooperation with MPKK or the local authorities (PeBT) themselves, involving young people and the young who are caught up in this, so that they can recover and return to contribute to society again. This is very important, and we also want to know what the State Government's position is regarding the policy perhaps being discussed at the federal level on decriminalising these drug offences, with permission, so that at the state level these people are given support, and it will also not burden the prisons or the Prisons Department with a flood of those subjected to imprisonment for these drug offences. This causes prisons to become increasingly 'packed', and they are forced to languish in prison.

And the second matter concerns social and security issues in the State of Selangor. As we are aware, today the problem of scammers or fraud is getting worse. These scammers. Alright. In terms of what name is this? Fraud through Facebook, WhatsApp and so on, it is getting worse. And, just as with the drug problem, there is also a problem of money mule scammers among these scammers. Most of these money mule scammers are among those who may have low knowledge and may also have less education, and many of the victims are aunties (makcik-makcik) who are widely deceived, to the extent that their accounts are used by scammers to deceive others. They are given accounts on the pretext that they are promised returns and so on, and in the end they hand over not only their account books but also their ATM cards to the scammers. And eventually these accounts are used as accounts to deceive other people. And ultimately those who are brought before the courts are these money mule scammers, involving many people in villages, especially in the Sabak Bernam district itself, where there has also been an increase in these matters.

And this needs attention. If we refer to PK4, for example, 04005, consumer affairs, there is a small budget allocated so that the government can consider an awareness programme so that these people, or the people out there, do not get caught up in this problem, which will ultimately burden them. And there are also those scammers who are charged in courts today, and this causes many problems. Second, if we look at scammers, we cannot avoid the issue of personal data and also the digital economy now, because there is far too much and it is easy to obtain this data, phone numbers and so on. And if I am not mistaken, this year, perhaps in the middle of the year, there were also scammers who impersonated the Menteri Besar himself, phoned the District Officer, and if I am not mistaken, impersonated the Menteri Besar, and the number that appeared was the Menteri Besar's number. And this is something dangerous, and from a security aspect this must be taken into account.

Tuan Sallehudin bin AmiruddinBERSATU · PHKuangEN

Does Sungai Panjang agree that the Love Scammer is part of the scam that is currently spreading in our online media? Is it caused by that?

Dato’ Mohd Imran bin TamrinUMNO · BNSungai PanjangEN

Thank you, Honourable Kuang. When we talk about these scammers, there are various methods or strategies that scammers use, apart from demanding money and so on. The Love Scammer is one of them. They have their targets. Perhaps their target is single mothers who are not among those in need of assistance, but single mothers and so on who may become targets or certain individuals. The Love Scammer will attack and obtain money and so on from them. So the government needs to give attention to this, and awareness programmes and so on need to be considered to ensure that the social life of the people of the State of Selangor is very stable, especially with regard to online security issues like those that have happened recently. And next, I would also like to touch on PK7, namely youth and sports. There are three items here. The first is youth development, upgrading sports infrastructure and also sports development programmes. Regarding the youth development programme, as we are aware, RM5.260 million is allocated to be channelled through the local authorities (PeBT), and we hope that PeBT youths can reach out to other youths, especially youth associations and so on. If we look at it, the PeBT is divided by state constituencies (DUN); there are 56 DUNs in the State of Selangor. If we take the RM5.260 million allocation, it comes to roughly less than RM100,000 per DUN. So this is very little to help these youths continue developing the younger generation, especially in rural areas. Perhaps if the allocation could be increased. As for upgrading sports infrastructure, if we look, for example, in the Sabak Bernam district. In the past, we had a fitness centre or centre of excellence for boxing. But I see that in the Sabak Bernam area, it is no longer well maintained, and in the end there are no more boxers produced or training there.

And finally, Honourable Deputy Speaker, concerning the 2020 development expenditure estimate, Vote P12, the Selangor State Public Works Department (JKR Negeri Selangor), there are many plans. I refer to Codes 01003 and 01004, namely Installation of Street Lights and Enhancing Safety Aspects. What I want to speak about is the condition of road infrastructure along FR5, especially within the Sabak Bernam district, starting from Sekinchan right up to Sabak Bernam. There are many accidents, and among the factors causing accidents are road safety aspects, lack of lighting, dangerous diversions, and even we ourselves who often use the road are sometimes confused by these diversions, and this can also cause accidents. So we hope that with the allocation, or with several of these matters, they can be improved. And for the information of the House, in front of my house in Sungai Nibong this year alone there have been four or five accidents, and one of them was a fatal accident. Although street lights have been installed, there are still many more hotspots that need attention for better lighting, for example at Simpang Lima in Sungai Limau, in the area

before reaching Pasir Panjang, and so on. There are many bends and so on that need attention, and the barriers are scattered in the middle of the road. And I also want to tell this august House that if the contractor, who I understand is Mangkubumi, cannot handle these matters, the government must take firm action, or take whatever appropriate action, so that they must look after the safety of residents so that there are no more accidents or incidents.

So, thank you, Honourable Deputy Speaker, for giving me the opportunity to highlight or bring forward several issues in the expenditure on this occasion.

Deputy SpeakerEN

Thank you, Sungai Panjang. I now invite Jeram.

Tuan Mohd Shaid bin RosliBERSATU · PHJeramEN

Thank you once again.

Deputy SpeakerEN

Five minutes, Jeram. Can you shorten it? Just five minutes.

Tuan Mohd Shaid bin RosliBERSATU · PHJeramEN

Yes. I will keep it short, but there are three main matters that I feel the State Government and the EXCO concerned should pay proper attention to. First, I would like to thank the Selangor State Government for approving a budget for the construction of a mosque, an additional budget of RM1 million under page 248, project code PK3, 03701, namely the Construction of Mosque in Puncak Alam. Thank you. It is really needed, given the very drastic increase in population.

Second, on roads and street lights, page 222, project code PK 04707, Street Lights, only RM500,000 has been given to JKR Kuala Selangor, which covers five DUNs. That means each DUN will get only RM100,000 for the addition of street lights and also road upgrading. If one DUN needs just 10 street lights, and each costs RM10,000, then only 10 poles can be installed for RM100,000 for one year, not counting the road upgrading. So what is this? I have already told you, I have already informed you, that street lights are an important matter and must be separated. Street lights and road works must not be mixed up. I want to tell you that yesterday someone died. Last week he had an accident, and yesterday he died. The State Government can see the records for the Jeram area, which covers several villages, some of which I have also given to Ijok and some to Melawati. It can be said that these villages have on average one fatal accident every week. You can check. I am not speaking without basis; you can check the facts, get the facts. Street lights are important. The person who died yesterday, his house had 19 family members living in one house, on the estate. 19 people living in one house on that estate, most of them children, his grandchildren. And before the festive season, someone else died. His wife died, and their children were very young when I went to pay my respects. The children were only one and a half and three years old. So, I feel I need to stress this issue so that people do not keep saying Selangor is a state that is progressing, a government that defends the people and so on, while basic matters are looked down on when it comes to rural areas. Not important, only the urban areas matter.

I feel very disappointed. So I feel the Honourable EXCO and the State Government should please separate street lights and road upgrading, two different things, at least as I have said. If each year it can allocate ten or even twenty street lights for each DUN, then in at least five years there would be a hundred street lights, and we would see a change from the Barisan Nasional government that ruled for 60 years in that area, and that change would be visible. I beg you very much. When I asked the engineer of the Kuala Selangor District about street lights, where are your street lights, there were none at all. He said there was no budget, no budget. But when you look, it is true. RM500,000 for five DUNs, how is that possible? Come on, we must make that budget, a rational budget must be made, we must take this into account, this is not enough. I certainly support the budget, I do not oppose it. Semenyih supports it, and I support it too. But we must be reasonable. Just five minutes, just a moment, sit down first.

Deputy SpeakerEN

I do not allow it.

Tuan Mohd Shaid bin RosliBERSATU · PHJeramEN

Next, page 219, project code PK0303701, Bukit Hijau to Shah Alam 2 Bypass Road. For this one, I want to tell the Honourable Member that if I want to go to Kampung Bukit Hijau from Puncak Alam, where I live, which is also in the Jeram area, it takes only five minutes. But if I want to take the proper road, right now I take a rat run, which is called a rat run. If I take the proper road, I have to pass through Ijok first before I can get to Bukit Hijau, which takes 45 minutes. So this road has become the main connecting route between the town of Puncak Alam and the residents of the villages, five villages in that area. The villagers keep asking, Honourable Member, why was it that in the Barisan Nasional days this road was always well maintained and could be resurfaced, even though it was a rat run? I said that the rat run was not gazetted, so it could not use the council budget or the JKR budget, because the road is a drainage and irrigation road.

The ADUN allocations can indeed be used, but it is a large amount and not enough. So, Honourable Member, I want to tell you here that in the past, Barisan Nasional representatives controlled the contractors and so on, and if asked to resurface, it was resurfaced. But we do not control anything, and we do not want to do that kind of thing. However, now that there is a proposal for a bypass road, why is it not being managed or continued? That is my question, because I have seen this in the Eleventh Malaysia Plan, which means this has been proposed five years ago. But until now there is nothing yet. Please, I repeat once more. The codes are page 222, project code PK404707, Street Lights, and also page 219, project code PK0303701, Bukit Hijau to Shah Alam 2 Bypass Road. I beg you very much, Honourable EXCO. God willing, next year when I look, I hope to see that there is a budget. That is all, thank you.

Deputy SpeakerEN

Okay, thank you, Jeram. I now invite Sungai Ramal. The younger member after that.

Tuan Mazwan bin JoharAMANAH · PHSungai RamalEN

Alhamdulillah, thank you, Mr Speaker. Time is short, so I will go straight to...

Deputy SpeakerEN

Five minutes, Sungai Ramal. Please proceed.

Tuan Mazwan bin JoharAMANAH · PHSungai RamalEN

Alright, thank you. With permission, I will go straight to the 2020 development expenditure, Vote P01, page 199, subject code PK17, State Special Projects. I would like to refer to the matter of the mosque question, the allocation for mosques. In my constituency there is a mosque under construction, the new Sungai Ramal Dalam mosque. This mosque was built on the promise of an allocation given by the previous Barisan Nasional government, but it was not completed in time. However, the scale of the mosque is very large, based on the scale of the state mosque in Shah Alam, only slightly smaller. And when this project was abandoned, well, it was not abandoned, it is not yet completed, but there is not enough allocation, because the allocation promised by the Barisan Nasional government at that time has not arrived until now from the Federal Government.

The mosque is now about 75 to 80 percent complete. Just imagine the car park of the mosque alone, the car park is under the mosque building, an underground parking that can accommodate about 150 to 200 cars. So, it is a large scale. So if this mosque is left like this without enough allocation, if it is not completed, it will be a large abandoned project in the middle of the village, which can cause big problems for us. It could become a den for drug addicts and so on. So we must, in my view, complete this mosque, and for that, the allocation needed is only about RM4 million more. That is all. The State Government has never given any allocation to this mosque. So imagine, with only RM4 million, the State Government could complete a large, beautiful, magnificent mosque. So for me this is a necessity for us to help.

The mosque committee applied for assistance from the Menteri Besar, the Honourable Menteri Besar, and only received RM20,000. Then the mosque committee and the village head came to meet me to ask for my help, so I also wrote a letter to the Honourable Menteri Besar. With my letter, they received an additional allocation of RM5,000. So just imagine, where am I supposed to put my face? When residents say, we asked, and the MB only gave RM20,000, while the ADUN himself asked and got one quarter of what we asked for. So I hope I am given a second chance in this august House, so that our dignity can be protected and we can get this completed. Because if we do not complete it, this mosque programme is now running in a state where it is being funded little by little, very slowly, collecting donations from the public, bit by bit. If we leave it and do not help, by the end of the year, 2022 perhaps, only a little will remain, and then the other side will come to help, and our image will be badly and severely damaged. So I hope this can be given attention.

Second, I move on to page 233, Vote P13, subject code PK3, River Basin Development. Here I refer to the construction of log booms, which are rubbish traps. In my constituency flows a river called Sungai Air Hitam. Sungai Air Hitam supplies water to a lake, Tasik Cempaka. It sits in the middle of Bandar Baru Bangi and is a pride of the Bangi residents, but the lake is now in a very eyesore condition because of severe pollution there. There is a lot of rubbish, and the rubbish carried by Sungai Air Hitam flows from the neighbouring DUN, the DUN Dengkil. So it is not the people of Bangi who are causing the problem, but people from the other side who are causing the problem.

There is a lot of rubbish, and the existing rubbish traps cannot now cope with or clean up such a large amount of rubbish.

We have, I have introduced to the State Drainage and Irrigation Department (JPS) for the Hulu Langat district, and have also brought this paper to the EXCO to show a new technology, the patented Auto Log Boom, which is more advanced and better than the existing log boom systems, and which can be installed in Sungai Air Hitam to overcome this problem. And what is even better is that this system is a newly patented system, developed using funds from the Ministry of Energy, Science, Technology, Environment and Climate Change. They received a grant of about, if I am not mistaken, RM1 million. So with that grant, the party conducting the research offered to install the Auto Log Boom in Sungai Air Hitam free of charge, without any cost to the state. So I have brought this matter forward and fought for it, but unfortunately this very good offer for me has still not been implemented, even though the EXCO itself has said it is a good idea and strongly supports the efforts I have made. I hope that whatever problems exist, whatever is preventing this from happening, can be looked at again.

Third, regarding page 234, Vote P13, project code PK4. Regarding 04002, Construction of a New GSM Siren Station. This is related to the warning system for when floods occur. I refer to the siren system in Kampung Bangi. In Kampung Bangi, the system exists, and the allocation shows that a system was built, but we often overlook maintenance. So the system there does not work. I have complained about this, but no repairs have yet been carried out. The village areas, village areas in general, lack infrastructure. There are no street lights at night. I have experienced this there. When the water rises from the river, because the river is close to the village, when the water rises at night in darkness, people do not notice, and suddenly the water has risen, causing panic. They want to save themselves by wading through the water in the dark, with drains and so on. So this is something that can very much cause injury, and cause panic among the villagers. Moreover, now that the siren system is broken, so I hope it can be fixed immediately, in a short time. I must stop here. Thank you for this opportunity, and I also support the 2020 development expenditure. Thank you, Mr Speaker.

Deputy SpeakerEN

Thank you, Sungai Ramal, and we end with Rawang. Please, Rawang.

Tuan Chua Wei KiatPKR · PHRawangEN

Thank you, Madam Speaker. Kuang will come later. Two minutes. Okay, here I want to draw attention to page 195, code PK404008, People's Mind Development Programme. We can see in the allocation distributed for next year, there is RM9 million 300 thousand. So, I just want to ask the Government: what programme is meant to be carried out with an allocation of that size?

The second is under Vote P01, page 199, project code PK18004, concerning the Worker Retraining Scheme. The reason for my question is that previously there was an allocation given for this programme under the Peduli Rakyat initiative, but we can see that next year there is no allocation given for this programme.

So, I would like to ask the Government about this, why there is no longer any programme or allocation channelled for this programme.

To summarise further, next is regarding page 220, Vote P12, which concerns JKR. Project code 04200, Gombak District. Here I want to say, earlier, thank you to Taman Templer, who gave an explanation or question regarding the road that climbs the hill from Selayang to Rawang. In fact, there are several infrastructure issues in Rawang that require attention from the government. If people from Kuala Lumpur want to go back to Rawang, they really need to use that road, and complaints at that site are very high, because there are broken-down lorries, and on the hill there are many vehicles moving slowly. Sometimes the traffic jam from Selayang can stretch as far as the UMNO PWTC building there. It is a long way, and we hope for the government's attention.

The second concerns FT3209, which Rawang residents use when they want to go towards the NKVE. They will pass along that road, and that road goes from four lanes into one lane, which is indeed a very serious bottleneck, and we hope for the government's attention. Next is regarding what I always mention, B27. Regarding the missing lane, earlier the Government and the EXCO answered questions from my side and also from the ADUN of Kuang. However, next year we do not see that matter in the road upgrading in that item. We ask for an explanation from the Government. And next, I want to refer to page 229, project code PK 1, River Flood Mitigation Project Development. We understand that last year or this year, many places experienced flooding. But usually when we chat with other ADUNs, we feel that the process of obtaining allocations or approving projects for JPS takes a very long time compared with JKR. I understand that JKR allocates funds to each district, but for JPS they must obtain approval from HQ, and it will take a very long time for the project to be approved, approved to resolve these problems. So I hope the process of obtaining allocations for JPS can be streamlined so that these flood problems can be solved in a short time.

Finally, although I am not a Muslim, I want to raise the issue of mosques. Regarding page 246, PK3, Object Code 03204, Mosque in Taman Pelangi. In the item details, we can see there is the Taman Pelangi Mosque in Rawang, but until now we cannot see any allocation channelled or any project approval for this mosque, and there is very high demand from residents there. Taman Pelangi is a housing area where the majority are Muslims, so I hope the Government can give attention to the development of a mosque in Taman Pelangi, Rawang. That is all from my side, thank you.

Deputy SpeakerEN

Thank you, Rawang. Next, Kuang.

Tuan Sallehudin bin AmiruddinBERSATU · PHKuangEN

Thank you, Madam Deputy Speaker. First of all, I would like to refer to a news report published by the newspaper Sinar Harian on 7 November 2019. Today the world is talking about climate change. This climate change, or climax change, is a phenomenon, and this phenomenon is occurring across the whole world. And when I read several articles concerning this climax change, several disclosures were made by a private education centre, namely the Center for Gabenor Political Study, stating that several major cities in Malaysia are going to sink by 2050. Given that we will reach, if we live long enough, I think Templer's age will be even longer, in the next 30 years he will only be just under 56 years old. Among the states affected are Perlis, Kedah, Penang, Perak, Negeri Sembilan, Pahang, Kelantan and Sarawak. In the Selangor area, Kuala Selangor may disappear from the geography as it exists now. Port Klang will sink, Shah Alam will shrink, Kuala Lumpur International Airport, which is located on the coast, will also shrink, and several areas in Malaysia will be directly involved, Bagan Datuk, Teluk Intan, and all of this is because of the climate change phenomenon occurring across the world. So in 30 years' time we will be able to feel it. We must feel it now, sometimes we can imagine what will happen in 30 years, but if we adopt an attitude of ignoring the reports, ignoring this climate phenomenon. Even in international forums, climax change has become a topic that is very hotly discussed at the international level. Therefore we have 30 years from now, apart from WKB or the Wawasan Kemakmuran Bersama, we must also focus on how to overcome, how we must learn to improve, improve what, improve the standard so that we avoid this disaster happening in our country.

Today we may not feel it, but in 30 years' time or 15 years' time the signs of this change will certainly occur. Therefore, if we look at the development budget that has been approved, this development budget is seen to be very marginalised. The issues concerning river basins that do not have sufficient allocations for us to maintain and manage these rivers should in fact be given priority. To prevent us, to help for at least the next 20 years, what we need to do, starting from today. If we more or less do not change or we do not contribute to these numerous river basins in the State of Selangor, we will more or less fall behind and we must be prepared to face an even greater climax change. Today, rainfall of 62mm is already very large for us, causing some areas of Kuang to sink, but what will happen when 100 millilitres of rainfall occurs, are we ready to face it. This is what we must prioritise in the coming budgets. The river basins across the whole of Selangor must be studied, to see how they can help us to solve the problems of climax change that will occur in our country in the future. That is regarding weather changes..

Tuan Mohd Najwan bin HalimiPKR · PHKota AnggerikEN

Can Kuang interject?

Deputy SpeakerEN

I do not allow it. Kuang, summarise.

Tuan Sallehudin bin AmiruddinBERSATU · PHKuangEN

Should I stop or what? I want to. Okay, there is one more matter concerning the replacement of the bridge at B149. I had previously conveyed my views to the District Engineer, that the substructure of the bridge building should be built for four lanes. What I mean by four lanes is the substructure, and this substructure consists of pile work as well as footings and so on for the bridge, for the enlargement of the bridge. According to the original design, this substructure was only for the two lanes of the bridge, so I request that this substructure be prepared earlier first, because to ensure that in 10 years' time we do not need to drive piles into the same place again, but instead we only erect pillars, and eventually we can place long beams to build the bridge. But unfortunately, when the design was completed, the Planning Unit did not approve the addition of this substructure, because if we do not do it now, in 10 years' time the beam at 149 will be congested, and another development project will be undertaken 10 years from now for the traffic of cars that is increasing in the area concerned. Anyway, the last thing I want to say is thank you to the Honourable Menteri Besar for giving us a mosque to be built at Batu 20, Masjid Al Hikmah, Batu 20 Kuang, and this additional amount will make possible the establishment of a new mosque, and I hope there will be 2 more mosques next year that we will submit to the State Government to be built. I thank you for the other matters regarding bridges and roads and so on, my fellow Honourable Members have all begun to express disappointment about our infrastructure, which has not reached the standard of a developed state, because when we look and when we walk on the roads, it is as if we are walking 20 years ago. Thank you.

Deputy SpeakerEN

Thank you, Kuang.

Next, I invite the Government side, if it wishes to clarify any matters raised by the Honourable Member. Batu Tiga, please.

Puan Rodziah binti IsmailPKR · PHBatu TigaEN

Thank you, Deputy Speaker. Alhamdulillah, I thank all the Honourable Members. There are 4 Honourable Members who touched on matters within the Vote related to my portfolio. Mainly, I want to correct from Bukit Malawati, the Object Code referred to should be 02004, not PK 20002, which concerns Malawati who raised the matter of the proposed directive to make a special allocation for the village security programme. I want to state here that approval has already been given during the time this programme was named the Ikatan Desa programme, that approval has been given for all, firstly, a course was held for all members involved, 10 persons per village, and secondly, equipment was provided for the members of this Ikatan Desa. It had already begun to be given from January 2018 until 14 March last, where the equipment that has been handed over consisted of caps, shirts, reflective vests, torchlights, walkie talkies, traffic cones, batton lamps, notice boards, Ripitor radios and first aid kits. When there was a change of government or the PRU14, there was a change of Village Heads, so some of the Village Heads or the equipment may possibly have not been retained or may have been lost, whereas all the equipment I have named is equipment that must be handed over in full to the responsible party at this time. So that equipment, but now the district office already has an inventory, yes, villages that do not have it, we will, we will ensure that the responsibility of the previous Village Heads must also be taken into account. And in fact the cost allocated there was three million six

hundred and seventy-nine ringgit and one hundred and fifty-two sen, sorry, three million six hundred and seventy-nine ninety thousand one hundred and fifty-two ringgit, which relates to the course and equipment, but the allowance for the 10 volunteers in each village was not given at that time.

So, at present, the insurance proposed is only for the Village Community Heads and Village Heads, but not for those who serve as volunteers. However, we have discussed, and plan to discuss with SOCSO, so that if possible these persons can, as people say, as volunteers or privately apply for group insurance that can be applied for by the responsible parties, and I wish to inform here that this programme has now been named in full the Nadi Desa, Sihat dan Sejahtera programme, in which the course will begin this month, namely 40 selected villages will be called back to ensure that issues related to village security are re-emphasised so that security issues, not only the initial warning for disasters and so on, can be dealt with by them at the outset. That is for Malawati. For PK, for Gombak Setia, there is nothing. I will answer for the PLB stall first, Meru first, because Meru is present in the House. For the information of Meru, PK 02006, regarding the issue raised, namely Meru saying 1 million is not sufficient. In fact, we see that the 1 million allocated here is after...

Deputy SpeakerEN

Batu Tiga may continue.

Puan Rodziah binti IsmailPKR · PHBatu TigaEN

Continue, Meru, thank you.

Deputy SpeakerEN

Please sit down first. Honourable Members all. The time has now shown one o'clock in the afternoon. With this, I adjourn the House until 2.30 in the afternoon. The House is adjourned.

(THE HOUSE WAS ADJOURNED AT 1.00 P.M.)

THE HOUSE RESUMED)

(MR DEPUTY SPEAKER IN THE CHAIR)

Deputy SpeakerEN

Bismillahhirohmannirrahhim. Assalamualaikum w.b.t. and good afternoon. Honourable Members all, the House sits again for the winding-up session by the Government side. Batu Tiga, please.

Puan Rodziah binti IsmailPKR · PHBatu TigaEN

Thank you, Deputy Speaker. To resume my answer to the Honourable Member for Meru, who raised the matter of allocation PK02006, namely the upgrading of rural roads amounting to RM1 million, which was reported to be insufficient. Let me, allow me to explain a little of the process by which this amount or matter can be understood by all Honourable Members. Firstly, as I always mention in the House, when the 371 MPKK Traditional Villages were required to complete the village information system, which we have often reminded everyone of. So the profile of these villages has already been raised, or has already been seen as the most important information to be taken note of by all the parties concerned. From this system, the allocations will be divided among several agencies that will take cognisance and take further action. Firstly, it will be channelled to rural development, the Ministry of Rural Development. Matters that we say are relevant, that are outside the scope of the State Government but under the purview of the Ministry of Rural Development, must be taken up. Secondly, we will also liaise, the government will liaise with the parliamentary allocation, under the parliamentary allocation, namely under the people-friendly programme allocation which we channel wherever possible, the people-friendly programme headed by ICU will take a small portion of the applications received there. Thirdly, it will be allocated under the MARRIS allocation, mainly for roads that will be managed by either the Public Works Department, JPS or the PBT. For the remainder, yes, the remainder of this RM1 million budget will be managed by AP, namely the Distribution Division, the Distribution Section, which will be channelled to the District Office. How and where will this RM1 million be spent? What I mean is, after we have distributed to all the agencies concerned, and we, the Selangor Government, set RM1 million based on the possibility of new applications. So this RM1 million, for now, there is no list yet, because starting from 2020, all Honourable Members who feel there are still roads that have not yet been, or need to be upgraded, roads or any rural development, mainly roads, yes. They will be selected, applications will be made, applications will be requested from the District Office to nominate. So usually it will be obtained at the beginning of the year, namely January or February 2020. From there, the distribution of the RM1 million will be carried out. So that is the question, the answer I have given. So, in conclusion, we, STANDCO Rural Development, coordinate all the applications received, we put them into one system and redistribute them to the agencies concerned. Ultimately, the RM1 million state allocation that we float must be applied for by all District Offices, perhaps from the views of the Honourable Members. Please proceed.

May I seek a little clarification, please. For this year, is there any surplus in the budget, or not? If there is a surplus, will it be carried forward to next year.

Puan Rodziah binti IsmailPKR · PHBatu TigaEN

The matter we are discussing is the RM1 million in the 2020 budget. So, starting next year, it will gather the requests that have not yet been made in 2019. Yes, meaning that after we distribute it to all the agencies, namely KPLB, the Mesra Rakyat programmes, JKR under MARRIS, under JPS and under the PBT, we will then set aside this RM1 million, should there be additional requests from the Honourable Members who wish to apply for more that are not on the list submitted by the existing agencies. So from January, usually January and February, we will accept new applications, but remember that our quantum, or the amount we give, is only RM1 million. That is the process that actually takes place, and I hope it is clear to the Honourable Member so that no one thinks that only RM1 million has been allocated for upgrading, when in fact it has already been distributed to the existing agencies. As for this RM1 million, if you ask me whether there is a list, there is none yet, because 2020 only begins in January, and we have only just started collecting additional lists, if there are any. If there are. So that is all from Meru. Gombak Setia has already come in, Alhamdulillah. So the question raised, or the supply raised, by Gombak Setia concerns issues relating to PLB stalls, or Rural Development Stalls. Now, I would like to say here that the issue raised throughout Selangor, apart from road issues and so on, the PLB stalls are also a problem for us. But I still remember that I myself asked the same question in 2016, and perhaps until now this matter has not been improved as well as it should be. But here is my answer, for the information of Gombak Setia and all the Honourable Members: PLB stalls were originally built and supervised by the District and Land Office, the purpose being to build these PLB stalls to help micro and small traders. But now, due to constraints on officers and maintenance allocations, the management of all PLB stalls has been handed over to the Local Authorities. That means any PLB stall now has already been handed over to the Local Authority to be managed, whether its licensing or other related matters. I take note of the infrastructure issues raised by Gombak Setia, but before they were raised earlier this year, I had actually requested, well, how many PLB stalls are in a dilapidated condition, have not been repaired and so on. And in my hands I actually have a complete list of these, and we can see here, God willing, we, I think this matter should, once it has been handed over to the PBT, meaning the PBT is the one responsible thereafter. Because this policy is already in place. So all PLB stalls are no longer managed under PLB but have been handed over to the PBT. So based on the feedback we received earlier from all the PBTs, the PBTs already have plans. Some PBTs have plans, while some Local Authorities still do not have plans on how to maintain and also repair the physical condition of the existing PLB stalls. So for that reason, the conclusion I can state here is that we hope, under STANDCO, my name, because that name is what keeps it still associated with PLB, with my STANDCO. So in summary, I am saying here that, following the study I have seen, all the PBTs that have PLB stalls, except Majlis Bandaraya Petaling Jaya, have all already changed the name so that it is no longer known as PLB; they have named them PBT stalls. So we also see that among the things we can improve is for all of them to be handed back, renamed so that they are no longer known as PLB, but named Majlis stalls. And finally, from the feedback received, it will certainly involve budget constraints or allocations, so from here I hand it over to the PBTs themselves to arrange so that in the near future it no longer becomes a problem. But God willing, as long as it is not handed over or better planning is not made, God willing I will take responsibility to ensure that all those processes run smoothly. That is related to PLB stalls, and finally Gombak Setia plans to increase the Hijrah limit, the Hijrah loan. Let it be more than RM50 thousand. I would like to state here that for the time being the government does not intend, yes, to increase the loan that we say can be borrowed from RM1,000 to RM50,000, because we see that, Alhamdulillah, Hijrah Selangor, in collaboration with Invest Selangor, has already carried out a proactive programme, a proactive step, namely we have ensured that we call them Hijrah graduates. That is, after RM50,000, when they want to further increase the productivity of their business or enterprise, and they want to borrow perhaps more than RM50,000, we call them Hijrah graduates. What has been done is that we have already started discussions, and there are already 120 graduates who, during the Selangor International Business Summit organised under Invest Selangor, we have engaged, or cooperated with, IBIM, namely the Persatuan Institusi Perbankan Islam IBIM, which we started in December 2018, to obtain capital or existing loan capital. Not only that, Hijrah also has an initiative to take these 110 to engagement with SME Corp, to development banks and to larger banks. Yes, so that afterwards they, we say without limit, without limit, they can borrow and can continuously elevate their businesses to a higher level. And most importantly, not only that, but under Hijrah and also under STANDCO, we help our entrepreneurs to also obtain programmes, for example if their business is good and can franchise, they have been linked with Permodalan Nasional so that they can obtain franchise programmes. Yes, meaning we pattern their business and eventually they can open a bigger business network. So that is all, Deputy Speaker, for the answer to Gombak Setia. Thank you.

Deputy SpeakerEN

Thank you, Batu Tiga. Next, from the Government side, I invite Pandan Indah.

Tuan Ir. Izham bin HashimAMANAH · PHPandan IndahEN

Thank you, Deputy Speaker. I also extend congratulations and thanks to the Honourable Members who participated in the debate and discussion regarding development expenditure. I will try, as much as possible, to respond to the questions that arose involving the Public Works Department (JKR) and the Irrigation and Drainage Department (JPS), and there was one question regarding the Department of Agriculture, no, sorry, under the Department of Agriculture, yes. Regarding the question on roads, as I mentioned in my winding-up speech the other day, the Government takes seriously the quality of roads in the state of Selangor and how we carry out maintenance efforts. I have presented the latest technologies that we already have and will implement, including the management of potholes, or road holes. We already have certain methods that we will implement. However, I would say here that, given our financial constraints, although I know many have requested large amounts, the cost of building roads or infrastructure is not cheap, it is very high, and moreover we face problems in terms of utilities. I have said many times that utilities, because they were not managed earlier, for decades, are now tangled underground with cables, water pipes, and on top of that gas, and gas pipes too, which means that whenever there are development efforts, upgrading, road widening or flood mitigation, we will incur high costs to relocate them. This is something we cannot avoid. We are not only losing money, funds, because of this, sometimes, well, not sometimes, almost all these costs, almost the cost of relocating these utilities, is about the same as the cost of building the road itself. Almost so! Or two-thirds, or half, that is what happens, and this cannot be solved in a short time, in the near term, but we must have planning, and we have already begun planning to establish what is called a utility corridor. A utility corridor where utilities are provided with a corridor in advance, and it will not involve road widening, nor will it disturb the pipes or whether the pipes or cables that will be buried there.

This has already been started in Pahang, and Johor has already prepared this, and Selangor will follow shortly. And it is suitable in areas called greenfield. Greenfield refers to areas that are still new, but brownfield areas, which already exist, we will study how implementation should be carried out. Because it involves areas that have already been developed, of course it is rather difficult.

However, we will find a way, whether by using tunnels, or utility tunnels, or common trenching and so on, that we need to implement. And also included is what I mentioned recently, namely the implementation of utility mapping. Which has already been implemented in many countries. Any work to be carried out in that area must first obtain a detailed utility mapping, which details the whole structure of utilities that exist there, including cables and so on, before entering to carry out work. Because we find that most damage to roads and water pipes is caused by third parties. These third parties do their work, they just bore, they just dig. And I found (my experience as a councillor earlier, 10 years too), they come. We have just resurfaced a road, as mentioned by the Honourable Member for Gombak Setia, we have just finished resurfacing, and on the weekend, they know we are off, they come and just dig. Utility contractors. This is what happens, and when it is patched, it is substandard. They patch it, and they are supposed to come back three weeks later to do a permanent repair. But they have never come. So this causes subsidence, causes accidents and damage to vehicles.

Because according to the standards set by the PBT as well as JKR, when utility works (excavation) take place, they must in fact resurface the entire road, not just patch that one spot. Not just that place. They must do the whole stretch of the road, they must resurface it. But this did not happen, and that is why I once proposed in Subang Jaya that the deposit for these utilities be imposed in the form of cash. If it is a bond, it is difficult to release. So use cash. If they are slow, do not do the work for several months, we use that cash to do the best for the road. This is what happens. I see this matter, we will implement it comprehensively for the state of Selangor too. It is not that we want to punish the utility companies, but we want everyone to be responsible together, to provide cooperation to ensure that the quality of our roads continues to remain in good condition.

Tuan Muhammad Hilman bin IdhamBERSATU · PNGombak SetiaEN

Honourable Exco Member.

Deputy SpeakerEN

Gombak Setia, please proceed.

Tuan Muhammad Hilman bin IdhamBERSATU · PNGombak SetiaEN

That is why yesterday, in my debate, I raised how we should carry out coordination among agencies, as the Honourable Exco Member just mentioned. There are some agencies that dig up roads carelessly, and if it is just digging, that is not a problem because it is only in one place. What is more unfortunate is, in the example I gave yesterday in front of Masjid Al-Khairiah, Taman Sri Gombak, they cut the road for several hundred metres. So this is something that I consider very serious, because it results in our expenditure eventually being wasted. Because we have to resurface several times, and this is what I think is important for us to look at, and I believe in this matter no agency should be allowed to dig as they please, at any time they like, whether on weekends, when no one is looking, at night and so on, that is not acceptable.

And that is why I say that, through the Smart Selangor efforts too, we can ensure this coordination can run without large and high-level bureaucracy, and at the very least, the simplest way, we can implement conventional coordination, perhaps before resurfacing any road, a coordination meeting is held between JKR or the contractor, the land office or the PBT, together with all the agencies involved, whether SYABAS, whether TNB and so on, to ensure this no longer happens in the state of Selangor. Because the people of Selangor today are very clever, smart, and they know that the government is unable to coordinate this, so that eventually government money is wasted. Thank you.

Deputy SpeakerEN

Pandan Indah, please.

Tuan Ir. Izham bin HashimAMANAH · PHPandan IndahEN

Okay, Honourable Member for Gombak Setia. It seems we have the same wavelength, the same thinking, which I am sure is shared by the Honourable Members present (everyone present in this House), and I will ensure that going forward there is better coordination in implementation, not only regarding utility involvement in digging works and so on, but also involving the management of potholes, which was raised by the Honourable Member yesterday, yesterday morning, yes.

On the question raised, I refer to the Honourable Member for Kota Damansara regarding Code 04107, the issue related to Jalan Bukit Badak. So for the information of the Honourable Member. Is he here? Oh, he isn't here. Never mind. We will continue.

For Dusun Tua, I (is Dusun Tua here?). Dusun Tua is here, okay. I will take note of the issue regarding Dato' Siti Nurhaliza cycling on the cycle track at Jalan Sungai Lui. Although I think it is still not confirmed, it is still just rumours, not yet news, but because it is just rumours, this project has been dropped.

(House laughs)

Because this project has lower priority, and we need the funds for other projects. However, we will review it. Not because Dato' Siti Nurhaliza cycled there, but we will re-examine the need for a cycle track there, yes.

For Banting. The question from Banting (03402) regarding Sungai Kelambu (Jalan Sungai Kelambu, Genting Sanyen). An allocation of RM500,000. If the allocation is small, it means either the project has ended or it is only just beginning. We must understand it that way, yes. So the RM500,000 there, although the project is large at RM120 million (if I am not mistaken), is used for design and land acquisition plans. This project is somewhat delayed because it involves land acquisition in forest reserve areas. There are about 44.5 acres involving forest in the area concerned, and we must complete the land replacement process. So it takes a little time. Is Banting not here? No. Never mind, no need to remember. And for the same one as well, which

Speaker.

Deputy Speaker

Morib.

Tuan Hasnul bin BaharuddinAMANAH · PHMoribEN

Related to the issue

Deputy SpeakerEN

Clarification? Morib, please.

Tuan Hasnul bin BaharuddinAMANAH · PHMoribEN

The Sungai Kelambu bypass. We are well aware that the budget for this project was, for this year's budget, 2019. So I should have asked whether that budget is still being kept, and will be carried forward to next year so that we can implement this project?

Tuan Ir. Izham bin HashimAMANAH · PHPandan IndahEN

We have allocated RM500,000 for next year because we are of the view that this project will not start with the existing issues. So we allocate funds to complete the design first, and for the ceiling, the project is already there. It has been approved, and the ceiling is RM120 million if you look at this book (this budget book). But for next year we allocate RM500,000 to resolve the issues related to the design and also the land issues in the area concerned.

About 4402. However, this project will not be dropped, yes. 4402 is related to the Klang alternative route, which is from FT005 here. Likewise, RM500,000 is for the design, and this project will also involve upgrading the two-lane road over a length of 8 to 11 kilometres. This is the 4402 that was raised, the Klang alternative route.

And for street lights, traffic lights, which were discussed so heatedly, every district receives RM500,000 for street lights, traffic lights and also 4406, or from one, which is road safety aspects, another RM500,000. This means for each district we indeed allocate RM100,000 for new works, yes. New works, not maintenance works, yes. These are new works involving street lights and also traffic lights. So I don't need to repeat this. Later when we reach Jeram. So I said

Tuan Mohd Shaid bin RosliBERSATU · PHJeramEN

If that's the case, I'll ask.

Tuan Ir. Izham bin HashimAMANAH · PHPandan IndahEN

Let me finish first. Let me finish first.

Tuan Mohd Shaid bin RosliBERSATU · PHJeramEN

Huh? Finish first?

Tuan Ir. Izham bin HashimAMANAH · PHPandan IndahEN

Not yet finished explaining.

Tuan Mohd Shaid bin RosliBERSATU · PHJeram

Nanti lupa.

Tuan Ir. Izham bin HashimAMANAH · PHPandan IndahEN

This involves new roads (street lights and traffic lights). For maintenance, it is separate, yes. And we must understand that the allocation tabled in this budget, or in this development expenditure, does not involve road maintenance, because road maintenance falls under the allocation of MARRIS. The MARRIS allocation is not provided in this book

here, yes. For next year we have RM500 million to be distributed for the maintenance of roads, including road furniture and also street lights and traffic lights that are under maintenance. So we actually have two sources. Not only this, but also through MARRIS, and for MARRIS we must understand that the federal government has made a statement that this allows, starting next year, MARRIS money to be used for upgrading works up to 15%. I recall 15%, but I heard later that it was raised to 20%, but we will check whether it is 15% or 20%, with a minimum of RM15 million, or 15%, whichever is lower. If he said only 15%, it would be easier for us, there would be more for us. But he said 15% or RM15 million, whichever is lower. This can be used for the first time for roads to be upgraded, including

Tuan Mohd Shaid bin RosliBERSATU · PHJeram

Yang Berhormat.

Tuan Ir. Izham bin HashimAMANAH · PHPandan IndahEN

road drains and also road furniture related to the road.

Tuan Mohd Shaid bin RosliBERSATU · PHJeram

Yang Berhormat.

Tuan Ir. Izham bin HashimAMANAH · PHPandan IndahEN

We will use this. Be patient first. Not finished yet. Be patient. Let me finish this part first. So these are the matters that will be used to help us implement the necessary works, and we must bear in mind that not everything can be done immediately at the same time. As I mentioned, our financial constraints. If we want everything done immediately, there will certainly be no financial capacity to implement it. So we have to choose priorities, and another thing, we must understand that not all street lights are under JKR. Do not assume all street lights belong to JKR. Some are under TNB, some are under PBT. So we have to look at the suitability of where we want to carry out the works. But we give a commitment to help improve lighting for roads, because JKR actually did not ask for RM500,000. JKR asked for RM2 million. RM2 million JKR application means RM2 million for that road in each district, but only RM500,000 was approved. So, that is the constraint we face. Let me give the floor to Jeram.

Tuan Azmizam bin Zaman HuriPKR · PHPelabuhan Klang

Mohon pencerahan.

Tuan Mohd Shaid bin RosliBERSATU · PHJeramEN

Wait. I'll go first.

Deputy SpeakerEN

Let us give the floor to Jeram first.

Tuan Mohd Shaid bin RosliBERSATU · PHJeramEN

Thank you.

Thank you, Honourable Member. The Honourable Member said each district gets RM500,000 only for lights and also traffic lights. So, the new ones, yes. I'd like to ask the Honourable Member because if RM500,000 is said to be a small amount, why, Majlis Daerah Kuala Selangor has 5 state constituencies (DUN). With 5 DUN, if RM500,000 is as I calculated just now, how many new lights can be made? And how many traffic lights can be made?

Deputy Speaker

Soalannya Jeram?

Tuan Mohd Shaid bin RosliBERSATU · PHJeramEN

Okay. Secondly, I also want to ask. This is not the Honourable Member's question. This is not a supplementary question, yes. If MARRIS,

MARRIS, I was informed is for roads only. MARRIS cannot be used for street lights. I understand. Because when I asked the District Engineer, he said MARRIS is for roads only, not for street lights. So where is the RM500,000 allocation sufficient?

Tuan Ir. Izham bin HashimAMANAH · PHPandan IndahEN

The Honourable Member must meet me. Later we will give the details. Actually that is wrong. Wrong. Actually under MARRIS, maintenance of roads, all types connected with roads can be maintained using MARRIS allocation, including drains, including road furniture, lights and signals connected with road maintenance. And we must also understand that traffic lights are not just built solely for the project itself. Most of these projects are connected with roads (included in the contract). So do not assume that traffic lights or street lights are just a standalone project. No! This is a one-off project that we must carry out. If it is connected with a new road upgrading, the street lights will also be upgraded together with the road project itself. That is what we must understand. This RM500,000 contract is only for one-off needs. Suppose there is one or two lights at a junction (on an old road), yes, that we can do. But if the road already has lights and they are damaged due to lack of maintenance, that can use MARRIS. Under road maintenance. We must understand this, yes. So we must be clear on which allocation we want to use for road furniture and for the use of facilities such as lights and so on.

Deputy SpeakerEN

Please, Pelabuhan Klang.

Tuan Azmizam bin Zaman HuriPKR · PHPelabuhan KlangEN

Thank you, Madam Deputy Speaker. Thank you for the explanation given by the Honourable EXCO for Pandan Indah. Regarding these street lights, we have to accept the fact, Honourable Member, that the lights that are problematic now are mostly JKR lights. And is it because for TNB lights, I really hope that TNB poles are used as street lights, because if we look at the road to Sabak Bernam which uses these TNB stone poles, the lights will not go out, because no one wants to go and steal the wires, no one dares to touch stone poles. But if JKR poles, they are often subjected to vandalism.

Is the State Government planning that for these JKR light poles, it is not only when they are damaged that innovation is done, is there any State Government or JKR Selangor that from the beginning has planned to build these new lights using the latest innovation? Let them not look pretty, let the wires look dangling, there is no need to bury them in the ground, but eventually when the light is damaged in future, the wires will still be left installed above, not installed below as well. Because theft often happens. Will the state government change the policy on new lights, we just go ahead and innovate so that there is no vandalism impact?

Tuan Ir. Izham bin HashimAMANAH · PHPandan IndahEN

I think. Thank you, Pelabuhan Klang. Pelabuhan Klang already knows, I already answered on that day about this lighting issue. I already mentioned in the winding-up that these lights, we will have cable theft. Actually I too was formerly from Tenaga Nasional. We have the same problem of cable theft. The thief will choose whether it is TNB's or JKR's. He chooses. He does not care

which one he can take, he takes it. So that is why among the innovations I mentioned in the recent winding-up is that we will change (begin changing) the cables from copper cable to aluminium cable, which is cheaper compared with copper cable. This is indeed welcomed because the price is expensive. And also the use of solar. Solar lights that have no cable will use solar. That too we will begin to introduce. But the cost, it takes time, this matter will be phased, and also its service door on the pole we will raise high so that it is not easy to open and take the cable and so on. These are among the innovations that will be introduced. I already mentioned that in the winding-up, yes.

Furthermore, this innovation is not limited to 4406 which was mentioned in connection with road safety. I understand there was indeed a complaint from Sungai Panjang earlier mentioning the problem on FT005, yes. 05, yes? Yes, 5 from Tanjong Karang to Sabak Bernam, which is under JKR Malaysia. However, it involves the safety of residents in the State of Selangor, and I have raised this matter many times in the State Action Council so that appropriate and proper action is taken against the contractors concerned because they failed to provide all the facilities or in terms of warnings for the safety of road users. I have raised this many times, but we are out of our control. The state JKR also does not know what they are doing there. So the use of blinkers and so on, there are already new technologies that can be used, cheaper, more durable, which we will introduce for use on our roads. Even the use of the yellow speed breaker, the thick yellow paint, has begun to be questioned because it is dangerous to motorcyclists because it is slippery. This too is an innovation that we must examine carefully to ensure more suitable cost while at the same time the safety of users.

For Pelabuhan Klang. Pelabuhan Klang asked many things, yes. But some of them I have already answered, yes. Okay. Regarding Telok Gong, we have mentioned here that the upgrading of Telok Gong 04306. There is some constraint in terms of cost, yes. So when the design was done and the costing or BQ was done, it was found that the cost has doubled from the ceiling we had asked for. The overall cost was estimated at RM50 million, but it was found the cost rose to RM102 million. So this caused a review of how we design to reduce this cost. That is why JKR has begun to review the design in terms of alignment and so on to ensure we can. So there is a bit of delay there, and if the Honourable Member needs it, JKR has no problem presenting again to the upcoming District Action Committee to explain how this project will be implemented.

For Pandamaran, the Pandamaran-Banting road through FT3218. Based on the specific check on Road FT3218, the one meant here, that is, this project will be implemented by the developer 'Fellox Development Sdn. Bhd.'. This has been made a condition for them, and the part FT181 is that the construction is titled under Pulau Indah Phase II, which is still under construction. Part of it is involved under that.

For road upgrading. I have said here that the road upgrading projects under this development expenditure have their own separate title for upgrading this road. If the roads are generally roads that we have not yet

identified, we will conduct a study. If there is an urgent need, we can use, as I mentioned earlier, MARRIS for upgrading and also for us to conduct further studies on its implementation if such a need arises. Usually for those where the need already exists, the projects to be implemented have already been listed.

For Seri Setia. Regarding the old Subang Airport road to Subang Airport. For the Honourable Member's information, this project has already conducted a traffic study on Jalan Subang Lama (Jalan Subang Airport) up to the Federal Highway, and the study will end on 16 November this month. Is it? Yes, yes. 16 November. And after the study, according to JKR SOP, it will prepare a project brief and cost estimate before being submitted to the JKR headquarters. So this means the study will be complete in about another week.

Tuan Halimey bin Abu BakarPKR · PHSeri SetiaEN

May I interrupt? Madam Deputy Speaker?

Deputy SpeakerEN

Please, Seri Setia.

Tuan Halimey bin Abu BakarPKR · PHSeri SetiaEN

I want to ask the Honourable EXCO, if according to what the Honourable Member said, the study it will conduct will end on 6 November (this November, yes) this year. So 6 November has already passed? 6 November this year, correct? 16 November. Okay. So that means after 16 November, it will issue another cost, including the estimate if this road is built. And will this estimated cost be included in the 2020 or 2021 budget?

Deputy SpeakerEN

Please, Pandan Indah.

Tuan Ir. Izham bin HashimAMANAH · PHPandan IndahEN

What I meant here is that this study usually looks at its flexibility, whether from the traffic assessment, whether there is justification for it to be given priority. So there is a method for it. Once we have completed the study and find that this road is indeed needed, then it will carry out a more detailed study on the design requirements and so on. Only then will it appoint consultants to help them prepare the details. That process also takes time to implement. And according to this plan, it means next year the detailed design for implementation of the project will be carried out.

As for Guthrie TTDI, I myself took the initiative because I found that this project has been delayed for a long time and found that the need is very, very urgent because of traffic light 199. Those who live on the Shah Alam side know. The old traffic light 199 where you wait. Near TTDI, near the Stadium. That is, whenever you arrive, it is 199. Yes, you wait. At peak times, we find congestion coming out from NKVE, from Bukit Jelutong, and added to that the GUTHRIE highway traffic, which causes congestion, and its LOS (level of service) is indeed E to F there, all the way to the Federal Highway. So this I have already mentioned, and they have carried out a study on this road, and this junction will be upgraded, involving the alignment that will start from the GUTHRIE Highway to the Federal Highway. This involves a cost of RM201 million, and an application has been submitted to be included in RMK12 under the RMK12 project.

Further regarding this road pothole that was raised, I would also like to touch on this matter. It is best that I mention it here once only, because this involves feedback from Gombak Setia and also Kuang who spoke about. We, at the MMIKN level, have indeed decided to implement holistic monitoring and implementation of port holes across the State of Selangor, which I am working on (I mentioned it earlier, yes). It not only involves complaints, but also involves implementation and also feedback. Sometimes we do it but people do not know we did it. There is no feedback on the progress or implementation of port holes that have been successfully carried out. So all of this is in our plan to be implemented as quickly as possible. It may also involve upgrading the IIR system or the intelligent respond system developed by SSQ to use as the method, but so far it is not comprehensive. The local authorities (PBT) have their own methods, JKR has its own and so on. We have many, too many systems and reports on port holes at any time, there are many. There are 45,000 or so. At any time. Many port holes. So we must do this carefully, and I have already held a first round of discussions with the PBT on how we coordinate these complaints so that they can be centralised. Otherwise it will be difficult for us to implement. At the same time, technology. Technology, I have mentioned in the winding-up. Technology for port hole patching now has all kinds of very sophisticated and suitable technologies. They can last a long time.

Deputy Speaker

Pandan Indah.

Tuan Ir. Izham bin HashimAMANAH · PHPandan IndahEN

In some places I visited, they can even give a two-year guarantee.

Deputy SpeakerEN

Pandan Indah, Gombak Setia wants an explanation.

Tuan Muhammad Hilman bin IdhamBERSATU · PNGombak SetiaEN

Honourable EXCO, so in my debate yesterday, the feedback I asked for concerns the efficiency status of the system or the implementation of what we have carried out before, because we want accurate feedback. If the Honourable EXCO just said 46,000 complaints, that is actually a small number if they are recorded in one system, because I am confident that with such sophisticated technology we can handle not just 46,000 complaints but even hundreds of thousands. That is why coordination down to the local authority (PBT) level is also important, so that in the end we can solve this problem. Because if we keep with the attitude of, meaning we will look again, review the situation again, then I think we will never be able to solve this matter. Thank you.

Tuan Sallehudin bin AmiruddinBERSATU · PHKuangEN

I want to continue a little.

Deputy SpeakerEN

Continue, Pandan Indah.

Tuan Ir. Izham bin HashimAMANAH · PHPandan IndahEN

Thank you, Honourable Member, I'll share.

Tuan Sallehudin bin AmiruddinBERSATU · PHKuangEN

I want to continue a little bit.

Tuan Ir. Izham bin HashimAMANAH · PHPandan Indah

Ada lagi?

Deputy Speaker

Silakan Kuang.

Tuan Sallehudin bin AmiruddinBERSATU · PHKuangEN

What Gombak Setia mentioned is okay. But actually the issue is the quality of work. The quality of the resurfacing. How they seal it. I looked at it, I just passed by this morning. They raised it, they top up the port hole and then they raised it one and a half inches. They assume that vehicles passing over will compact the resurfacing. Actually that is not right. Actually they must do it according to the proper conditions, with proper quality. Why does it need to be raised? This height is what makes everyone's motorcycle jump. Right? When you hit it, you must jump. Your backside hurts even more. Ha, this also has to be counted, right?

Tuan Azmizam bin Zaman HuriPKR · PHPelabuhan KlangEN

Example in front of the SUK. In front of the SUK.

Tuan Sallehudin bin AmiruddinBERSATU · PHKuangEN

Quality is what is important, what we want to emphasise. Is it the system or whatever, it's not a matter la, actually. The quality of work is what matters. How the resurfacing is done, why it must be raised one and a half inches above the old road surface. Why must it be high? Our question is, why must it be high? Why not levelled as well as possible? This is the quality we want to know about.

Tuan Ir. Izham bin HashimAMANAH · PHPandan IndahEN

Actually, Honourable Member, in terms of the idea, it is correct. There will indeed be a depression and it will go down. It will settle. But it is not proper to let it settle on its own. Yes, according to the SOP, they must do compaction. They must do compaction, there is a machine for compacting. But they took the shortcut. But I don't know, perhaps if I want to explain at length, I would have to explain here. But actually our technology, our technology, can be used. I understand. The SOP must also be followed. Some places cannot have water, they must dry first. But now, with the technology, even when it is raining they can compact. The technology is already there. It's just that we are behind. That is the only problem.

Second, we must understand, Honourable Member, that there is a method called cold mix. For temporary patching we have cold mix, because we do not have equipment that can withstand temperature. The temperature must be around 40 degrees so that the bitumen does not harden. So what equipment will they use? They don't have it. That is what we want to buy. So it can withstand that temperature, because the bitumen is left to cool briefly. For the time being they use cold mix for temporary patching, but the problem is that the temporary becomes permanent. That is the problem.

Third, I have told you many times. The structure of our roads is already damaged, it is too old, it is 20 to 30 years old, it cannot be patched anymore. Patching alone cannot work, it cannot hold, it must be upgraded. This is what we will begin to implement and have already implemented, but in stages, so that the old roads are upgraded and patching can then hold. Patching alone, if the structure is already damaged, will not do. It will be damaged again very quickly. We must understand this from the technical side. For Meru, I want to mention it here.

Tuan Halimey bin Abu BakarPKR · PHSeri SetiaEN

Mr Speaker, may I interject?

Tuan Ir. Izham bin HashimAMANAH · PHPandan IndahEN

Yes, this is not… I have a lot of this. I will be scolded shortly because I am late. Please sit down for a moment, yes.

Because we have to… I am always given warnings about my time. I always speak too long. So for Meru, 04307, this is the upgrading of Jalan Haji Manan. We were not given an allocation in 2020. Only now, when speaking, it is about to be included.

For Jalan Haji Manan, we have required the two relevant developers there to upgrade the road up to the existing junction. That means they will complete the upgrading, that is the condition. For the stretch involved in the project to upgrade the drainage system by the Drainage and Irrigation Department (JPS), the Public Works Department (JKR) has also required the contractor to carry out overall repair work on the road after the project is completed. That means, cases of damaged roads and so on, they will complete it after upgrading the drain.

For the river… Pandamaran, my… there is no Pandamaran. There is no Pandamaran. For Sungai Kandis, Honourable Member. I did mention the issue you raised, which is indeed accurate. This utilities issue, that is exactly why we say there is no other way. We must have a long-term plan, and a short-term plan too. The long term is the provision of utility corridors and utility mapping. Only then can we manage the issues relating to utilities scattered underground and reduce costs. We can actually save a lot of money if we succeed, it seems so at the start. I know just now the Honourable Kuang mentioned that, if possible, we build the sub-structure in advance. If the bridge now is to use two lanes, we build the sub-structure for four lanes in advance, the foundation, the piers, all ready. Indeed that is a good idea, and then it is easy to place the rest on top. But the reality is, who will bear the cost? The cost will only be used ten years from now, but we must invest now. Like when we build a house, we want the final plan to be four storeys. We build the four-storey foundation but we build only two first. But the cost of the foundation is among the most expensive. We cannot, we do not have the capacity to do that. Similarly with drains, we say that in 10 to 30 years we will need a large drain. So we build the large one in advance.

Tuan Sallehudin bin AmiruddinBERSATU · PHKuangEN

Honourable Member, if we build it 10 years from now, the cost will have tripled. It needs to be studied now, ideally.

Tuan Ir. Izham bin HashimAMANAH · PHPandan IndahEN

That's fine, I'll tell you the reality. I want to explain this from the technical side. From the technical aspect, from the financial aspect. Indeed, if we have a lot of money, a very large fund, we can do it. We build the largest drain in advance for 30 years to come. But the reality is we do not have that capacity. So we have to do it in stages. That is called upgrading. Because we have to balance between current needs and the funds we have. This is what happens. So I hope this matter can be at.

For Selayang, regarding the issue of road widening at Selayang-Rawang. We have discussed the need. Taman Templer, okay… quiet… cannot hear the voice…

So this is indeed our attention in the area relating to… 600m of road length involved from Selayang to Rawang, has already been included in the study. The study has been done, and indeed the need to upgrade it to 2 lanes was found to be correct. Adding 2 lanes, and it has already been included in our application to upgrade the road. If I am not mistaken, a few tens of millions… it has indeed, it has already been included in the application for the implementation of that road.

In connection with JPS (Drainage and Irrigation Department), for Kota Damansara there is none, okay. Dusun Tua has, okay.

Dusun Tua, feedback on Sungai Serai. Actually, for Sungai Serai, the flood mitigation project has been completed at a cost of RM4.9 million, completed on 12 September 2017. The allocation of RM300 thousand is the cost for a fine survey. The survey cost, because we want to gazette the area concerned. That is the low cost. It is not the cost of construction. It has been completed.

Apart from that, the project to implement a flood retention pond to overcome flooding at Sungai Serai is a different matter. There is a retention pond, the cost is RM15 million, and it has been included under the Twelfth Malaysia Plan (RMKe-12). It has already been included in the RM15 million. Regarding the Sungai Langat flood mitigation scheme (RTB) phase 1, which is in the detailed design process, the appointment of surveyors has been approved by the ministry. This is the federal budget. For information, the department has applied for an allocation of RM145 million under Rolling Plan 4 and also under RMKe-12 for implementation of the Sungai Langat flood mitigation project phase 2. Phase 1 is okay, phase 2 is being applied for implementation. Because the overall Sungai Langat Flood Mitigation Plan, the total is RM700 million. But we apply in stages, this is among the processes we are carrying out. For Banting there is none, I will skip it.

For Ijok, I need to mention here that for maintenance work on drains, rivers and so on, it does not fall under development allocation, development expenditure, it falls under operating and management expenditure. You may refer to B13. For next year it is RM76 million for this maintenance work. And it is distributed, for information this year Kuala Selangor received RM9 million for maintenance. So for Kuala Langat, which he said has none, RM7 million plus for maintenance work. That is strange, yes. For specific work on flood mitigation, for solutions to flooding in the areas involving Ijok and a bit of Bukit Melawati and also in the Kuala Selangor area, the department is implementing the Sungai Buloh Flood Mitigation Project phase 1 with a ceiling cost of RM50 million. This project will be tendered in December 2019. This is a federal project. The project alignment is from the mouth of Sungai Buloh to Bukit Mayong, 17km long. The scope of the project is to upgrade and build banks on the left and right, raised a further 2m… 2 feet… but along 16.7, now roughly 16.7 length will be upgraded. It involves deepening the river along 9km, building 4 pump houses and deepening the borrow pit (surrounding land used to build the banks). It also functions as an inner tributary area to collect river water from the inner side before it is pumped. So this will be implemented and the tender will be issued in December this year. We are confident this project will resolve the flooding issue in Ijok and around Parit Mahang.

For Meru, there is already an allocation for drainage and also for maintenance of the retention pond. But for the bigger project in Meru, involving the Meru flood mitigation plan of RM200 million that was mentioned. This has already been applied for under RMKe-12 for implementation by the Federal Government.

Next, from Semenyih, for Semenyih regarding agricultural roads. These agricultural roads, for information, are under the allocation of the Ministry of Agriculture and Agro-based Industry. Once implemented, JPS will be responsible for maintaining these agricultural roads. So if there is a need, we must look at and study the need for these agricultural roads under the allocation, and if the roads meet the conditions, we can register them under MARRIS and they can receive the MARRIS allocation.

For information, there are 2 areas involved in the sand extraction activities mentioned by Kumpulan Semesta Sdn. Bhd., namely Kampung Sungai Semantar, Sungai Beranang, Kampung Sungai Kembong upstream and downstream. In principle, the department has no objection to sand extraction, as long as the prescribed conditions are followed, that is what we implement. So if there are matters that violate them, they must be reported.

Tuan Zakaria bin Hj HanafiUMNO · BNSemenyih

Timbalan Speaker.

Deputy Speaker

Iya, Semenyih.

Tuan Zakaria bin Hj HanafiUMNO · BNSemenyihEN

Thank you, Honourable Member, Mr Deputy Speaker. I want to request information for the Honourable EXCO: that in Kampung Sungai Semantar, several houses near the riverbank are affected by erosion. I request the attention of the EXCO's office, they have made a complaint and request support from the Honourable Member to be forwarded to the District Office and JPS as well, to ensure these houses do not collapse under the force of the river current. Thank you.

Deputy SpeakerEN

Please, Pandan Indah. Continue.

Tuan Ir. Izham bin HashimAMANAH · PHPandan IndahEN

Thank you, Semenyih, we will take note of what is relevant. Regarding Taman Templer, in connection with the flooding issue apart from this recent one, so as the Honourable Member also mentioned, phase 1 of the RTB Sungai Udang project was completed in May 2019 last year, RM1.2 million, completed. The phase 2 stage, which will involve a cost of RM10 million, has already been approved, but not approved, under RMKe-12 for implementation. Because we have a bit of an issue with land acquisition, as mentioned, that needs to be resolved, and its components involve upgrading the drain or tributary or the river concerned, and also there is a retention pond. Those are its components. RM10 million has already been applied for and placed under RMKe-12. So I think that is all, except one thing I need to mention, which is regarding the Honourable Member for Bukit Melawati. I also mentioned in my speech on flooding, I indeed gave a commitment, in sya Allah, I will give full attention to those who constantly face this flooding problem, especially Ijok, Bukit Melawati, Bandar Utama, and also our EXCO, he cannot speak, but they also have problems, Kota Kemuning and also in Seri Serdang at Sungai Koyoh. So all of these I will give attention to, and focus on finding the money, how, Batu Tiga does not flood, right… how we implement as quickly as possible, short term, long term and so on. And also Bukit Melawati, the phenomenon of high tide, we have already obtained a federal budget of RM42 million which will be distributed to the areas affected by this high tide phenomenon, so that we can take appropriate measures. And for Bukit Melawati, the final supplementary question is regarding government policy on assistance to fishermen. We always provide allocations for our fishermen, not only from the State Government but this year, from the zakat centre, we received more than RM600 thousand for the purchase of equipment for fishermen. RM650 thousand, if I am not mistaken, has already been distributed, and we buy various items, nets, GPS, fish finders, fish containers. Only previously we bought outboard engines and boats and so on, but it was found afterwards that the engines went missing, the boats went missing, and the prices were high, so if this is not managed properly, not many will benefit, and it is not really utilised properly, yes, that is the problem, and we will review it if there is a need for repairing boats and so on, we will look at the cost and implications of how to implement it. Yes, so for this year, Honourable Member for Bukit Melawati, I have also approved the building of one jetty in the Bukit Melawati area, so Bukit Melawati is getting quite a lot. Okay, that is all from me, thank you.

Deputy SpeakerEN

Thank you, Pandan Indah. Next I invite Paya Jaras.

Tuan Mohd Khairuddin bin OthmanPKR · PHPaya JarasEN

Thank you, Madam Deputy Speaker. I would like to take a little time to respond to the Honourable Members who have raised many matters relating to the younger generation, especially those closely linked to PEBT. I believe this is the sitting in which the most Honourable Members have raised issues relating to our youth.

First, I would like to go to what was raised by the Honourable Member for Kota Damansara, in connection with the Selangor Mega Job Fair and the sectors that succeeded in obtaining jobs, although the Honourable Member for Kota Damansara is not here today. For the information of everyone present today, on average the sectors that provided many jobs at our Job Fair were 31.45% manufacturing, 21.2% wholesale and retail trade, repair of motor vehicles and motorcycles, 14.49% accommodation and food and beverage service activities, 6.15% service activities, and 26.72% other sectors and industries. These are the sectors that provided many job opportunities at the Job Fair programme we held recently.

On another matter, the Honourable Member for Dusun Tua also raised the Job Fair, saying that, in his words, it seemed not to receive, did not receive, a response. I would like to stress once again, as the Honourable Member, the Most Honourable Dato' Menteri Besar, mentioned, that the first Job Fair programme we held attracted the participation of 20,000 visitors and involved 180 employers and 70 government department agencies.

Of that total, 12,000 job opportunities were offered, and 20 employers also offered job opportunities to Persons with Disabilities. Perhaps we also held a second Job Fair, which was a modest one, and for that second Job Fair we indeed did not invite many, because only 30 companies took part in the modest format. But for the information of the Honourable Member for Dusun Tua, we will continue to hold the Mega Job Fair, and we cannot deny our success.

For the information of the Honourable Member for Dusun Tua, the Job Fair we organised with 180 is the largest Job Fair compared with those held in other states. Normally, when we hold a Job Fair, we take 30 to 50 companies, but at the Job Fair we held at MIX on 16 March, we invited and held it with 180 companies. So,

this is the largest we could assist with, because our target is certainly to provide job opportunities for the community or the people in the state of Selangor. Of course, there will be weaknesses here and there, Honourable Member, and our Committee is ready to listen if there are changes or corrections that need to be improved; in sha Allah, we are ready to make improvements from time to time.

Next, in relation to the function and role of Kem Ghaffar Baba, this falls under the Most Honourable Dato' Menteri Besar for Education. However, for the information of all Honourable Members, because it also involves our youth centres for us to hold programmes, this camp, the state government through the Management Services Division, Office of the State Secretary, has handed over the administration of the camp to the Ampang Jaya Municipal Council (MPAJ) from 2018.

Among the facilities offered at the place are warden hostels, 8 units. Women's hostels, 10 units. Men's hostels, 10 units. Cafeteria, 1 unit. Lecture rooms, 5 units. Surau, 1 unit. Main hall, 1 unit. VIP house, 1 unit, and a Padang Kawat.

So, if there are Honourable Members who like to run programmes for human capital development or character building, we invite you to Kem Ghaffar Baba to make use of the opportunities available there.

Tuan Haji Saari bin SungibAMANAH · PHHulu KelangEN

Request for clarification. Yes. What I mean is that we have such training centres, and we have facilities such as the National Zoo. We have chalets organised and run by residents, but people do not know that if people from outside want to take a holiday in Kuala Lumpur and go to the National Zoo, they do not know where to stay. So, can we not work together and package the facilities available at the chalets, the operators, private, the hostel facilities, accommodation, as one package for a visit offer to the National Zoo and Kampung Kemensah?

Deputy SpeakerEN

Paya Jaras, please.

Tuan Mohd Khairuddin bin OthmanPKR · PHPaya JarasEN

That is a very good view from the Honourable Member for Hulu Klang. In other words, open it to the public, but I think this matter we should discuss with MPAJ, because they are more focused on developing human capital among government employees. For the Honourable Member's information, these centres are maintained by MPAJ. However, we will discuss with MPAJ the proposal of the Honourable Member from Hulu Kelang.

Dusun Tua also raised the mechanism for attracting youth in Selangor. I am confident that most of the Honourable Members present in the House today face a great challenge in reaching out to youth. We have 10 core policies, which were brought by our PEBT, and the Honourable Member still sees that there are still areas we can improve. Perhaps I would like to suggest to all Honourable Members that the trend now has changed.

I heard the debate from the Honourable Members, and some among the Honourable Members raised why this PEBT focuses only on sports, because that is one of the core pillars we have in our 10 policies. But I also liked listening to the debate and

the answer from the Honourable Member for Batu Tiga, who mentioned that there is now what is called the Gig Economy, which is a free economy; these youths do not want to be tied down, they prefer to seek non-permanent, free work. They deliver food, Food Panda and so on, and Grab. This is the trend that exists today.

This means that today's economy has moved from the traditional economy to the Gig Economy. The same goes for our youth. If we remain with traditional approaches, the answer is the same: the result we get is that not many youths are interested. That is why I would like to offer a suggestion to the Honourable Members. Try to find other ways in line with the trend. If the economy has the Gig Economy, our youth are referred to as an independent group, and these are the people we must reach out to, whether through entertainment, through sports, or in various other forms. I want to say to all Honourable Members that when we carried out the Selangor SYR programme recently, among the many programmes we implemented, we had concert programmes, we had sports programmes, strongest man, retro run, E-games, fitness, skateboard, fun run, netball, penalty shoot, job fair, drug-free workshops, and we also held lifestyle programmes, motorcycle and car exhibitions, food trucks, corporate exhibitions.

Among all the programmes we implemented, the one with the largest attendance, which nearly reached 10,000, was the concert we held. This is the trend among youth. First, concerts. I would like to take a lesson from when the Honourable Member for Sijangkang became EXCO for Youth and Sports, and he organised, with permission, I stand corrected if my definition is wrong, what replaced the Selangor State Youth and Sports Day, the State Youth Day held at the Seksyen 7 Cultural Centre. The attendance we recorded at that time was only around 150 to 200 people, correct, Honourable Member? Only that much at that time, why? Because at that time the Selangor Youth Day was served with motivational speeches, motivational talks, and youth did not want this. This is the real answer. If Selangor does not take the stance of openness involving youth as independent groups, or what is now called Indie Groups, then if we remain with our traditional approach, the answer, Honourable Member, will be the same result, and the same, and the same. That is why, Honourable Member,

Boleh mencelah?

Tuan Mohd Khairuddin bin OthmanPKR · PHPaya JarasEN

Of these many programmes, the one that people did not attend at all that day was the drug-free workshop, with 250 people.

Deputy Speaker

Paya Jaras.

Ya sila.

Deputy SpeakerEN

Dusun Tua wishes to interject.

Thank you, Honourable EXCO. I indeed agree with the current trend, where, if we look at the commitment of young people to associations, organisations and so on, it is indeed quite loose. I often joke, I say, if now we want to commit to a partner it is already difficult, let alone commit to an association. So the trend now is

indeed like that. But among young people who tend to be independent, we can also see that when they want to gather, they usually form collectives, which are gatherings that are not so tightly bound, more flexible and adaptable. So we can see these collectives sprouting like mushrooms everywhere.

So what method can we use to tap into these collectives? Do they have the opportunity to access allocations, state government funds and so on? Because I believe these groups may not have registered organisations, but they move as groups and carry out activities as groups. If I may give an example, like in the past, in my time, long ago, like street books and so on. And now, I too may have new collectives emerging, moving according to their own interests, and perhaps each has its own crowd. So do these groups have access to state government funds and so on? So what method do we have to reach out to these groups? Thank you.

Tuan Mohd Shaid bin RosliBERSATU · PHJeram

Boleh tambah?

Tuan Mohd Khairuddin bin OthmanPKR · PHPaya JarasEN

Let me answer this question.

Deputy SpeakerEN

Paya Jaras, please.

Tuan Mohd Khairuddin bin OthmanPKR · PHPaya JarasEN

So that the answer is more focused. The answer indeed lies in the hands of all Honourable Members. At state level we are only policy makers, and of course our policies are made in accordance with the rules and regulations we have, but the openness of the Honourable Members at the State Assembly level plays the main role. I believe many of our youth approach all the Honourable Members, but if we mention which association, which organisation, what type of organisation, they will gradually run away.

For the information of the Honourable Members in the State Legislative Assembly, I want to take the information available in Indonesia. In Indonesia, the mainstream of all Honourable Members, music, mainstream music, compared with music referred to as Indie now, Indie music is more popular than mainstream music in Indonesia. This means that a time will come when our youth will go to activities that are not tied to formal forms, protocol forms, or bureaucratic forms. But they exist within our state. I take the data I mentioned yesterday: we have 2.9 million youth up to the age of 40. There are 1,300 registered associations under the Ministry of Youth and Sports, but only 100,000 youths are in those associations.

So I would like to return to what the Honourable Member for Dusun Tua said. I indeed hope that after this we will have a more open policy towards these youth groups who are considered not wanting to be tied down, and we will study how this changing trend can help Selangor keep up with developments. We have already, we must change from the traditional approach to a more open approach now. And indeed, as Dusun Tua mentioned, Honourable Member,

Deputy SpeakerEN

Paya Jaras, Seri Setia wishes to interject.

Ya.

Tuan Halimey bin Abu BakarPKR · PHSeri SetiaEN

Thank you, Honourable Deputy Speaker. Honourable EXCO, I agree with what the Honourable Member has stated, that concerts are an attraction for youth to come, to be present, to be together. If we run programmes like briefings or ADK talks, attendance will be low. There are youth, I just did one recently too, and there were youth, but few. But at a concert we can include that element. Secondly, we have arts cities, yes, namely the PBT in MBPJ and MBSA, which the state government has recognised as arts cities, yes. So I, I would like, if possible, I would like to submit a request and a view to the State Government to help them, or these PBTs, to organise concerts. I take the example of the Petaling Jaya City Council, which every year holds the PJ Fair, in which it holds a concert, and at the end there are very outstanding artistes. And I have seen for myself that many youths come and there is a lot of content there. Only, when there are artistes, if we want to attract youth to come and watch the performance of these artistes, the artistes we invite must be popular, outstanding, and the cost is high. That is what is needed, I suggest, there needs to be assistance also from the State Government. And one more thing, if we look at young people today, if concerts are held at Stadium Malawati, I take that as an example, the ticket price may be expensive. They may not be as many as those outside, like in our funfair days in the past, the funfair era, indeed young people. Nowadays that era has come back. So, I suggest that if possible the State Government can help to further encourage this industry.

Tuan Mohd Khairuddin bin OthmanPKR · PHPaya JarasEN

Thank you, yes, I strongly agree. We must choose artistes who have followers. Honourable Members, try opening the Instagram of political figures and compare it with Instagram, political figures are leaders at Federal and State level, and Honourable Member, open the Instagram of our artistes. Our artistes have followers of 1 million, 1.5 million, extraordinary. So, in other words, the trend that exists today is that our youth refer more to artistes than to political figures. This is the reality we have to face. And InshaAllah Honourable Member, the Butterfinger concert that we held at Stadium Malawati was done in cooperation with us, so that we could show that we are open to music. We are open in a situation where we control them. So, InshaAllah in the coming years we will hold more programmes of a kind that can attract our youth. And that is why, Honourable Members, among the changes we will make to the New Year celebrations this year is that we want to open it up somewhat in the form of a carnival. Please go ahead.

Deputy Speaker

Silakan Meru.

I want to interject briefly. Okay, perhaps I want to interject a little. Thank you to Madam Deputy Speaker. I want to ask the Honourable EXCO regarding these concerts. I am afraid we will be misunderstood as wanting to become an entertainment state. So, how, in our situation, yes, Islam does not reject entertainment, but at the same time we want to protect our young people from being caught up in unhealthy trends. And, most of them,

if we look, these concerts are exposed to negative matters. Is it merely that we want to provide entertainment there, or do we want to create a new culture, merely to follow the mainstream, the wishes of teenagers or our young people, merely to liven up the event, without us considering the negative aspects that could arise because of the new culture that we want to introduce? Because, for me, if it is merely for entertainment, to make young people happy, I disagree somewhat with that situation, unless there is content or a new approach, a good one, that we can bring to our young generation. Thank you.

Tuan Mohd Khairuddin bin OthmanPKR · PHPaya JarasEN

Do not sit down yet. I want to ask the Honourable Member.

Tuan Mohd Khairuddin bin OthmanPKR · PHPaya JarasEN

Honourable Member, what is your view on youth who like this music? Do you look at them with disgust or how?

No, I have already said just now that Islam does not reject it, and indeed I myself also ..

Tuan Mohd Khairuddin bin OthmanPKR · PHPaya JarasEN

But the Honourable Member said just now that you did not agree. Where is your disagreement?

I do not agree if it is merely for entertainment.

Tuan Mohd Khairuddin bin OthmanPKR · PHPaya JarasEN

So, the Honourable Member does not agree?

Tuan Mohd Khairuddin bin OthmanPKR · PHPaya JarasEN

So, my question to the Honourable Member is, what is your view towards the youth who like this music?

Okay, we can .. we can allow..

Tuan Mohd Khairuddin bin OthmanPKR · PHPaya JarasEN

If we may allow.. sit, sit

Deputy SpeakerEN

The EXCO must answer the question..

Tuan Mohd Khairuddin bin OthmanPKR · PHPaya JarasEN

That is why, Honourable Member, so you agree that we must reach out to these youth, correct?

Tuan Mohd Khairuddin bin OthmanPKR · PHPaya JarasEN

Okay, sit down. Let me answer.

It is not fair to answer like that only!

Tuan Mohd Khairuddin bin OthmanPKR · PHPaya JarasEN

That is not right. (Members of the House laugh)

Let us also be allowed to explain.

This is my, ini floor saya

Tuan Mohd Khairuddin bin OthmanPKR · PHPaya JarasEN

This is my floor. (EXCO laughs)

I have to give an explanation, because we do not want to create

Tuan Mohd Khairuddin bin OthmanPKR · PHPaya JarasEN

Because the Honourable Member gave the impression that there are youth whom we consider good, and there are youth who are problematic. Does the Honourable Member look at some youth with disgust, is that so?

Tuan Mohd Khairuddin bin OthmanPKR · PHPaya JarasEN

Does the Honourable Member mean that?

I do not mean that. But when we only see it focused like this, we need to understand, so that we do not end up like yesterday when the headline comes out again, this news.

Tuan Mohd Khairuddin bin OthmanPKR · PHPaya JarasEN

No, that is a different matter. This is about the youth, Honourable Member.

Cerita belia.

Later it will become glamorous. Ha, yes.

Tuan Mohd Khairuddin bin OthmanPKR · PHPaya JarasEN

So, no, like this. The Government side, whether the youth are good people, or ..

Asked to stand again?

Tuan Mohd Khairuddin bin OthmanPKR · PHPaya JarasEN

(Laughter). You may sit. Ha, now you may sit. I .. (laughter). In our view, Honourable Members, whatever the condition of the youth in Selangor, they are our people's youth in Selangor. (Members thumped the table). We cannot say, 'oh, these are youths who are interested in religion', so we approach them, and those who are interested in things that are rather wild we leave behind, that cannot be done. We must look after drug addicts, we must look after those with social problems, we must look after good people too. Because we are the Government!

No, as I have informed, I did not object and I have already explained earlier, Islam does not prohibit entertainment, but I gave a reminder so that we can control matters that may give rise to an unhealthy culture.

Tuan Mohd Khairuddin bin OthmanPKR · PHPaya JarasEN

That is right, Honourable Member.

That is my purpose.

Tuan Mohd Khairuddin bin OthmanPKR · PHPaya JarasEN

We have rules in our PBT. We have our laws. We have guidelines that we uphold. But we must approach our youth. Surely we have learned how preachers went into places like nightclubs, I am not telling you to go into nightclubs, Honourable Member, but this is approaching. Approaching. Later it is wrong, Berita Harian will misquote me. All Honourable Members go into Berita Harian. No, no. I'm telling you, what I mean is the openness of our State of Selangor. Selangor is not like Kelantan. Kelantan is not Selangor. Selangor is not the North, the North is not Selangor. We are Selangor! Selangor has its own approach. That is why, if the Honourable Member, if, I can imagine if the Honourable Member Meru did it, like surfing. Do you know surfing? Surfing Club.

If you do that it will shock people later.

Tuan Mohd Khairuddin bin OthmanPKR · PHPaya JarasEN

(Laughter) If the Honourable Member does that, I am afraid you will fall down. However, Honourable Member, the statistics of our experience show that if Honourable Members feel that our Youth Programme is very cold, then it must be mixed with sports elements, have a bit of entertainment, a bit of running, a bit of cycling, InshaAllah I am confident the Honourable Member is on the right track. But let us take care. Let us look after it.

Next, Sijangkang raised the issue of allocation for the young generation. I do admit we have limitations in our allocation, however, we thank the Honourable Members who have understood that among the constraints we have is a rather modest allocation for the generations, but nevertheless, I hope in future we will get help from the Honourable Members themselves to assist us, so that we can run programmes that we feel are suitable. I move on to the matter that was raised by the Honourable Member Banting, the Honourable Member Banting is not here today. Ha, he has just come in. Feedback means the participation of Malaysians in World Skill is low. Perhaps Inspen, Inpens can help. The State Government under the Human Capital Development Committee has made plans in cooperation with the Most Honourable Member under the Education Portfolio to implement the World Skill of Selangor skills programme in 2020. To ensure the implementation of this programme is more effective and comprehensive, the State Government will cooperate with the education industry of the State of Selangor, namely Inpens (Inpens International College), Universiti Unisel, Selangor Human Resources Development Centre (SHRDC), and the Ministry of Human Resources and relevant departments or agencies to make this programme a success. So, perhaps among the Honourable Members there is a question of what World Skill is? What is World Skill? As a simple analogy for us to understand, in sports, the pinnacle of the biggest carnival in athletics is the Olympic Games. The greatest pinnacle for football festivals is the World Cup, and the greatest pinnacle for this TVET programme is World Skill, World Skill itself. So, when World Skill, it invites many countries, the latest was held in Russia, in Kazan. So, the countries that send representatives, including Malaysia, in which there are also children of Selangor. I did not get the actual data as Banting did, perhaps this data, they are from private institutions or the like, but this is the World Skill that we are trying to bring and hold in our State of Selangor.

Tuan Lau Weng SanDAP · PHBantingEN

Yes, thank you. In my speech a few days ago, I mentioned that the two (2) bronze medal winners from Malaysia were from private universities that are engaged in TVET studies, and in the competition mentioned by the Honourable EXCO, countries such as Taiwan and China won five (5) or up to four (4) gold medals, but from Malaysia, we only got two (2) bronze medals, and of those two (2) bronze medals, both were not from Selangor. They were not from Selangor, and they did not originate from INSPEN colleges or vocational colleges in Selangor, they were from the private sector. So, this shows there is a need for the Government to focus, allocate and also provide more resources to ensure that from Selangor, especially from Inspen, we can send at least participants to take part in this World Skill competition, and at the same time uplift the good name of Selangor and the good name of INSPEN. So, that is my suggestion and I hope more allocation can be made for next year if possible. Thank you.

Tuan Mohd Khairuddin bin OthmanPKR · PHPaya JarasEN

Thank you, Honourable Member Banting. I believe the Most Honourable Dato' Menteri Besar has on several occasions mentioned the priority and focus on this TVET, and it would be better for us to hear the answer from the Most Honourable one later on the direction of education itself, including empowering our younger siblings, our youth in the skills we mentioned earlier. Then, I move on to Kota Anggerik who mentioned the monitoring of our youth. I would like to remind again that the monitoring process of our PEBT is carried out by the Honourable ADUNs. That is why, if the Honourable Members look again at the form submitted by our PEBT, to release the money itself or to carry out the programme itself, it must get the endorsement of the Honourable ADUN Members. So, as mentioned by Kampung Tunku earlier, Bandar Utama earlier, who said that the ADUNs, if the Honourable Member feels the programme does not have impact, do not sign. If the programme has impact, sign. So, the Honourable Members themselves are the entities that monitor our PEBT. So, I will take into account what Banting mentioned regarding the audit of our PEBT, InshaAllah, from time to time, we will improve on whatever weaknesses we have.

Tuan Halimey bin Abu BakarPKR · PHSeri Setia

Tambahan.

Seri Setia.

Deputy SpeakerEN

Please, Seri Setia.

Tuan Halimey bin Abu BakarPKR · PHSeri SetiaEN

Thank you, Deputy Speaker. Honourable EXCO, the matter of PEBT, as I brought up in my previous debate, what is sad, I want to suggest that there be a course or a motivation programme can be held for them. And there is PEBT, what is sad, when I asked the name of the Menteri Besar, he did not know. I asked the name of the EXCO too, he did not know. Sorry, not the YB EXCO for Youth, I tried to test him, with permission, I asked the name of the EXCO of the Selangor State Government too, he did not know. This is what saddens us. That means, their knowledge is lacking.

Tuan Mohd Khairuddin bin OthmanPKR · PHPaya JarasEN

Did the Honourable Member ask there for the name of the ADUN too? (Laughter)

Tuan Halimey bin Abu BakarPKR · PHSeri SetiaEN

He wants to sign, so he knows, lah.

Tuan Mohd Khairuddin bin OthmanPKR · PHPaya JarasEN

I am worried if the name of the Honourable ADUN too .. (laughter). Yes, yes. For the information of the Honourable Member, we have that module. We have modules to empower our PEBT, not only in terms of knowledge but we also have modules on self-presentation, attire, speaking style and so on. So, InshaAllah, give us some time and we will review our modules so that we can, produce a more empowered PEBT. Taman Templer mentioned about upgrading. Yes, I recall that in the previous session there was mention of the status of upgrading for the Kampung Melayu Batu 16 Rawang football field, Honourable Member. Yes, yes, in fact we have, Selayang Municipal Council has already sent us the proposal. InshaAllah we will ensure that the Honourable Member will get that field later, Honourable Member (laughter). Bandar Utama mentioned about effectiveness, I think I already mentioned about programmes, effectiveness or otherwise depends on the programmes and initiatives of the ADUN side itself.

And Sungai Panjang mentioned about engagement with associations and the centre of excellence mentioned earlier. I understand that the Honourable Member for Sungai Panjang has a view that our youth can work with the Department of Youth and Sports or through associations. I think this is a good view although the PEBT we will not unite them. But that cooperation we will continue to encourage them. Therefore, Honourable Member, for the information of the Honourable Member from Sungai Panjang. At the State level now, we are not only cooperating with MSN but we are also cooperating with the Department of Youth and Sports at the State of Selangor level. We have that engagement now. And finally, regarding Startup Excellence Saya, may I give it in writing? Because this is more specific. I did not get the detailed information. Thank you, Deputy Speaker.

Deputy SpeakerEN

Thank you, Paya Jaras. Next I invite Lembah Jaya.

Puan Haniza binti Mohamed TalhaPKR · PHLembah JayaEN

Thank you, Madam Deputy Speaker. I only have one or two matters raised by the Honourable Member for Kota Damansara relating to the issue of offering Rumah Selangorku to the squatter settlement of Kampung Bunga Raya. So, Honourable Member, the State Government, through the Selangor Housing and Real Estate Board, actually has no obstacle to offering Rumah Selangorku to these former squatters and also to the squatter families involved in Kampung Bunga Raya, Sungai Buluh. However, they need to obtain written confirmation from the Honourable ADUN of the constituency, confirming that they are truly families of squatters from Kampung Bunga Raya. After obtaining that confirmation, we will submit their names to the Name List Selection Committee Meeting for endorsement and then be forwarded for approval by the Honourable Dato' State Secretary. So I, and it must be reminded that all offers of Rumah Selangorku are according to the conditions that we apply. So, InshaAllah, if they fulfil all the conditions, they will be offered Rumah Selangorku units.

For the information of the Honourable Member for Kota Damansara, there is actually a project under way on the outskirts of Subang, Seksyen U5, a Rumah Selangorku that is under construction. This was originally an abandoned project but, InshaAllah, it is in the process of being revived. It is already 90% complete. It is only waiting for the title to be separated for the land boundary of two blocks there. So, these may be the units that can be offered, because it is quite near. Another issue raised by Kota Damansara is the resolution of the settlement of former Subang estate workers. This is also necessary, we can offer through the Selangor Housing and Real Estate Board, it only requires that the names of these estate workers be submitted and approved by the STANDCO Ladang. So, I hope the Honourable Member can help them go through this process, and STANDCO Ladang needs to confirm these names, and we will receive these names through the usual process, enter them into the meeting and forward them directly for endorsement and approval by the Honourable Dato' SUK.

Deputy SpeakerEN

Please, Kota Damansara.

Tuan Shatiri bin MansorPKR · PHKota DamansaraEN

Thank you, Deputy Speaker. Before the new Government, this Subang estate was promised by the developer. There was an agreement, there was a contract. That was Rumah Murah. Not Rumah Selangorku, Rumah Murah. And they have already been given forms and there was an agreement to offer them houses. About 40 Indian families there, more or less. I was given to understand that the project has been cancelled. For the Damai Suria project, by the contractor developer Titi Jaya. So, I also do not know why when the Government changed, the project was cancelled. I do not know why. So I ask the Government side to intervene again so that we continue the Rumah Murah project. And these people have been waiting at that place because that is where they live, were raised, and they hope for the land that had been taken by the developer to develop and promised Rumah Murah, suddenly it was cancelled. So I hope the Government side will step in on this matter so that we can resolve it. That is one matter. On the matter of that house in the long term. Even now, there are still problems involving the developer and residents, TNB and Air. So, I hope I too will go down often to ask for help so that it can be resolved. So there is an issue actually. And I am concerned that tension will arise to the point that the project cannot be continued and so on. Thank you.

Deputy SpeakerEN

Please, Lembah Jaya.

Puan Haniza binti Mohamed TalhaPKR · PHLembah JayaEN

For the information of the Honourable Member for Kota Damansara, we have actually also made a check on the developer who was said to be going to build these low-cost houses for estate workers. The developer in question is Titi Jaya Land Berhad. In our check, we did not receive any application. And when there is no application, there is no cancellation of any project. So that is the doubt we have. If it is said that the project has been cancelled, in our records there is none. However, I ask the Honourable Member for Kota Damansara to bring this matter up, to present this matter in another meeting. Together with the Selangor Housing and Real Estate Board. OK. Thank you.

Deputy SpeakerEN

Next, thank you, Lembah Jaya. Next, Seri Serdang.

Puan Dr. Siti Mariah binti MahmudAMANAH · PHSeri SerdangEN

Thank you, Honourable Madam Deputy Speaker. I will answer several questions raised by our ADUNs. Thank you all. The ADUN for Bukit Lanjan asked for feedback on dengue. For the information of the Honourable Members, beginning in 2018, the State Government disbursed a total allocation of RM1,248,000.00 to each Councillor in every Local Authority (PBT) for dengue prevention and control activities. The breakdown of the allocation is RM5 thousand for each Councillor in PBTs with City Council and Municipal Council status, while RM3 thousand is for each Councillor in PBTs with District Council status. In addition, allocations were also given to the PBTs and District Land Offices as follows: PBT allocation apart from the Councillors' allocation, RM1,200,000.00. Allocation to the District Land Office, RM350,000.00. Appointment of Pest Control Operators (PCO), RM1,890,000.00, and promotional campaigns amounting to RM52,730.00.

Also in 2018, through MMKN decision No. 34/23/2018, it was decided that every State Assemblyperson must utilise the Community Service allocation of RM10,000.00 for dengue control and prevention activities in their respective areas, based on the guidelines distributed through the PBTs. I recall that this is the allocation the YB/ADUN used to purchase those mosquito magnets. The one who said that. For 2019, the State Government continued to maintain the same allocation, namely RM1,248,000.00 to the Councillors in every PBT. Given that the allocation for dengue control and prevention activities has been increased to RM5 million in 2020, the State Government will consider applications from any State Assemblyperson who requires additional allocation to carry out these dengue prevention and control activities.

Next, regarding the question from the Honourable Member for Bukit Lanjan on the Women's Health Scheme, which was allocated RM700 thousand for 2020. Honourable Member for Bukit Lanjan, for your information, the RM700 thousand allocation mentioned is solely for the Mammogram screening programme. It is free of charge and does not include other health programmes. I would also like to inform this august House that, up until August 2019, a total of 4,091 women had participated in this programme, bringing the overall total of participants to 50,044 women in Selangor who have benefited from this free Mammogram screening since it was introduced in 2010.

Next, Bukit Melawati, the Honourable Member for Bukit Melawati asked about gender mainstreaming. Honourable Deputy Speaker, as I have informed in the previous winding-up session, in line with the objectives of the Sustainable Development Goals (SDG) 5, 10 and 16, namely achieving gender equality and empowering women and girls, reducing inequality, and peace, justice and strong institutions, which are consistent with the expression of Smart Selangor 2025, the State Government is committed to implementing gender mainstreaming (GM) beginning in 2020. The implementation of GM is enshrined in the first objective of the Selangor Women's Policy itself, namely to encourage a gender-sensitive development framework. Gender mainstreaming is the most important strategy to ensure gender-responsive development in order to achieve the objectives of gender equality and women's empowerment. This is a strategy to ensure that the interests and experiences of women and men become a core dimension in the planning, implementation, monitoring and evaluation of policies and programmes in State administration.

GM is important to be implemented to ensure that the issues of gender equality and women's empowerment remain relevant and always become a priority in every planning, including policy formulation at the State Government level, through processes such as gender audits, gender responsive budgeting and gender action plans. The gender action plan that will be produced, God willing, we will begin with 3 pilot EXCOs in 2020. This will include proposals on how gender perspectives and targets can be integrated into all planning and budgets of departments and agencies. It will be implemented with an emphasis on sex disaggregated data (SDD), which will play a key role in this matter. This framework is very important because it can provide benefits not only to women, but is also inclusive of men and all groups in society. It is also consistent with the 3 dimensions of the Twelfth Malaysia Plan.

Kampung Tunku, the Honourable Member for Kampung Tunku asked about pap smear and HPV screening. For the information of all the Honourable Members, at this time the State Government does not yet have any special allocation for pap smear screening programmes or HPV injections. However, under the National Population and Family Development Board (LPPKN), there is a pap smear laboratory service, LPPKN, implemented for early screening to prevent cervical cancer. At LPPKN, pap smear services can be obtained at all LPPKN Klinik Nur Sejahtera, while at LPPKN Selangor, they can be obtained at Klinik Nur Sejahtera Shah Alam, Ampang, Klang, Kajang and Selayang. Apart from that, they can be obtained through the outreach service of the Mobile Family Centre Bus. I suggest to the Honourable ADUN that if you wish to focus on the people within the Honourable ADUN's area, please contact LPPKN because they have an outreach service. For the information of the Honourable Members, the minimum fee charged under this package is RM25 for obtaining the Pap Smear Test, Glucose Cholesterol Wellness Screening, BMI Check and Blood Pressure Check. So this is RM25 for the tests just mentioned. For pap smear outreach services, they can be carried out through the Mobile Family Centre based on invitations and programme cooperation with agencies, departments, NGOs, the private sector and the ADUN Service Centre that I mentioned earlier. Regarding HPV vaccination, the Federal Government has continued to provide free HPV vaccines to female Form One students in secondary schools, where the vaccination is administered by Medical Officers from the District Health Office for 13-year-old children, while 13-year-old girls who are not in school can obtain it at the Health Clinic, yes. And, all the Honourable Member's proposals on this are good. Indeed, the Selangor State Government always considers and deliberates on them, but everything must be in accordance with the State's financial capacity, yes. Every programme that we want to organise or add to the existing programmes must also consider sustainability or the sustainability of the programme.

Alright, the question I recall most, I think I received, is about the Skim Mesra Usia Emas (SMUE), yes. The realignment of the Skim Mesra Usia Emas that was carried out in early 2019 is intended so that the benefits are given to members who are still alive. As I explained this morning, yes. Therefore, if the benefits are given to heirs, Dusun Tua, I recall suggesting that if possible, it be given to the heirs in case they did not have a chance to go shopping, yes. But, meaning that if we give these benefits to heirs because the senior citizen has passed away, then the main objective of the benefit is not achieving the true aim of this programme. The Honourable Member for Sentosa asked why the programme was stopped? Is it because the money has reached the allocation or is it insufficient? To answer this question, Honourable Member, I would like to state that previously we spent, let me give these statistics, from 2016 RM28,800,000.000 for the Skim Mesra Usia Emas, which was formerly known as Khairat Kematian. Then RM27,365,000.00 in 2017, and then 2018 RM28 million for 2000...for 2018. All of these have been disbursed to the District Offices. If we look here, Honourable Member, the allocation for 2019 that was approved for 2019 is only RM7,590,199.00. And, the estimated deaths up to 30 April 2019, just recently, we have RM22,346,500.00 there, and the Jom Shopping Vouchers from September to December are estimated at RM13,400,000.00. And, when we add up all the required allocations, it comes to RM35,746,500.00, far higher than Khairat Kematian three years before, yes. And, the additional allocation that we approved during the last State Assembly sitting, amounting to RM28,000...RM28,156,301.00, still needs to be added for us to implement the SMUE Jom Shopping programme, yes. So, it is not true if we say that we want to do this because we are afraid or because we have run out of money, yes. But we want to see it reach these senior citizens. For the information of the Honourable Member, originally the proposal to give Jom Shopping was only up to the age of 74, but all the EXCOs objected, saying that if we want to do Jom Shopping, we must give it until they pass away. So, that means the commitment of the Selangor State is far higher than what we have spent on Khairat Kematian. Because we want senior citizens to feel it while they are still alive. For everyone's information, the Selangor State Statistics, yes, in 2019 we have 544,400 senior citizens, aged 60 and above. So, if all of them register, Honourable Member, then the government must provide about RM50 million more than what we used for Khairat Kematian. But we feel it is worthwhile because it goes to the senior citizens. That's it...yes, YB.

Alright...The Right Honourable...The Honourable Member for Sentosa also asked about the chronology of the implementation of this SMUE programme. The Khairat Kematian Scheme (SMUE) was launched in August 2008. The announcement regarding the Khairat Kematian Scheme was made...the announcement not to continue this Khairat Kematian was made by the Right Honourable Dato' Menteri Besar on 26 April 2019, yes. So, the Khairat Kematian (SMUE) Programme was stopped at the end of 30 April, yes. And, the last claim or submission for deaths on 30 April and before is 30 May. So, the SMUE Scheme, whether Khairat Kematian or Jom Shopping, does not exist between the months of May, June, July and August. Four months without it while we realign and we start with Jom Shopping from 1 September, Honourable Member for Sentosa, yes. So, this is what was asked about SMUE. I just want to show here, suggesting to the ADUNs that we encourage Muslims, as almost all mosques have Khairat Kematian. With a small payment, they can receive the full benefits of Khairat Kematian from...from the mosques. However, I admit that for our Indian community, we do not have Khairat Kematian. So, perhaps Indian community leaders can propose to the temples, and other places of worship as well, to start a Khairat Kematian Scheme for...what do people say...those of the same faith. So, with that, we have also proposed that for the B40 group, if there are those who pass away and their family is poor, the ADUNs are advised to take from their allocation to help them overcome the problem of burying the deceased. I think that is all my answer, thank you.

SpeakerEN

Thank you, Seri Serdang. Anyone else? Yes, I invite Kajang, the Honourable Member for Kajang, EXCO.

Tuan Hee Loy SianPKR · PHKajangEN

Thank you, Mr Speaker. The Honourable Member for Bukit Lanjan has asked whether the Department of Wildlife and National Parks (PERHILITAN) received any allocation under the Environment Programme? For the information of the Honourable Member, PERHILITAN is a member under the Standing Committee on Environment. Every year the State Government disburses allocations to PERHILITAN. The allocation in 2016 was RM101,800.00. In 2017, RM111,000.00 from the allocation, and in 2018, RM182,000.00 was allocated. Meanwhile, in 2019, this year, the State Government has already disbursed a sum of RM230,000.00 to PERHILITAN for the purpose of Wildlife Conflict Areas, namely RM80,000.00, World Tapir Day Carnival RM50,000.00, and also upgrading the facilities of the Wildlife Conservation Centre and the Sungai Dusun Wildlife Reserve Environment RM100,000.00.

The Honourable Member for Bukit Melawati has raised the proposal to implement a recycling centre in the State of Selangor. For the information of the Honourable Member, the State Government intends to establish a comprehensive recycling centre, including for processing purposes, in all PBTs in line with the concept of the circular economy, or circular economy, namely waste to wealth. Therefore, all PBTs in the State of Selangor will identify strategic locations to ensure that the establishment of recycling centres achieves its objectives. For the initial stage, this recycling centre will operate as a waste collection point, serving only as a source-based waste disposal approach to reduce waste disposal costs at the disposal site. This project will indirectly improve the effectiveness of solid waste management, in addition to reducing the generation of carbon dioxide. The implementation of this recycling centre can become a catalyst towards the well-being of the environmental community through direct public participation in waste management, where residents will be educated to be more responsible in managing daily waste and also to practise the 3R concept, namely Reduce, Reuse & Recycle, which indirectly educates residents to reduce the production of waste through reuse and recycling.

Thirdly, last...the Honourable Member for Kampung Tunku has also raised the matter of the allocation under the Standing Committee on Orang Asli Affairs in 2020, which is too small, namely RM500,000.00. So, for the information of the Honourable Member, Orang Asli Affairs fall under the jurisdiction of the Federal Government, namely under the Department of Orang Asli Affairs (JKOA), where JKOA itself receives its allocation from the Centre. Nevertheless, out of the State Government's concern for the Orang Asli community, in 2020 a Standing Committee on Orang Asli Affairs will be established, and a sum of RM500,000.00 has been allocated for the purpose of human capital development and welfare of the Orang Asli, compared to only RM100,000.00 in 2019. With the establishment of this committee, it is hoped that it can help drive closer cooperation with the Federal Government to raise issues relating to the Orang Asli in the State of Selangor. Thank you.

SpeakerEN

Yes, thank you, the Honourable EXCO Member for Kajang. Now I invite Kinrara.

Tuan Ng Sze HanDAP · PHKinraraEN

Thank you, Mr Speaker. I would like to begin with the question raised by the Honourable Member for Bukit Lanjan. Mr Speaker, the Honourable Member for Bukit Lanjan raised matters relating to the PK.12 allocation, namely the Conservation of Solid Waste Disposal Site. For 2020, this allocation has been placed under the PK.19 allocation, namely Miscellaneous Vote, yes. But it is placed under Miscellaneous Vote, PK.19, nineteen. OK. To answer the question raised by the Honourable Member for Gombak Setia, who raised the monopoly of KDEB Waste Management Sdn. Bhd. in solid waste management and the contract period of up to seven years. For the information of the Honourable Member, prior to the takeover of KDEB Waste Management as the solid waste management company, the appointment of waste collection contractors was carried out by the Local Authority, with price evaluation selected through open tender at the lowest price, and the contract period given was two or three years. The effect of the short contract period and low price was seen as a weakness in terms of investment by contractors, where contractors could not purchase new assets such as lorries and compactors. Therefore, the lorries used by contractors were old lorries, causing collection schedules to be disrupted due to broken-down lorries and so on. In addition, there were compactor lorries operating in different PBT areas at the same time because the company owner obtained contracts in other PBTs. For new contractors who obtained contracts, it was found that they only rented lorries from companies that had many lorries, causing the contractors' operating costs to increase. This problem caused complaints received by the PBTs, such as rubbish not being collected, collection not being on schedule or the like, to increase. Therefore, the State Government, through the 7th MMKN of 2016 on 24 February 2016, which was endorsed by the 8th MMKN of 2016 on 2 March 2016, agreed to establish a PMC owned by the State Government, namely KDEB Waste Management, as the manager for the implementation of integrated solid waste and public cleansing services. And, Klang Municipal Council was chosen as the pilot project. The State Government also agreed to adopt this model across all PBTs in Selangor if the implementation of this PMC succeeds in MPK. Based on that decision, PMC operations have been expanded to 11 PBTs until today. And, the State Government has given a period of up to seven years...

SpeakerEN

The Honourable Member for Kinrara, please sit down for a moment. Honourable Members, as the business of this House is still lengthy, the House today needs to be extended. I invite the Right Honourable Dato' Menteri Besar to move the Motion.

Tuan Amirudin bin ShariPKR · PHMenteri Besar · Sungai TuaEN

Mr Speaker and Honourable Members all. I would like to move a Motion which reads as follows. Whereas, the House sitting today, pursuant to Standing Order 11 and the Standing Orders of the Selangor State Legislative Assembly, shall be extended until 5.30 p.m.

Dato’ Teng Chang KhimDAP · PHBandar Baru KlangEN

Mr Speaker, I second the motion.

SpeakerEN

Honourable Members, this motion has already been seconded. I put it forward for approval. Honourable Members who agree, please say YA. Honourable Members who do not agree, please say so. No. This motion is agreed to. Honourable EXCO, please proceed. Kinrara.

Tuan Ng Sze HanDAP · PHKinraraEN

The State Government has given a period of 7 years for the implementation of PMC to allow new assets such as new lorries and compactors, and system development, to be invested in by a PMC-type company owned by the State Government, with the aim of managing and operating refuse collection services. For the information of the Honourable Member, the implementation of this PMC is not seen as a monopoly, because there are as many as 1000 companies or contractors operating under the umbrella of KDEB Waste Management. In fact, KDEB Waste Management has helped many small entrepreneurs in the solid waste industry and has been able to change the landscape of solid waste assets in Selangor, and through this capital the State Government has succeeded in creating opportunities for 1000 companies to remain active in solid waste collection and public cleansing. However, the monitoring carried out by KDEB Waste Management is very strict against any company with performance problems; to date, KDEB Waste Management has terminated 11 contractors on account of unsatisfactory performance. To answer the question from the Honourable Member for Balakong regarding the welfare of stray animals. Through the 2019 budget, the Most Honourable Dato' Menteri Besar...

Tuan Muhammad Hilman bin IdhamBERSATU · PNGombak SetiaEN

Regarding KDEB Waste just now, I would like an explanation, because I think what the Honourable EXCO has just said is true, that our original idea was to ensure that cleanliness and solid waste collection take place in good condition. That is why we set up the original idea of KDEB, using a pilot project in Klang, and we asked KDEB Waste to assist several local authorities (PBT) as a safeguard, especially to ensure cleanliness, and when contractors appointed by the local authorities fail, KDEB Waste steps in. But in the present situation, what I raised yesterday is what the State Government's position is and what steps the State Government will take when KDEB Waste itself has unsatisfactory performance and attracts objection or criticism among the State Assemblymen (ADUN) and also Council Members. Furthermore, I think, if the Honourable Member mentioned just now is correct in terms of the debate, when I began yesterday with the debate, we can speak only of beautiful things in this House. We can say we help 1000 entrepreneurs, 1000 new companies and so on, but the reality on the ground that I want to raise is that among the companies that receive contracts from KDEB, some in the end are unable to carry out the work to the standards provided by KDEB, and in the end they sub-contract to other companies. This is what I referred to as the culture of subbing and sub-subbing to a second, third and eventually further level, which causes wastage because the performance is not satisfactory. And the ones who become victims are the people; collection does not take place properly, and those who become the victims most directly are the ADUN and Council Members in the local authority areas. That is why I ask the Government to look at this matter very seriously, because we cannot compromise at all on performance. I said yesterday that the quality and standard of municipal services reflect the performance of the State Government today. Thank you.

Tuan Ng Sze HanDAP · PHKinraraEN

Thank you, Honourable Member for Gombak Setia. In fact, the original idea and the present idea are still the same. That is, we want to make Selangor the cleanest state in Malaysia. So through KDEB, we hope KDEB can carry out the best cleaning and refuse collection work. And a study will be carried out next year. Through this study to examine the performance of KDEB contractors, I am confident we can see the actual performance, whether it is improving or declining. As for the question on sub-contractors, this did not happen only now. It happened before as well, but I am confident that situations like this have greatly decreased if we compare them with the past.

Thank you, Honourable EXCO. The Honourable EXCO mentioned that a study will be carried out next year on refuse collection performance and so on. So I would like to ask whether the party carrying out this study is an impartial party, because if we look at all the data we rely on to see whether KDEB's performance or whatever meets the targets, our data still depends on the party doing the work itself. So we are not saying there is any manipulation of data or anything like that, but our data depends on one party that is still biased. So will this study be carried out by a body that is truly independent and not tied to anyone, so that it can provide clear and truly accurate information on the actual situation on the ground? And we must also remember that management here concerns not only refuse but also public cleansing. Thank you.

SpeakerEN

Honourable Member, just a moment. Does Dusun Tua have a debate on development regarding KDEB?

Tak ada.

SpeakerEN

There isn't, is there? Please, it is up to the EXCO.

Tuan Ng Sze HanDAP · PHKinraraEN

I can answer. Yes. The State Government is indeed in the process of selecting an independent company or body, not KDEB, not dependent on data from KDEB or the PBT, to carry out the study. To answer the question from the Honourable Member for Balakong regarding the welfare of stray animals. Through the 2019 budget, the Most Honourable Dato' Menteri Besar agreed to allocate RM1 million for an animal control project. The main objective of the programme is to safeguard the safety and harmony of local areas from animal nuisance, especially involving stray dogs and cats. The implementation of this control project includes the following.

First, upgrading animal adoption care centres to address the shortage of space for housing stray animals. Second, providing training to local authority (PBT) officers on more practical and humane methods of capturing animals, to minimise injury to the stray animals that are caught. Third, providing equipment to safeguard the safety of animal control officers. And fourth, awareness programmes through the local authorities in efforts to control and prevent the breeding of animals such as stray dogs and stray cats that disturb local well-being. A question from the Honourable Member for Teratai regarding the performance of CCTV. Mr Speaker, as previously informed, up to October 2019 a total of 775 CCTV units have been installed throughout the state of Selangor, comprising 414 units owned by the State Government, 225 units owned by the Ministry of Housing and Local Government (KPKT), and 136 units owned by the PBT. The performance of CCTV is constantly monitored by the PBT and the respective District Police Headquarters (IPD). Any damage that occurs will be reported immediately to the vendor, and the damage must be repaired within 24 hours. The Honourable Member for Teratai also raised the issue regarding the Smart Selangor bus service implemented by the State Government. The Smart Selangor bus service is implemented by the State Government out of concern for state development based on the concept of by the people, for the people. This service is provided free of charge to all citizens. However, on the basis of humanitarian rights, the State Government has never prevented foreign nationals from using this service. As a government that is caring and prioritises the people, and also upon the pressure and request of the Honourable Members, the State Government recommends that this service continue free of charge for the people, while a minimum fare is introduced for foreign nationals. Therefore, the rate of RM1 recommended is reasonable and suitable compared with the rate of RM2 proposed by the Honourable Member for Teratai, considering that the rate for MRT or LRT feeder buses is also the same, namely RM1 only. One more question from Taman Templer, regarding the request of the Honourable Member for Taman Templer that the commuter line be extended to Bandar Baru Selayang. The State Government takes note and will bring the matter up at the Ministry of Transport level. That is all, thank you.

SpeakerEN

Thank you, Honourable EXCO Member for Kinrara. I invite the Most Honourable Member for Sungai Tua to continue.

Tuan Amirudin bin ShariPKR · PHMenteri Besar · Sungai TuaEN

Thank you, Honourable Members all. Thank you, Mr Speaker. I extend my thanks for the participation of all Honourable Members, especially those who debated matters relating to the allocation involving development of RM1.333 billion, and this will drive it. It is hoped that this strategy will advance the growth and development of the state as a whole, and at the same time can invigorate our joint efforts towards a regional smart state by 2025, as has been outlined from the beginning, or as was determined from the beginning of the deliberation and discussion of the budgets, or of the 2020 budget later.

Honourable Members all, I have examined closely, whether in this room, in this House or outside, every word and every view expressed by all Honourable Members, and I hope that all Honourable Members can examine more thoroughly the concept of development and also the intention of the development that is planned. When I examine, there are several specific debates. Some of us are interested in discussing the localities, the localities in your areas in particular, but cannot combine and connect them with the overall context. Our aim is to become a Smart State. Our aim is to become a regional state and so on. If this attitude continues, in the end we will fail to shape

our budget and our values more thoroughly and effectively. That is why, when I mention populist policies in budget allocations, it does not mean that populist policies are a continuing grave sin, because in democratic context the measure now is 50%+1. That means it is the minimum that must be obtained. That means popularity must reach a certain best level to qualify you to sit in the House. But populist policies should also not isolate. We must not isolate ourselves from the institution, namely this House, from the state and also from the people, or from your representation as representatives and also from the people as a whole. And this reminds me of an interesting book on this populism, entitled "Me the People" by Nadia Urbinati. If we have the chance to study it, we will be able to see and find a point of balance between excellence and popularity. We are in the constituencies and also in the aspiration for a country, state and House that we possess. That is why there are demands that we sometimes cannot fulfil at the initial stage. Or, if from the humanitarian aspect, from a temporary aspect, we can see it, but at large, or from the picture and the big framework of thinking, the big framework of the course of our state, we have to take actions that are sometimes unpopular, that are sometimes considered backward, that sometimes do not make sense in some matters, but for certain interests and certain moments we take firm actions. Kota Damansara raised the matter of Sungai Pelepas and also what happened at Sungai Kedondong as an example, and several follow-up actions that we will take. We limit the free water supply, for example. We arrange and realign our policies of the people-caring initiative, or our populist policies, or our people-centric policies. All of these are arranged and organised for no other reason than so that we can move one step forward, processing several views and also processing several policies so that we can achieve the objectives outlined. We have a broad outline, namely Smart State, and now we must invest, or we must put money into several infrastructures and programmes. That is why in this year's budget we have allocated a sum of RM50 million, and the RM50 million that we will allocate will focus mainly on important tools towards a Smart State, for example, our Command Center. Now our Command Center operates at Bangunan Darul Ehsan. Yes, it is still quite good. It has become a reference, but to operate in a way that can analyse our data we need a wider space. We have carried out a CCTV pilot project, which is not enough, only over 700, so we have to extend and widen it further. Apart from that, we thank MCMC, Malaysian Communications and Multimedia Commission, especially for guaranteeing that by 2022 the whole of Selangor State will be connected with fibre optic, or optical fibre, which indirectly becomes an important backbone for the birth of a smart state, or the birth of a smart state that we hope for and dream of in the future. I want to give direct feedback on several views that have been put forward.

First, from Sijangkang, which proposed that the State Government continue programmes that prioritise consensus, consultation and unity of the multiracial community in Selangor State. This is the principle we have upheld from the beginning, and that is why we will continue, only perhaps the mechanism will be slightly different. Previously we implemented programmes in the form of code, uncode, doktorinesasi, namely training programmes for local leaders, for civil servants and so on. I think that after 10 years

forward, we changed the focus to a better direction, namely meetings and direct relations with the people. Therefore, from the SPICE programme to the INSAN programme, and we now implement it in the form of a national education programme by creating direct participation of the people in programmes arranged together with leaders such as State Assembly Members, such as Councillors, such as Village Heads, PEBT and PWB. So Team Selangor becomes one of our agents that proposes and outlines community programme relations with the State Government and also encourages several new elements, for example volunteerism, or volunteering among the community and the public in particular, and next year we try to focus on green volunteerism and see green not only as green, but at the moment when they plant trees, beautify landscapes, pick up plastic, recycle discarded materials, elements of unity are indirectly absorbed in those programmes, and not only through lectures in the classroom, or lectures in the classroom or in seminar halls, which I believe we have passed those levels or those spaces where previously we educated leaders, especially, for me, in 2008 until 2012 and 2013. Perhaps some civil servants did not fully understand the approach and methods of Pakatan Rakyat at that time, and now in Pakatan Harapan, after nearly completing three terms, I think that matter has been resolved at the policy-making level and at the top management of the states, or top leadership at state level, and we must cultivate it at the grassroots level through programmes implemented under the national programme. So, Insya Allah, these elements will be maintained: community unity, inter-racial relations, knowing what the policies and direction of the state and country are at this time, what the objective of establishing this state is, so that it remains in a moderate condition and becomes a home comfortably inhabited by everyone. And now Selangor indeed has become a place of residence for all our communities, regardless of multiracial background, from various states and even from overseas or from other places.

Therefore, we have also allocated a large amount to answer Bukit Melawati regarding the development of the people's minds, and these are allocations channelled through our media such as Selangor TV, such as TV Selangor, or Selangorkini and several media that are issued. Basically, this development of the people's minds, previously we spent more than RM10 million, and now we allocate nearly RM9 million to ensure that information channelled to us, the State Government, is channelled through Selangorkini and also through TV Selangor. And at this time, in fact, in line with the political change that has taken place at federal level, with our access to the Federal Government being friendlier and closer, we are thinking about how to include Selangor TV content in the existing digital TV channels that will begin to be implemented soon. Before long, the analogue TV broadcast will stop and switch to digital TV, and this actually gives us an opportunity to fill the content and programming of our TVs, but we must improve the quality, not only news, not only live broadcasts of the House or live broadcasts of Parliament. For the information of all Honourable Members, TV Selangor recorded high readership, as well as subscriptions or attendance, during the last general election, because the people wanted alternative sources of news that are more credible and more forthright, and at this time its value has dropped somewhat because they now consider the latest RTM survey to be trusted, the most trusted.

The second is Astro Awani. It is different from the previous times, and I think it is a good time for us to change the strategy of approach to this media by mixing with them, but still maintaining the value of news from Selangor and also the content of news from Selangor that may be able to continue in digital TV. The cost is quite high, nearly RM10 million. If we spend it all, then we cannot issue Selangorkini, but we are discussing merging and combining with several TV broadcasts. Now there are TV broadcasts that want to reorganise after the analogue TV is abolished. In fact, TV broadcasts such as TV Hijrah, TV3, TV9, TV1, RTM and even Astro are facing a very challenging situation. Challenging in how they will fit with digital TV that is provided free of charge but is of HD quality and can be accessed almost everywhere. There is now a pilot project in Langkawi. We are waiting for the relevant feedback, but I am confident that if we can include these elements, we can expand them and we can strengthen the delivery of news about Selangor State. Sometimes people do not remember Selangor, people did not know Selangor for years. In fact, in the past five or six years, on the part of the State Government, EXCO for Investment and also EXCO for Entrepreneurs, including several other EXCOs, when we go abroad we have to introduce Selangor, we have to introduce it because when people say Malaysia, they think of Kuala Lumpur, when they say Malaysia, they will think of Melaka, but they rarely think of Selangor, even though many headquarters are in Selangor, but they consider those headquarters to be in Kuala Lumpur, of course, because Kuala Lumpur International Airport is actually located in Selangor too. But we are rather proud of several of our initiatives, for example our Smart Selangor initiative, which to this day, not long from now, I and several EXCOs will go to Barcelona for the Conference of Smart States or Smart City. So, if we look at the list, the so-called Malaysia is not called, the representative of Malaysia is from Selangor Darul Ehsan State, and we will sit together with Singapore. Singapore's representative is their Foreign Minister, to present what discoveries, latest results, and to share what new values and new initiatives they have regarding Smart States. So I think this matter must be brought and developed by all Honourable Members, that we are leading in front. When we lead in front, there are certainly many weeds, stumps and blocks that we must face or avoid, there are matters of trial and error and so on, but, Alhamdulillah, we are still a reference and recognition, and good results can be presented and represent Malaysia towards a better direction. Therefore, I am very pleased with the concern of Honourable Members regarding basic facilities, the flood problem, the road problem, the drain problem. These are important problems, the problem of solid waste collection, which was mentioned by the Honourable Member for Gombak Setia and also answered by Kinrara a moment ago. These are basics, but how we want to overcome these matters with the concept of Smart States, we must talk about this, we must raise this, we must connect, combine and link these questions so that we can together move towards a Smart State by 2025. I call on this: this is not only the government's dream, it should become the dream of all Honourable Members, including Opposition Members, and we hope that the people throughout the country, our state, move towards that direction, and only then can we achieve the targets and hopes that we have hoped for and outlined as we have done. Alhamdulillah, in fact our format and formula are different from other places in the world.

Our formula is quite accepted, which is why every year we are still invited to Barcelona, because we have a somewhat different approach, which appears to be problem solving and has direct relations with the people. I have repeatedly mentioned, including to civil servants at a meeting with the Smart City Council, that Smart City is not only about its technology, not about internet speed and the sophisticated elements of the applications we present, but about how the people can benefit, receive blessing, receive good, and use every facility we introduce through the term or through the Smart State approach. Honourable Members, related to this unity, several Honourable Members such as Sungai Kandis and Kota Anggerik also raised the matter of translating great works, which we continue. So far, more than 22 works have been published by us. Western works, local works, foreign works, external works, especially because they involve translations, because for us what is important, or materials in Bahasa Melayu, must be increased so that their views are broadened, so that they can see from various contexts. I mentioned in the previous winding-up that among the works that were fastest sold out were the works of Al-Ghazali such as al-Munqaz al-Dalal and several other works, especially those relating to or Islamic, and we have published them repeatedly, and we welcome this. Moreover, the State Library has begun this year, perhaps not yet popular, the series of book reviews that we have published, and we encourage the library or Tun Raja Uda Library, or Pustaka Raja Uda, to hold these programmes, even though the location is somewhat inside, but we will try to popularise it and make it a place of attraction for many people, apart from sharing information and also books that we will translate later, which we have presented.

Honourable Members all, at the same time we are building the people's thinking, we are enriching the people's thinking, we are raising the quality of the people's thinking, and we are also facing social problems. Sungai Panjang raised the matter of allocations that we have prepared for anti-drugs or drug abuse, and Kuang also raised the same matter, and of course this is a continuous effort that we should improve, and with several arguments from our friends, such as Jeram and so on, we must be careful because the condition of drug abuse is very serious, especially when there is the term NPS, None Psychotic Substance. None Psychotic Substance refers to drugs in synthetic form, and their price is cheaper, but their effects, their effects are hundreds of times more dangerous than herbal drugs such as cannabis or ketum. It is included in the category of dangerous drugs, and we have to face these competitions. Moreover, if I may mention here, in the area of Sabak Bernam, especially in the Pancang Bendena area, where? In Air Tawar or in Sungai Panjang? In Sabak, this is a rather embarrassing matter, but we must fight it. I mention it here. That place has the most affordable drug prices in Malaysia. From Penang, from Singapore, from the south of the country, from the north, from the east coast, people come to that place, even though transactions and distribution are carried out by undocumented migrants, especially or Myanmar nationals, whom we have identified. Several raids have been carried out, several arrests have been made, several obstructions and restrictions have been imposed, but in the end it still continues. For the first time, we actually allocated one million this year solidly, because we work with the National Anti-Drugs Agency (AADK) to tackle this drug abuse problem. And, Alhamdulillah, our request to the Federal Government has approved RM15 million to tackle the hotspots. I mention them here so that everyone understands. We have hotspots at Felda Soeharto, Hulu Selangor. We have hotspots at Sabak Bernam and we have hotspots at Desa Mentari

or in the Seri Setia area. One (1) in the urban area, two (2) in the rural area. And I think this needs to be tackled by working with every agency, and PEMADAM comes as an agency appointed by the state to popularise it among the local community.

Our approach is also somewhat different. This 30 November, for example, we are holding a run. Previously, we held a concert with Ella. That concert was not just a concert, we wanted to popularise anti-drugs. In addition, we worked with the Dewa Reunion Concert, the Dewa Reunion Concert from Indonesia, solely to insert anti-drug elements into the messages delivered, even though only indirectly, around 20 to 30 per cent. I believe it has had some good effect. If we say RM1 million, is it enough or not? Indeed, we are not yet sufficient, but our capacity, based on our existing agency, namely PEMADAM, I think it is sufficient for the first year, and as I have said, if there is no concrete improvement visible in terms of the handling and the drug problem next year, we will use other methods, including cutting the RM1 million allocation. Perhaps we will have to move it to other matters. Because now we use it, we must involve schools, we must involve the university side. If we imagine drugs among those who do not study and those who do not attend school, those who are unemployed, that is actually an old view. If we are truly serious, we know this problem began as early as 12 and 13 years old among our young people. And this is a matter that we must view seriously. We talk about Smart State, we argue fiercely about insufficient street lights, floods not being resolved. But this problem will continue to haunt us, and the State Government is committed with all our strength to tackle and eradicate the problem of drug abuse from the early stage. But we must understand it as a whole. That is why I ask our Honourable Members to be careful. Do not easily say "halal ganja". I also understand the context, but it is better for us to be specific. We use the word "Hem" so that it does not lead to what Kuang mentioned just now, decriminalisation. What Kuang said, indeed addicts are victims, but in our community, in our society, when these addicts emerge, they become restless. Up to a certain level there are excuses, "it is no use conducting drug operations". In the end these addicts are arrested and released, arrested and released, arrested and released. And they repeatedly return. This is a real matter that happened in Rawang, and I think we need to tackle it by making serious efforts and understanding this context as a whole. This is a real problem that all Honourable Members must face seriously.

Alright, at the same time, I think several Honourable Members also raised matters about the Professional Programme, namely Bukit Melawati and also Banting. The specific matter, if possible, I will mention the rebranding of Inspens International College to the Selangor State Training and Technical Skills Development Centre through the Professional Committee. It will conduct a comprehensive study to reorganise the organisational structure and ensure the involvement of academia and industry practitioners can be combined to achieve its objectives. Besides that, for existing staff, several proposals for empowerment programmes in terms of training and competency will be implemented. The establishment of the Professional Institute is expected to take some time to ensure its role and function play a role in line with the role played by the Federal Institute of Vocational Education and Training, or BIBB in Germany.

Honourable Members all, when we made a visit to Germany this year, we found that the ecosystem is a very important matter in the education system, technical and vocational. If we want to talk about the dual system and so on, it is one view, that is true. But the dual system is supported by the ecosystem. That ecosystem must stand, for example, training centres that study the elements and vocational matters, what must be developed? And then there are institutions and there are relations with the relevant agencies and companies. It cannot be only a government effort to develop the technical and vocational industry, because in the end, students, undergraduates or graduates from the Professional Programme will need to work. But if that work does not meet the target, for example, we have five (5) fields outlined by investment and industry, F&B, Life Sciences, Aerospace, Halal and E&E, Transport and Halal, for example, Transport and Machinery and Halal E&E, for example. These are all fields that are the core in Selangor State. But when we look at some technical and vocational training offers provided at Inpens, most of them take up low-level or low-yield work. And we must change our view that TVET is not for second chance small ground. I saw a question from Templer which said that TVET is for dropouts. True, that was part of the earlier view, but now we want TVET also for first class students, first grade students, who have high mathematics and science skills, combined with high skills, because they must manage and control machinery, automotive tools and also high-technology tools. That is why this shifting must be supported by an ecosystem.

That is why we did this, and we restructured Inpens so that it becomes one of the ecosystems that fills every empty space so that it is not eroded. Otherwise, we have Community Colleges that provide TVET. We have IKDM that provides TVET, we have Giat Mara that provides TVET. We have other institute centres that plan to provide TVET. In the end, they do the same thing. Repairing motorcycles, repairing engines, haircuts, hair styling, nail styling, everything is available. Yes, that is needed. But for technical, for the aerospace industry, we are experiencing a huge shortage. To control large machinery, we still face a huge shortage. That is what happened when I mentioned we offer 26,000 job opportunities every time an investment comes in. Perhaps thousands of job opportunities. Outside there, the unemployment figure is still in the thousands too. Why is it not matching? Because professional skills and their capabilities are not balanced. So, the State Government has to intervene although this is a Federal Government matter, because for us, we want to move to a Smart State, there is a Human Resources and Human Capital space that must be filled with those programmes. And I welcome the suggestion made by Banting that the State Government achieve international recognition, and the Standing Committee on Education and the process of preparing a professional ecosystem, that those involved are included comprehensively. And it is not a one-day job. If I asked in Germany, how was BIBB, this ecosystem, built over a period of 700 years. And we do not need to wait 700 years, until it rots as well. We already have the model. We can follow it, but we do it according to our existing capability and capacity, combined with the aspiration of the Smart State, combined with the industrial needs that come, as mentioned by the parties concerned.

Teratai raised matters about allocations for schools. Yes, we still maintain the same system, including for Chinese National Type Secondary Schools,

which have been allocated in previous years, and there is no need to worry about that figure. Finally, I want to give feedback to Sijangkang regarding Friday prayers, or surau Friday prayers. Permission to hold Friday prayers is under the consideration and full authority of the Mosque and Surau Management Committee, and is accepted through the surau's application or through the proposal of the Committee Secretary. Based on the Committee's consideration, permission for a surau to hold Friday prayers is given for, first, reasons that should be properly considered according to law, the benefit and effect on worshippers, namely construction and renovation as well as disasters involving existing mosques. Second, (c) the distance of the mosque is about 7km and density that justifies it, and (d) the effect on the Friday worshippers of existing mosques and suraus. That means these four matters will be given consideration: whether there is an effect on benefit, whether there is an effect of distance, whether there is an effect on Friday prayers. Sometimes when we permit it, the mosque becomes empty. Ha, that cannot be allowed. The Government has built a mosque worth more than RM10 million now, and in the end it becomes empty because people prefer going to the surau because the surau is in front of their houses. So, we cannot, we have to look at the suitability.

Thank you, the Honourable Dato' Menteri Besar. I propose that the Islamic Religious Department or whichever party has the authority take a more proactive role, rather than only waiting for the congregation members or the Mosque Committee to apply for the upgrading of a surau so that it is permitted to hold Friday prayers itself. In my view, there are some mosques whose congregations are very large, where our children come to the mosque but do not pray because the conditions are not conducive or the space is too limited, and I think this is a loss for us in building up our children.

Tuan Amirudin bin ShariPKR · PHMenteri Besar · Sungai TuaEN

Thank you. I refer this back to the committee concerned, asking it to assess and be proactive as in the proposal from Sijangkang. We want the comfort of the congregation to be prioritised. We once gave permission at Hotel De Palma, for example, and up to now it has had a good effect, because residents there would otherwise have to travel more than 6 to 7 km to reach a place for Friday prayers, and some residents failed to perform Friday prayers when they lived at De Palma. These formulas may be reviewed from time to time according to suitability. I think I have answered almost everything, Honourable Member. If there is anything left out, perhaps you can inform me directly, but I wish to reiterate, Alhamdulillah, our thanks for everyone's participation, and what is reflected overall in this Motion, namely that our Motion wants to move forward, and in the course of that progress we do not want anyone to be left behind. And of course, we have to rearrange and reorganise in order to move forward. If we follow the old phases, the formulas of 2008, 2009 up to 2015 and 2016, we could still maintain what already exists. But, as I mentioned earlier, current issues, the latest findings of facts, and current trends such as Smart City and so on, if we do not act quickly to move ahead, we will eventually be left behind. We would only be talking about past glories, but fail to compete at a larger level. May development continue to flourish, welfare be safeguarded, and the state be outstanding and its people dignified. Thank you.

SpeakerEN

I invite the Honourable Member for Selat Kelang to speak briefly.

Datuk Abdul Rashid bin AsariBERSATU · PNSelat KlangEN

Thank you, Mr Speaker. I apologise for being somewhat late in answering several of the debates raised by the Honourable Members. I wish to express my utmost thanks and congratulations to the Honourable Member who debated and touched briefly on state tourism. As we are well aware, we have launched several initiatives that can improve tourism programmes in the State of Selangor, especially the 3S pilot project, and we are also developing a more detailed and better registration system to ensure that tourism registration in this state can be recorded and checked more thoroughly. However, I wish to answer several questions raised by Sentosa. The first is whether the Government has set aside the allocation for a cultural centre along the Sungai Klang. For the information of the Honourable Member, the State Government has never set aside the importance and social development, nor the preservation of the customs and culture of any race in the State of Selangor. It is the aspiration and inspiration of the State Government to implement the development of Malay, Chinese and Indian Cultural Centres in the State of Selangor, in an effort to appreciate and uphold the harmonious diversity of arts and culture in society. The original plan was to develop all three cultural centres in the State of Selangor, in line with the announcement of the Sungai Klang Development Stimulus package, which will place the State of Selangor's Cultural Centres along the Sungai Klang.

However, since this development began as early as 2012, there have been many constraints and obstacles to implementing the development of this cultural centre. Among the causes of these constraints is the very high estimated cost, which is expected to amount to nearly RM300 million until full completion. At the same time, the process of land acquisition at the proposed sites is feared to affect the socio-economy and demography of Klang Town as a Royal Town that must be upheld and respected. This is because the proposed area also involves high-value commercial land, in addition to other effects that may involve the economic and social sectors and must also be carefully examined. Nevertheless, the State Government remains committed to developing an integrated cultural centre for the State of Selangor, as announced by the Most Honourable Dato Menteri Besar when tabling the Selangor Budget 2020 recently.

The State Government has committed and intends to establish Kampung Budaya Selangor, which can become a reference centre for the history, culture and traditions of other ethnic groups in the State of Selangor. An area of 35 acres along the Sungai Klang, located in the middle of Klang Town, has been identified for development, and a sum of RM5 million has been allocated for this purpose. It is also believed that this will be able to enhance the attractiveness of the Selangor Maritime Gateway Project, or MSG, through this initiative. Secondly, I would like to touch on the question raised by the Honourable Member for Sungai Kandis regarding the Sultan Alam Shah Museum, where upgrading works are currently being carried out. For the information of the Honourable Member, the Sultan Alam Shah Museum is under the administration of the Selangor Malay Customs and Heritage Corporation, or PADAT. The museum was temporarily closed for 13 months beginning 1 May 2019 and will reopen no later than 31 May 2020. The total cost of the upgrading works is RM1.4 million, allocated by PADAT. The upgrading of this museum is very necessary because of the 19 galleries opened in 1989, almost all of which have suffered serious damage. PADAT has planned to reopen 6 galleries, comprising the Selangor History Gallery, Selangor Culture Gallery, Modern Design Art Gallery, Selangor Natural Science Gallery, Fine Arts Gallery and Selangor Islamic Gallery. To make this museum a centre of knowledge and a heritage tourism destination, PADAT has sought to add artefacts or collections related to the State of Selangor.

Apart from that, the museum also wishes to open a new gallery known as the Modern Design Art Gallery to meet the needs of studies and the development of studies at institutions of higher learning. Both of these museums will use exhibition methods that meet the tastes of the present and future generations. And lastly, I would like to address the question raised by the Honourable Member for Bukit Melawati regarding making use of the Cultural Ground at Bukit Melawati for cultural performances for the benefit of tourists. For the information of the Honourable Member, the State Government, through the Standing Committee on Tourism and Heritage, has taken note and given attention to the development of tourism in the Kuala Selangor District, especially at Bukit Melawati. The State Government, through the Selangor Malay Customs and Heritage Corporation, or PADAT, has also planned to revive the Kuala Selangor Cultural Ground at Bukit Melawati. This will involve cultural performances to be shown to visitors to Bukit Melawati starting early next year. As a sign of the State Government's sincerity, PADAT has carried out preliminary works to rehabilitate the structure of the Kuala Selangor Cultural Ground at Bukit Melawati this year, and the total cost is RM18,350.00. The State Government hopes that this effort will be well received by the public and visitors to Bukit Melawati, and will in turn help to enhance the image and the number of visitors to Bukit Melawati and the State of Selangor in general. At the same time, the State Government also hopes that the Kuala Selangor Cultural Ground will become a stage and platform for the development and growth of cultural activities among the younger generation, especially in the Kuala Selangor District. Thank you, Honourable Member.

SpeakerEN

Thank you, the Honourable EXCO Selat Klang. Honourable Members, the matter before this House is a motion that, pursuant to Section 9, Subsection 4 (3) of the Development Fund Act 1966, this House resolves that the allocation of RM1,133 million stated in the Development Budget Estimates for the Year 2020, tabled before this House under Section 4(1) of the same Act, as contained in the schedule, be approved. Schedule of Estimated Development Allocation Expenditure 2020: B01 Office of the Menteri Besar and State Secretary RM745,681,000.00; B04 Selangor State Treasury RM1,565,000.00; B08 Selangor State Department of Agriculture RM11,767,000.00; B10 Selangor State Forestry Department RM5,225,000.00; B12 Selangor State Public Works Department RM178,000,000.00; B13 Selangor State Irrigation and Drainage Department RM84,400,00.00; B14 Selangor Islamic Religious Department RM98,980,000.00; B16 Selangor State Town and Rural Planning Department RM1,955,000,00; B17 Selangor State Veterinary Services Department RM5,427,000.00; Total RM1,133,000,000.00. Honourable Members who agree, please say "Yes".

HOUSE: Yes.

SpeakerEN

Honourable Members who do not agree, please say "No". The motion is carried.

Secretary of the HouseEN

The next motion is Motion No. 21 of 2019. A motion under Standing Order 76 (5) by the Honourable Member for Pelabuhan Klang.

Speaker

Silakan.

Tuan Azmizam bin Zaman HuriPKR · PHPelabuhan KlangEN

Can one speak like that?

Speaker

Silakan.

Tuan Azmizam bin Zaman HuriPKR · PHPelabuhan KlangEN

Mr Speaker and Honourable Members, I wish to move a motion as follows. Whereas, pursuant to Standing Order 76 (5) of the Standing Orders of the Selangor State Legislative Assembly, this august House receives the Report of the Select Committee on Local Authorities, JPPBT, of the Selangor State Assembly regarding the issue of allocation for the Malaysian Road Records Information System, or MARRIS, which was tabled before this august House as Paper No. 28 of 2019. Honourable Members, as we all know, every day Honourable Members receive complaints about problems and complaints frequently received regarding MARRIS roads, where the allocation provided by the State Government of Selangor is RM500,000,000.00 a year. Yet Honourable Members still receive complaints from users, and we ourselves see roads that were newly resurfaced but suffered immediate damage. Some roads that should not have been resurfaced were resurfaced. Some roads that needed resurfacing were not resurfaced. Round and round.

Finally, the Select Committee on Local Authorities held a closed hearing on 27 August 2019 with the Procurement and Asset Management Division of the Selangor State Treasury, the Engineering Department of the Petaling Jaya Municipal Council, the Engineering Department of the Klang Municipal Council, the Klang District and Land Office, the Petaling District and Land Office, the Selangor State Irrigation and Drainage Department, and the Public Works Department, regarding the Procedures for Managing the Allocation of the Malaysian Road Records Information System, or MARRIS. The purpose of this closed hearing was to obtain information and explanations from the relevant agencies as to why complaints were received even though the roads had been resurfaced, and yet there were still voices of dissatisfaction among users. During the closed hearing, we were briefed that, under Article 109 (1)(B) of the Federal Constitution, the Federal Government is empowered to provide financial allocations to State Governments for the maintenance of state roads, and that, under Part Two of the Tenth Schedule of the Federal Constitution, the maintenance of state roads means the preservation, upkeep and restoration of state roads, roadside furniture, bridges, flyovers or drainage forming part of or connected to such roads, as close as possible to their original condition as built or as subsequently repaired. And, under paragraph 11 of the Guidelines on Procedures for Managing the Allocation of State Road Maintenance, there are 4 plus 1 categories of maintenance, namely first, routine maintenance, which is scheduled; second, periodic maintenance; third, emergency maintenance; fourth, preventive maintenance; and fifth, the limit of slope maintenance boundaries. According to the MARRIS online system records up to 31 October 2018, a total of 21,742.38 kilometres of roads in Selangor will be maintained by the allocation provided through MARRIS, and these roads are State Trunk Roads, Municipal Roads, Back Lane Stretches, Low-Cost Housing Estate Roads, Village Roads and also Agricultural Roads, for which the expected receipts in 2019 amount to RM516,578,820.00. This total is very large, yet problems still remain numerous, and every year the State of Selangor receives RM500,000,000.00 for State Road Maintenance. The calculation rates for the MARRIS allocation are as follows: first, State Trunk Roads and Municipal Roads cost RM31,000.00 per kilometre. For Low-Cost Housing Estate Roads, Village Roads, Agricultural Roads and Back Lane Stretches, the cost per kilometre is RM14,000.00. The agencies that will handle the MARRIS allocation are the Selangor State Public Works Department, the Local Authorities of the State of Selangor, the State of Selangor District and Land Office, and lastly the Selangor State Irrigation and Drainage Department. The determination of the ceiling for implementing agencies is as follows: first, the capacity of the agency; second, the performance of the agency; third, existing obligations; and fourth, the allocation for each State Legislative Assembly (DUN) constituency of RM3,000,000.00, which will be given to each DUN and to the local authorities; fifth, repair costs; sixth, agency applications; and lastly, 10% allocation. And after hearing the hearing, the Committee... There is much more, Mr Speaker.

SpeakerEN

Honourable Member for Pelabuhan Klang, please sit down. Honourable Members, the time has reached 5.30 p.m. The House will therefore resume tomorrow, Wednesday, 13 November 2019, at 10.00 a.m. The House is adjourned.

(THE HOUSE ADJOURNED AT 5.30 P.M.)