Sarawak · 8 May 2019

18th Assembly, 4th session, 1st meeting (unedited) · not final · 87 turns · 34,479 words · official PDF ↗

13 of 87 turns machine-translated from Malay (Claude Haiku 5.5), marked EN. The original is the record.

ExperimentalSarawak publishes only unedited transcripts (Belum Disunting). The 19th Assembly was dissolved on 26 Oct 2026. Speakers are matched by our parser and will have some errors.

(Opening)

Deputy SpeakerEN

Good morning and greetings, Honourable Members. I have granted the leave of absence under Standing Order 81 to Honourable Puan Hajah Simoi Binti Haji Peri, Honourable Member for N.28 Lingga for today and tomorrow sitting. With respect, I invite Honourable Dato Sri Michael Manyin Ak Jawong, Minister of Education, Science and Technology Research, to deliver the winding-up speech.

Continuation of debate on the Motion of Thanks for the Speech of Tyt Yang di-Pertua Negeri of SarawakMotion

Dato Sri Michael Manyin Anak JawongPBB · BNMinister of Education, Science and Technology Research · Tebedu

Tuan Speaker, terlebih dahulu saya ingin mengucapkan merakamkan setinggi-tinggi penghargaan dan terima kasih kepada Tuan Yang Terutama, Yang di-Pertua Negeri Sarawak, Tun Pehin Sri Abdul Taib Mahmud di atas ucapan perasmian Mesyuarat Pertama Bagi Penggal Ke-4, Dewan Undangan Negeri Sarawak Ke-18. Saya amat menghargai penekanan Tuan Yang Terutama Tun Pehin Sri terhadap kepentingan program-program latihan STEM dan TVET bagi melahirkan tenaga pekerja mahir untuk memenuhi keperluan industri. Selain itu, Tuan Yang Terutama juga menghargai usaha Kerajaan Negeri untuk membaik pulih sekolah-sekolah daif khususnya di kawasan luar bandar bagi mewujudkan persekitaran sekolah yang selesa. Kita mendoakan agar Tuan Yang Terutama Tun Pehin Sri sentiasa dikurniakan kesejahteraan dan kesihatan yang berterusan. Importance of Education

Tuan Speaker, the value of education in the development and progress of any society has been expounded by all facets of society including philosophers, statesmen, educationists and politicians. The Greek philosopher Diogenes said around 400 BC that ”the foundation of every society is the education of its youth”. Nelson Mandela, the former President of South Africa, said in more recent times, that ”education is the most powerful weapon which you can use to change the world” and he went on to say that ”without education, your children can never really meet the challenges they will face, so it is very important to give children education and explain that they should play a role for their society and their country”.

The value of quality education is even more critical in our present age with the advancement of technology and proliferation of new knowledge taking place at an unprecedented pace. Our children must not just be able to learn, but also to unlearn and relearn rapidly.

Unfortunately, despite the acknowledgement of the importance of education by all quarters, our children are not getting the quality of education that they deserve. In December 2013, the World Bank released a report “Malaysia Economic Monitor: High Performing Education” in which it raised concerns on the declining quality, quality of education of Malaysian Education and commented that “schooling has not been translated to learning” in Malaysian Schools. In June 2018, the World Bank again released another report “Productivity Unplugged: The Challenges of Malaysia’s Transition into a High-Income Country”, and the essence of this report is that despite the high level of expenditure on education, Malaysia has lags behind most Asian countries in terms of the outcome of its education system.

The situation in Sarawak is far worse. After more than 50 years of neglect, the physical conditions of our schools have deteriorated, our proficiency in English has plummeted and our performance in Science and Mathematics has fallen.

Our teachers cannot be blamed for the quality of education that we are having now. They are very dedicated and hardworking. If you have to work even for a month under the conditions in which they are forced to work in, you will realize that what I mean by their dedication and hardworking. The constantly changing policies and system has changed and failed them. Our school leaders do not get sufficient opportunities to develop their capabilities, our teachers have limited continuous professional development, and many of our teachers have been forced to teach subjects for which they are not been trained for.

This sad state of affair was what prompted our Right Honourable Chief Minister to establish Sarawak’s own Ministry of Education, Science Technological Research in 2017 to be exact 9th of May 2017. Although education is a Federal matter and Sarawak cannot interfere in the Federal ministry’s policies, the idea is to have a ministerial level platform to have more leverage in our negotiations with the Federal government. It is also to supplement and complement the Ministry of Education (MOE) in strategic areas and help improve the standard of education in Sarawak.

After extensive engagement with the Sarawak Education Department, MESTR, that is my ministry, has decided to focus on four key areas. These are:

(a) Improve the physical condition of all schools so that our teachers and students have a safe and conducive place to work and learn; (b) To Improve the proficiency of English amongst the teachers as well as students, so that our students can have access to knowledge and enable them to fit the requirement of the market and the industry; (c) Nurture interest and improve the performance of our students in STEM; and (d) Nurture and promote a culture of creativity and innovation.

The ultimate goal is to improve the performances of our schools and our students.

Improving Physical Conditions of Schools

Tuan Speaker, with the formation of the Ministry of Education, Science and Technological Research (MESTR) and the presence of political will on education in Sarawak, Sarawak government was able to highlight the deplorable condition of our schools and to impress upon the Federal government for special allocation to address the issue. It was agreed by the previous government to allocate a sum of RM1 billion which was supposed to be over and above of the annual allocation under the 11th Malaysia Plan. RM500 million was to be spent in 2018, and another RM500 million will be spent in 2019 to repair and upgrade the schools in Sarawak. In 2018, RM416 million that was allocated in 2018 to repair and upgrade 116 schools was not part of the RM1 billion allocated under the 2018 budget. Of the 116 schools, 50 schools were implemented by JKR Sarawak and all have been fully completed. Of the remaining 66 schools implemented by MOE, 22 schools are still under construction (offer date: the award date actually between February and March 2018 and supposed to be completed at the latest on 18th July 2018).

The RM1 billion allocated by the previous government under the 11th Malaysia Plan was never honoured by the Pakatan Harapan government. However, Pakatan Harapan government has allocated RM100 million in 2019 to repair or upgrade 32 schools. The project is expected to start in July and should be completed by the end of the year. The management of these projects is directly under MOE, with JKR Sarawak as the implementing agency. The two major issues faced by Sarawak are dilapidated schools and low enrolment schools.

Dilapidated Schools (DS)

According to Sarawak Education Department (JPNS), in 2017, out of 1,457 schools in Sarawak, 1,020 schools are identified as dilapidated schools. These are divided into three categories that is DS1, DS2 and DS3 (DS1 – 25% dilapidated; DS2 – 50% dilapidated; DS3 – 75% dilapidated). Since 2017, a lot of effort has been made to upgrade our dilapidated schools by both the Federal and the State governments. Projects by Federal Government

The projects by the Federal government include those in the 11th Malaysia Plan, and additional allocation for the IBS projects in 2016 to 2018. Under the 11th Malaysia Plan, 18 schools are being rebuilt. Under the IBS project, 166 schools are being upgraded, out of which 144 are completed. As mentioned earlier, another 32 schools will be ugraded this year using the RM100 million.

Projects by Sarawak Government

Sarawak also has implemented its own projects to improve our schools. These are:

(a) Through the Special Development Allocation Fund (SDAF), Sarawak has allocated at least RM37 million to assist Government-aided Schools to improve their facilities. (b) Under the Rural Transformation Initiatives (RTI), 63 schools have been identified for repairs and upgrades at a cost of RM21 million over the period of 2018 to 2020. Of these, 26 schools have been completed. (c) Sarawak is also funding the relocation of SK Ulu Segan, Bintulu, and SK Maludam, Betong. Both are currently under construction and expected to be ready, to be completed by 2021. For the information of Ahli-ahli Yang Berhormat, 13 companies participated in the open tender for the construction of SK Ulu Segan. The successful bidder or tenderer is Town Builder Realty Sdn. Bhd. which submitted a bid of RM29.5 million. For SK Maludam, 15 companies participated, and the successful tenderer is Tokoh Bina Sdn. Bhd. which submitted a bid of RM35.8 million. So I would like to clarify here, Tuan Speaker that what Ahli Yang Berhormat for Kota Sentosa was just an assumption. This is the reality. (d) Sarawak has also allocated RM160 million for upgrading of schools in the Northern Region Development Agency (NRDA) area. We are currently identifying the schools and finalising the scope of work. (e) Sarawak government has allocated RM6.2 million to connect at least 33 rural schools to treated water supply under its 11th Malaysia Plan. This is expected to be completed by the end of this year.

RM50 million has also been allocated to connect at least 113 rural schools to the electricity grid for uninterrupted electricity supply. However, we cannot proceed with this until consent is received from the Ministry of Education (MOE). Additionally, Sarawak has also provided assistance to 50 schools affected by flood in 2018 to replace damaged ICT and non-ICT equipment, facilities and furniture. The amount was RM4 million.

The Sarawak Education Department (JPNS) is currently reviewing the total number of dilapidated schools throughout the State after the various upgrading projects. The verification workshop on dilapidated schools was carried out in March 2019, and we have yet to receive the final report. Low Enrolment Schools

Low Enrolment School is defined as a school that has less than 150 students. In Sarawak, out of 1,265 primary schools, 651 schools have been identified as Low Enrolment Schools (LES) by the Education Planning and Research Division of the Ministry of Education (MOE). There are issues and implications with low enrolment schools, particularly:

(a) The allocation of teaching and non-teaching staff are based on students population. Thus, our low enrolment schools do not get the full complement of staff such as option teachers to teach relevant subjects or option subjects; (b) The allocation of facilities is also dependent on students population and as such, many of our low enrolment schools are deprived of essential facilities; (c) Resulting in a non-conducive learning environment in schools (i.e. lack of interaction and exposure due to small numbers of students and staff) which affects the students’ full potential in their studies and overall performances and development; and (d) In our rural areas, not all parents are well educated unlike those in developed countries who are able to assist their children’s and staff in education.

Tuan Speaker, Sarawak, in collaboration with the Federal government, hopes to merge some of these low enrolment schools into centralised schools to ensure optimisation of resources and facilities. According to initial estimation, 357 of the current Low Enrolment School (LES) can be merged into 126 centralised schools. The criteria for merging of schools include:

(a) which is the most important and the most critical and crucial, consent from the parents; (b) site availability; (c) road accessibility; (d) boarding facilities; and (e) access to public utilities – i.e. water and electricity supply.

The merging of schools will involve substantial amount of funding which we hope the Federal government will consider favourably because it is to their advantage, as it will reduce operation costs in the long run. We will also need the support of all the Ahli Yang Berhormat and community leaders to ensure successful implementation, or even before we embark on the project.

Improving English Proficiency

We all know that English is the international language of knowledge, commerce and science. Therefore, proficiency in English is an important requirement for young Sarawakians to succeed. As the Standard of English has declined over the years in Sarawak, there is an urgent need to improve it among our teachers and students. Practical approaches are pertinent to ensure effective implementation by all parties involved. Efforts that have been initiated / planned by the Ministry towards increasing English proficiency in the past years include:

(a) Sarawak English Language Education Symposium (SELES):

In 2017, our theme for SELES was “Connecting the Dots: Curriculum, Classroom and Community” while for 2018, our focus shifted to “Creativity: From Inspiration to Implementation”. The two symposium or symposia whichever it is, it is all correct, involved over 2,000 teachers and practitioners. Based on the feedback received by our Ministry, the teachers find the symposium or symposia very beneficial to update their knowledge on international best practices. The recent symposium also gave our own teachers the platform to showcase their innovation in teaching English. The participants are also tasked to share what they have learned to their colleagues in their respective schools. Our hope is that our teachers will adopt and adapt these in their own classrooms. The theme of SELES 2019, which will be held in September, will be “Back to The Future” where the emphasis will be on 21st Century teaching and learning.

(b) In September 2018, MESTR organized the English and STEM Baram Outreach Programme that involved 1,546 students from eight schools.

To understand the actual situation with respect to the teaching of English and STEM in our schools, MESTR is planning to undertake a “Baseline Research for English and STEM”.

Tuan Speaker, since the establishment of the Ministry in May 2017, MESTR has organised several education activities/ programmes as follows:

Enhancing Science, Technology, Engineering & Mathematics (STEM):

MESTR has organised several initiatives to enhance our performance in STEM in collaboration with the Sarawak Education Department, universities, NGOs and corporate organisations.

Together with the Sarawak Education Department, MESTR has been conducting training of non-option teachers (that is, teachers who are not trained to teach the subject) for Science and Mathematics, since 2018. The objective is to ensure that our Science and Mathematics teachers are equipped with up-to-date skills, content and pedagogical knowledge in teaching these subjects. This is very important because if students are taught using the wrong approach during their formative years, they are likely to lose interest in the subjects, and this damage may be irreversible.

Summary of activities:

(a) Training of Trainers (ToT) for 43 key personnel in mathematics and 90 key personnel in science since 2018; (b) 80 non-option science teachers were trained in 2018, and a further 300 teachers will be trained in 2019 to enhance their competencies in teaching science (through the Workshop on Content Knowledge and Pedagogy); and (c) 302 non-option mathematics teachers will be trained in 2019 for the same purpose.

The State has spent RM170,000 on training of Science and Mathematics teachers.

To nurture and develop interest in STEM amongst our young school children, MESTR is grateful for the contribution of universities, Teachers Training Institutes (IPGs), corporate bodies, NGOs, State agencies, and schools in the State that have organised various activities to promote STEM. Among the notable activities include the establishment of Petrosains PlaySmart, STEM Playground, “Scienceploration”, Science & Maths Olympiads and Quizzes, Mentor programmes, TRIA (Training and Industrial Awareness Programme), and MyGEEK movement.

To support classroom learning, MESTR has implemented a pilot project to provide 20 schools in the Central Zone with special resources for STEM in English which include training of 55 teachers on the use of these resources. As the feedback from these schools is positive, MESTR intends to provide similar resources to 60 schools this year.

To ensure comprehensive and coordinated efforts to enhance STEM, the State has developed the Sarawak STEM Strategy with involvement of universities, NGOs and corporate bodies.

School Leadership Development

Tuan Speaker, strong leadership in schools is critical for excellent performance. For this, MESTR, JPNS, and Institute Aminuddin Baki (IAB) have developed customised training programmes for school leaders. Some activities/ programmes organised include:

(a) School Leadership Workshops; 543 (out of 1,265 headmasters) have been trained. MESTR hopes to cover the rest of the headmasters by August 2019. RM327,000 has been spent for this programme thus far. (b) We have conducted three conferences for headmasters in 2017 and 2018, covering all 1,265 headmasters in the state with a budget of RM1.5 million. MESTR is planning another Headmasters Conference for 2019 in Kuching.

Teaching Science and Mathematics in English

On the 24th of April 2019, during his meeting with YAB Chief Minister, the Federal Minister for Education offered Sarawak to be the first state to fully implement the teaching of Science and Mathematics in English. The Chief Minister has accepted the offer, and the onus is now on Sarawak Education Department (JPNS) and Sarawak government to execute this successfully. There are many challenges that need to be resolved first before we can implement this initiative. This includes the training of teachers, the production of resource materials, and the decision on the assessment and examination format that will be used and for the information, we have a total of 1265 schools, primary schools, out of which 152 have already followed the dual language programme and there are 222 Chinese primary schools.

Teaching Science and Mathematics in English

So if you were to take the remainder because Chinese primary schools they have already indicated that they do not want to follow this initiative. So that is the remainder of 891 primary schools if you were to follow this initiative.

So, these are not easy tasks as they require the acceptance of the parents, the readiness of the teachers, and the support of all parties concerned, especially the Ministry of Education (MOE). MESTR has started engagement with the Sarawak Education Department to obtain the number of teachers that have to be trained, the modules for training, and the resources required. We will also be engaging with all the relevant Institutions of Higher Learning (UNIMAS, UiTM, Curtin, Swinburne, and IPGs) to discuss the training of the teachers.

Although we plan to start the implementation in 2020, to be effective, it will be carried out in stages, beginning with roughly 30% of schools for the first year. We really request and need the support of all Ahli Yang Berhormat from both sides of this august House to convince their constituents to support this important initiative that will have significant impact on the proficiency in English in Sarawak. To carry out all these will require a substantial amount of funding. For that, we will work together with the Ministry of Education to get the funds.

Issues Relating to Education

Tuan Speaker, now I would like to respond to issues related to my Ministry raised by Ahli-Ahli Yang Berhormat in this august House. For the information of Ahli Yang Berhormat for Bukit Goram, Tasik Biru, Tanjung Datu, Murum, Meluan and Batu Danau, who have proposed the upgrading of dilapidated schools in their constituencies, I would like to inform them that the upgrading will depend on the availability of fund, and will be done in accordance with the priority that has been established by the Sarawak Education Department and Sarawak government.

RM1 Billion as a Contra to Sarawak’s Debts to be used for upgrading/repairing of Dilapidated Schools

Tuan Speaker, I am very, very reluctant actually to dwell on this issue. But since Ahli Yang Berhormat for Kota Sentosa did raised this matter in his debate, I feel I am obliged to response. The reason why I am quite reluctant is because the issue is still in negotiation.

On the 20th of February 2019, the Minister for Education met with YAB Chief Minister to discuss Sarawak’s offer to repay RM1 billion of its outstanding loan to the Federal government as contra payment for the repair of dilapidated schools in Sarawak. In the meeting, the Minister agreed:

(a) that the RM1 billion be paid as contra payment for Federal loan to Sarawak “to be utilised to fix dilapidated schools in Sarawak” (Borneo Post, 20th February 2019);

(b) a Special Committee comprising Ministry of Finance, Ministry of Education and Sarawak government be established to “to ensure the management of the fund is clean and a transparent process can be implemented” (Borneo Post, 20th February 2019); (c) that projects would be tendered through the Federal Tender Board; and (d) JKR Sarawak would be the implementing agency.

We were invited to a meeting at the Ministry of Finance on the 11th of March 2019, during which we were informed that the Federal Cabinet did not agree with the proposal for the repayment of the RM1 billion as contra payment. The Federal Cabinet instead wanted the RM1 billion to be paid into the Federal Consolidated Fund as advance payment, and that the disbursement would be made through the annual budget. This was confirmed through a letter which was received from the Ministry of Finance dated the 20th of March 2019. However, the State did not agree with the conditions stated on that letter, and subsequently we wrote a counter proposal to the Federal government on the 21st of March 2019.

Ahli Yang Berhormat for Kota Sentosa made a grand show in the Dewan in reading the letter from the Ministry of Finance. We do not dispute the letter. However, the State government is concerned about the consequence of paying the RM1 billion into the Federal Government Consolidated Fund. As a parliamentarian, Ahli Yang Berhormat for Kota Sentosa should know that once money is paid into the Consolidated Fund, it goes to the EPU and the Parliament to allocate budget from this fund for whatever purposes. This will definitely take considerable time and will delay the upgrading of schools that are already in critical condition. Further, there is no guarantee that the RM1 billion paid will be fully allocated for dilapidated schools in Sarawak, as the EPU and the Parliament can decide on how the money should be used.

Another concern of the State is that this RM1 billion should be over and above, I repeat over and above, the normal funding for upgrading of dilapidated schools in Sarawak. Ahli Yang Berhormat for Kota Sentosa’s allegation that the money would be misused by the State Government is totally baseless and malicious, and purely intended to obtain cheap political mileage. For his information, all school projects have always been under the Federal Tender Board, and the State has no say in the procurement process.

Yang Berhormat Dr Maszlee Malik, Minister for Education and Dato’ Dr Mohd Gazali Abas, Ketua Setiausaha (KSU) of MOE visited Yang Amat Berhormat Ketua Menteri again on the 24th of April 2019. He informed that MOE and the Federal government did acknowledge our concerns regarding the decision to pay the money to the Federal Consolidated Fund and for it to be disbursed through the annual budget. I repeat here, they acknowledged our concerns because it may not be disbursed for our purpose. During this meeting, Yang Berhormat Dr Maszlee and his Ketua

Setiausaha (KSU) made some proposals to break the impasse. These are

(a) That the RM1 billion be placed into a special account (vote), and not into the Federal Consolidated Fund; (b) A tripartite Committee consisting of the Ministry of Finance, Ministry of Education, and Sarawak Government would be established to manage the fund and to oversee the project; (c) An agreement would be signed between the Federal Government and Sarawak Government to ensure that the RM1 billion is spent only on dilapidated schools in Sarawak; (d) The procurement process would be managed by the State Federal Tender Board, not the State Tender Board; and (e) JKR Sarawak would be the implementing agency.

So, these were the proposals. We sincerely appreciate the efforts of the Minister for Education, Yang Berhormat Dr Maszlee Malik who shares our concerns over the dilapidated schools and the

quality of education in Sarawak. Yang Berhormat Dr Maszlee visited our YAB Chief Minister twice in trying to resolve the issue of dilapidated schools in Sarawak. We would to like put on record our sincere thanks and gratitude to YB Dr. Maszlee and his staff for their understanding, genuine and sincere efforts at resolving this issue, unlike the Honourable Member for Kota Sentosa who talks without knowing the full story and who does not offer any solutions to the issue. It looks like Yang Berhormat Dr Maszlee is more concerned about Sarawak than the Honourable Member for Kota Sentosa. I would appreciate that all Members of this august House from both sides please refrain from commenting on this issue while it is being negotiated.

Tuan Speaker, we will forward the following issues raised by Members of this august House to the Federal Ministry of Education for its consideration:

(a) Honourable Member for Telang Usan on the status of K9 School being categorised as Primary School in Long Bedian and the creation of new PPD in Telang Usan district; (b) Suggestion from Honourable Member for Daro to place Pegawai Pendidikan Pencegahan Dadah at all PPDs and schools in the State; and (c) The request from Honourable Member for Meradong for trained teachers for special students.

For the information of Ahli Yang Berhormat for Kabong, the Sarawak Government is concerned about problems faced by schools having two sessions. My Ministry together with Sarawak Education Department has conducted labs to identify these school:

(a) Schools with double sessions; and (b) High enrolment schools.

And I would like to highlight some. All together there are 41 secondary schools have been double sessions and among the worst are schools with enrolments bigger than some Universities:

(a) SMK Bandar Bintulu, 2,583 students, 36 classrooms but they have 71 classes; (b) SMK Baru Bintulu, 2,426 students, 24 classrooms but they have 76 classes; (c) SMK Bintulu, again Bintulu, 3,351 students. They have 55 classrooms but 100 classes. So, all are in Bintulu; and (d) SMK Kidurong, 1,910 students. They have only 48 classrooms but 86 classes.

These are the critical one. There are many others; altogether there are 41 secondary schools having double sessions.

On the issue of SK Abang Leman, the Ministry of Education has re-tendered the project on 25th April 2019.

For the information for Ahli Yang Berhormat for Balingian, SMK Balingian project is under tendering process. For SK Kenyana and SK Jebungan, the State Education Department (JPNS) is in the process of identifying and evaluating new sites for the relocation of those schools.

For the information of Yang Berhormat for Dudong, the enrolment of our students in Form 4 Science stream has increased from 19.7% in 2017 to 23.2% in 2018, and 24.3% in 2019. The State Government is tackling the issue in a serious and coordinated manner through the implementation of Sarawak’s STEM Strategy.

For the information of Ahli Yang Berhormat for Meluan, Program Ijazah Sarjana Muda Bahasa Iban has started since 2013 in IPG Kampus Rajang. The programme is also available at IPG Kampus Sarawak, Miri and IPG Kampus Batu Lintang, Kuching.

For the information of Ahli Yang Berhormat for Saribas, total replacement project of SK Sebemban, Spaoh has been approved under the first rolling plan, of 11th Malaysia Plan. The project has been tendered which closed on 18th March 2019. The award of the project to the successful tenderer will be known soon.

Technical Vocational Education Training (TVET) and Institutions of Higher Learning (IHL)

Tuan Speaker, in view of the fact that Technical, Vocational, Education and Training (TVET) is necessary to provide adequate supply of skilled workforce for Sarawak, my ministry has implemented several initiatives:

(a) Continuous promotion of TVET through activities such as the annual Sarawak Career and Training Fair (SCaTFair) and the biennial TVET Symposium; (b) Assisting in resolving issues related to introduction of new programs, enrolment of students and students industrial attachment for TVET; (c) From 2014 to 2018, Sarawak Government has spent RM20.8 million to provide study loans to 4,352 TVET students; and (d) To enhance the profile of TVET, Sarawak government plans to organize the 2nd Sarawak Worldskills Competition at the end of this year.

Institutions of Higher Learning

Organise focused promotion to increase student enrolment in Institutions of Higher Learning in which Sarawak has an interest (Swinburne, CURTIN, UCTS, Kolej Laila Taib and i-CATS).

The government intends to promote Sarawak as an attractive destination for international students. Towards this, the state will organize a conference for international marketing agents of our local institutions of higher learning.

Nurture and Promote a Culture of Creativity and Innovation

As creativity and innovation are very important for future economic progress of Sarawak, MESTR is working very closely with Sarawak Multimedia Authority to nurture and develop innovations and creativity amongst our students.

The activities include:

(a) Collaboration with UiTM to organise the biennial Sarawak Innovation, Invention and Design Expo (SIIDEx). Preparations are ongoing for the finals scheduled for September 2019; (b) Collaboration with DreamCatcher and UNIMAS to organise the Innovate Sarawak Design Challenge. 64 teams (17% of total participation nationwide) from Computer and IT Faculties in Sarawak participated in this competition; and (c) MESTR is also organising similar programs namely the Young Innovators Sarawak Challenge and the Junior Innovators Sarawak Challenge for Secondary schools and Primary schools, respectively. We are grateful to DreamCatcher, Chumbaka and All Aboard for their support.

Issues Relating to TVET and Institutions of Higher Learning (IHL)

For the information of Ahli-Ahli Yang Berhormat for Lingga and Kalaka who have requested for the establishment of skills training centre such as CENTEXS, Community Colleges and Giat Mara, it is not feasible for the government to establish these facilities in all constituencies. Apart from financial consideration, it is necessary to also consider the availability of trained teaching staff,

sufficient enrolment of students and opportunity for industrial placement/internship to ensure that the training is in line with the needs of the industry, so that the trainees will be employable.

For the information of Ahli Yang Berhormat for Layar, CENTEXS will explore the feasibility of offering a certificate in surveying programme in one of its campuses.

Workforce Development

MESTR has implemented, the online Sarawak Workforce Information System (SWIS), to collect data on current and projected workforce supply and demand.

The system which was launched on 16th March 2019 by the Chief Minister of Sarawak, is currently being promoted to both industries and institutions. To date, 56 companies and 53 institutions have registered with the system. We hope more companies and institutions will register with us to use the system. MESTR is providing on-going training throughout Sarawak for all potential users.

MESTR also conducts studies to obtain data on specific manpower requirement for selected industries. The study for the Construction industry was completed in 2018 and is awaiting endorsement of the Steering Committee. For 2019 we will conduct a study on “Human Resources and Skills Requirement in the Logistic Industry”.

MESTR will continue to collaborate with relevant parties such as the Statistics Department, Labour Department and Institute of Labour Market Information and Analysis (ILMIA) to ensure availability of workforce data to meet the need of the various state agencies for their planning purpose. Science and Technological Research

The Sarawak Research and Development Council (SRDC) Ordinance, 2017, came into force in 2018. In January this year, Sarawak government has recruited the General Manager and Deputy General Manager of the Council. In the first four months, SRDC, this is not Sibu Rural District Council, this is Sarawak Research and Development Council management has engaged, and is continuing to engage with local research agencies and universities to take stock of the R&D activities in Sarawak. Conclusion

Tuan Speaker, there is a saying; only a complete fool makes accusation based on hearsay. Do not assume everything you hear to be true, and never accuse without knowing all the facts or both sides of a story. The best option is to stay silent if you do not witness the thing yourself.

I heard many-many statements from the opposition, truth hurts. Yes, truth may hurt for a while, but a lie hurts forever.

So, for those from the other side of this House, if you stop telling lies about GPS, I repeat, if you stop telling lies about GPS, we will stop telling the truth about Pakatan Harapan.

The truth hurts but lies hurt even more. They hurt excruciatingly painful which subsequently may even affect the moral standard of our society adversely. So, the truth hurt but lies hurt forever.

Throughout the years, governments have been overthrown either through revolutions or elections. This is to give opportunities to a new government to solve the many problems affecting the people. The people’s hope is that the new government will be sincere, transparent, and work hard for the sake of the people.

In May 2018, to be exact, 9th May 2018, Malaysians have given the mandate to Pakatan Harapan to form the new government in the Federal level. The hopes and expectations of Malaysians are very-very high are that Pakatan Harapan will deliver its promises in its election manifesto.

Unfortunately, the performance of the new government in its first one year has been very-very disappointing. They seem to be stuck in their election campaign mode and keep on blaming the previous government instead of developing effective strategies to fix our economy, resolve the many problems faced by the rakyat and bring growth to the nation.

As I said during my winding up speech in the last session of this august House, the ball now is on your feet. They should stop complaining about the referee, stop complaining about the players, stop complaining about the playing field, but start to kick the ball and score the ball or be prepared to be changed by the next parliamentary election. Thank you.

Tuan Speaker, I would like to also here express my appreciation to Tuan Speaker and The Deputy Speaker and all those who are working here for your hardwork to conduct this sitting for the past few days.

And, before I sit down, I would like to say selamat berbuka puasa, and Selamat Hari Raya, and also Selamat Gawai for those Dayaks who is going to celebrate Gawai “Selamat Ngintu Andu Gawai”. Terima kasih.

Deputy SpeakerEN

With respect, I invite Honourable Dato Sri Wong Soon Koh, Minister of Finance II and Minister of International Trade and E-Commerce, to deliver the winding-up speech.

Dato Sri Wong Soon KohPSBMinister of Finance II · Bawang Assan

Tuan Speaker, before I begin with my Winding Up Speech, I would like to express my utmost appreciation to Tuan Yang Terutama Yang di-Pertua Negeri Sarawak, Tun Pehin Sri Haji Abdul Taib Mahmud for officiating the First Meeting of the Fourth Session of the Eighteenth Dewan Undangan Negeri on the 29th of April 2019. His Excellency’s address certainly serves as invaluable guidance in discharging our duties and responsibilities in transforming Sarawak into a high-income economy by 2030 and foremost, ensuring Sarawak continues to be a prosperous and harmonious State.

I would also like to express my congratulations to Yang Amat Berhormat Chief Minister for having led Sarawak with such able leadership and high commitment to bring greater development to Sarawak. Under his leadership, we have seen the conviction of Sarawak Government in intensifying its effort to initiate and accelerate strategic and critical development programmes throughout Sarawak under its development initiatives which cover, among others, the rural transformation programme, digital economy initiatives and various infrastructure and public amenities projects. These initiatives are none other than for the wellbeing of the rakyat and for the economic growth of the State as a whole. No doubt that Sarawak Government will continue to make significant advancement to further strengthen the State’s economy and to attain new heights of development. Economic Performance 2018 and the Outlook for 2019

Tuan Speaker, I would now like to update this august House on the latest economic performance for the year 2018 and the outlook for 2019.

Global Economy – Performance 2018

The global economy softened at 3.6% in 2018 due to slow down of growth momentum in the second half of the year. The greater uncertainties created through the escalation of trade conflicts especially between the United States and China have resulted in weakened industrial production

across Europe and Asia. The implementation of higher tariffs by major economies has also pulled down the trade growth and investment.

At the same time, the volatility of commodity prices and tightening of financial conditions in key economies had caused most of the major advanced and regional economies to grow modestly in 2018. With the exception of the United States which grew at 2.9%, economic growth in other major advanced economies had expanded at a slower pace compared to 2017. The economic growth of the Euro Area declined from 2.4% in 2017 to 1.8% in 2018 owed to the weakened business confidence and investment as well as slower global trade.

Japan economy registered a modest growth of 0.8% in 2018 as manufacturing output fell. The impact from Typhoon Jebi that hit the country in the third quarter of the year also had weighed on Japan’s economic performance. As for United Kingdom, the uncertainty over Brexit has affected business sentiments and investment which had slowed the economic growth to 1.4%.

Growth in the emerging market and developing economies also moderated to 4.5% in 2018 as market sentiment deteriorated and some economies experienced large and persistent capital outflows, most notably in Argentina and Turkey. In China, investment, industrial production and export had also weakened. Outlook for 2019

The global trade developments will remain the key risk to the performance of the global economy in 2019. The global weaknesses and the lingering uncertainty of trade tensions are expected to persist into the first half of the year. The International Monetary Fund (IMF) has projected the global economy to slow down to 3.3% as the advanced economy decline from 2.2% in 2018 to 1.8% in 2019. Growth in the emerging and developing economy is also expected to slow down at 4.4% in 2019.

The United States economy is expected to soften to 2.3% in 2019 whilst the United Kingdom economy is expected to grow at only 1.2% given the prolonged uncertainty over the unresolved Brexit outcome. During the same period, growth in the Euro Area is set to moderate to 1.3%. Japan however, is projected to perform better at 1.0%, strengthened by its additional fiscal support.

The financial regulatory tightening and trade tension are expected to further bring down the growth of China economy to 6.3% in 2019. On contrary, India economy is expected to pick up from 7.1% in 2018 to 7.3% in 2019, reflecting the continued recovery of investment and expansionary stance in its monetary policy.

National Economic Performance 2018 and Prospects for 2019

Tuan Speaker, the Malaysian economy expanded moderately at 4.7% in 2018. Growth was underpinned by domestic demand particularly from the private sector expenditure. The external sector remained resilient despite increasing challenging global economic environment. In spite of weakness in export for commodity, the growth in export was reinforced by demand for semi-conductors and other manufactured products.

Private consumption recorded a growth rate of 8.1% in 2018 driven by favourable wage and employment growth. The three-month tax holiday arising from zero-rated of the Goods and Services Tax from the 1st of June until the 31st of August 2018 and the fixing of the retail fuel price of RON95, had encouraged household spending. For the same year, private investment however, grew at a slower pace of 4.5% due to uncertainty stemming from both external and domestic developments.

With reprioritisation of expenditure by Federal Government, public consumption grew modestly at 3.3% in 2018 while public investment contracted by 5.2%, mainly attributed by lower spending by public sector.

On the supply side, most economic sectors recorded an expansion in 2018, with the exception of commodity-related sectors. Growth was led by the services and manufacturing sectors which expanded at 6.8% and 5.0%, respectively.

Tuan Speaker, Malaysia economy is projected to grow between 4.3% to 4.8% in 2019, underpinned by the gradual recovery from unanticipated commodity disruptions the year before. On the demand side, private spending continues to drive growth, supported by private consumption and improved private investment. The continued reprioritisation of Federal Government spending continues to weigh on public expenditure.

Sarawak Economic Performance 2018 and Prospects For 2019

Tuan Speaker, I shall now move on to the Sarawak economy. The State economy grew at 4.6% in 2018, sustained by growth in domestic demand both from the public and private expenditure.

Supply Side

Dato Sri Wong Soon KohPSBMinister of Finance II · Bawang Assan

Services Sector

The services sector expanded by 6.9% reinforced by the wholesale and retail sub-sector particularly in the third quarter of 2018 as better consumer sentiments spurred spending. Growth in trade related activities also supported the growth in the transport and storage sub-sector. The continued demand for data communication also drove the growth of the information and communication sub-sector. Besides that, the finance, insurance and business services sub-sector remained strong in the household and business segments. Growth in the services sector is projected to sustain in 2019. Construction Sector

The construction sector grew strongly at 14.3% in 2018 due largely to the expansion in civil engineering sub-sector as well as the residential sub-sector. With the continued emphasis on infrastructure and utility development by the State Government, the construction sector is expected to remain robust in 2019, with growth projected at 16.8%, The projects, amongst others include Rural Transformation Projects, water and electricity supplies and road networks.

Manufacturing Sector

The manufacturing sector registered a slower growth at 3.1% in 2018 compared to 3.5% in 2017. Despite the increase in production of electrical and electronic products in 2018, the production of refined petroleum and petroleum products, mainly LNG slowed down given the disruption in supply of natural gas. Nevertheless, the production of LNG is expected to gain back its momentum in 2019 with the recovery from the disruption. Growth in the manufacturing sector is projected at 4.0% in 2019. Mining and Quarrying sector

The mining and quarrying sector also expanded at a slower pace of 2.6% in 2018. Demand for oil was slow coupled with the unplanned maintenance shutdown which had affected the production of crude petroleum. However, the mining and quarrying sector is projected to experience a turnaround in 2019, where the recovery in the production of natural gas will support and partly offset the declining output of crude petroleum. Thus, this sector is projected to grow modestly at 2.5% in 2019.

Agriculture Sector

Growth in the agriculture sector moderated at 1.8% in 2018. Production of crude palm oil experienced a drop especially in the first half of the year before it started to pick up beginning of August 2018. Overall, the production of crude palm oil and palm kernel oil increased marginally at

1.2% and 0.5%, respectively. It is expected that the production of crude palm oil will regain its momentum in 2019, supported by better yield and increased mature areas. The agriculture sector is projected to grow at 2.3% this year. Demand Side

Tuan Speaker, on the demand side, Sarawak total trade registered a growth of 4.4% from RM137.7 billion in 2017 to RM143.7 billion in 2018 against the backdrop of mixed commodities prices. Export expanded marginally by 0.2% in 2018. This was largely attributed to the growth in export value for crude petroleum and petroleum products. Import on the other hand registered a strong double-digit growth of 14.5% on account of increased in importation of intermediate and capital goods. This is in tandem with the increasing of infrastructure development activities in the State. Better external demand performance is expected in 2019 with anticipation of recovery in commodities prices and continued progress of infrastructure development in Sarawak.

Private Consumption

Private consumption expanded at 4.8% in 2018 mainly supported by stable growth in employment and wages and increased household spending. In 2019, private consumption is projected to grow by 3.1% as consumption spending is expected to remain resilient due to subdued inflation.

Public Consumption

Public consumption expanded at 4.2% in 2018 attributed to spending on emoluments. The special incentive payment to the State civil servants in December, 2018 had contributed to higher public consumption as well as household spending. Nevertheless, public consumption is expected to grow moderately to 2.8% in 2019 mainly attributable to the reprioritisation and rationalization of Federal Government spending. Public Investment

Public investment grew at 5.1% in 2018 supported by higher State Government spending as the State embarked in accelerating the development of public utilities, basic infrastructure works and digital economy initiatives throughout the State. Public investment is projected to expand further in 2019 driven by higher capital expenditure by the Sarawak Government which will benefit all sectors of the economy. Private Investment

Tuan Speaker, private investment grew at 5.2% in 2018 underpinned by the implementation of on-going and new investment projects in the State. A total of RM8.7 billion of investment was approved during the year. The higher public investment particularly for the provision of infrastructure development, provides the necessary enablers to support private investment in the State. The growth in both public and private investment brings about synergistic progress that spin-off the State economy in 2019. Overall, the State economy is expected to grow between 4.5% to 5.0% in 2019.

Labour and Employment

Tuan Speaker, the labour market remained stable in 2018. Job vacancies of 94,149 were reported to the Labour Department in 2018, an increase of 9.2% from 2017. These vacancies were mainly in the agriculture, construction and manufacturing industries. The labour market condition is expected to remain stable in 2019 with unemployment rate below 4.0%.

Financial Performance Of The State 2018 And First Quarter 2019

Dato Sri Wong Soon KohPSBMinister of Finance II · Bawang Assan

Tuan Speaker, let me first highlight the 2018 financial performance of the State.

Revenue, 2018

The State registered a total revenue of RM7.201 billion in 2018 contributed mainly from the following sources:

(a) Dividend from investment; (b) Cash compensation in lieu of oil & gas rights; (c) Interest from money markets; (d) State Sales Tax; (e) Land premium; (f) Forests royalty; and (g) Water royalty.

Expenditure, 2018

Ordinary Expenditure, 2018

Total Ordinary Expenditure for 2018 was RM7.091 billion. Out of this amount, RM2.641 billion was for operating expenditure while a sum of RM4.450 billion was appropriated to the Development Funds Account. For the year, the State had recorded a surplus of RM110 million due to higher than expected revenue and stringent control and discipline in managing the State’s financial affairs.

Development Expenditure, 2018

For development expenditure, the State has spent a total sum of RM8.326 billion or 89.4% out of RM9.317 billion approved allocation in 2018. In comparison, a sum of RM4.289 billion was spent in 2017. The substantial increase in development expenditure in 2018 reflected the efforts of the State Government in accelerating development initiatives to bring greater development for Sarawak.

Financial Performance of The State, First Quarter 2019

Tuan Speaker, now, I would like to highlight on the financial performance for the first quarter of 2019. Revenue, First Quarter 2019

Revenue collection for the first quarter of 2019 amounts to RM2.219 billion, which represents 21.1% of the estimated revenue of RM10.513 billion for the year. The revenue collection was mainly received from cash compensation in lieu of oil and gas rights. The revenue collection is expected to pick up towards the later part of the year.

Expenditure, First Quarter 2019

Ordinary Expenditure

For the first quarter of 2019, RM2.874 billion or 27.7% of Ordinary Expenditure of RM10.390 billion has been expended. Out of this, RM0.799 billion was for operating expenditure while the balance of RM2.075 billion was appropriated to the Development Funds Account.

Development Expenditure

As for the development expenditure, RM1.691 billion or 18.6% out of the approved allocation of RM9.073 billion has been expended for the first quarter of 2019. Development expenditure is expected to increase progressively in tandem with the on-going activities during the year.

Financial Management

Tuan Speaker, I am pleased to report that the State financial account for the year ended 31st December 2018 has again been accorded with an unqualified report. This is the 17th consecutive year that the State earned the Clean Bill of Financial Health.

The State’s commendable investment credit ratings have also been re-affirmed at A3 and A-by the International rating agencies, Moody’s and Standard and Poor’s, respectively.

These achievements are clear testimony of the State continuous sound financial management in exercising financial prudence and financial discipline at all levels. We will continue to strengthen our strategic financial management by benchmarking and adopting best practices, leveraging on technology advancements as well as building capacity to achieve operational excellence and good governance.

In light of the present global economic turmoil that posts challenges to our financial survival and economic resiliency, it is critical for us to continue adopting and exercising good financial practices and good governance, upholding the principle of disciplined and responsible financial management.

I would also like to express my appreciation to all Controlling Officers, Heads of Departments, and CEO’s of agencies and Government-Linked Companies in continuing to work closely and cohesively as well as collaborating with the private sector to optimize public value and to deliver better results for the people of Sarawak.

State Development Initiatives

Tuan Speaker, the State places strong emphasis on intensifying its infrastructure development initiatives to achieve the State’s aspiration to have a sustainable and balanced development throughout the State particularly between the urban and rural areas. The State is serious in these efforts and this is reflected in its commitment on public expenditure for infrastructure and public utilities development which is at a record high this year and expected to continue in the next few years.

As what I have mentioned earlier, the public investment would boost the growth in construction sector as well as benefitting all sectors of the economy and ultimately, spur the development of the State. Eleventh Malaysia Plan State Funded Projects

Under the Eleventh Malaysia Plan, the State Government has approved a total ceiling of RM37.1 billion to implement 1,424 programmes and projects throughout the State. Out of this, 911 are physical projects while the remaining 513 are non-physical projects.

As of March 2019, out of the 911 physical projects, 329 projects have been completed while the remaining 582 projects are still at various stages of implementation.

Rural Transformation Project (RTP)

Rural Transformation Project is a people centric projects introduced in 2015. This project aims, among others, to expedite the development in the rural areas and to ensure the people in the rural areas be provided with better infrastructure and facilities.

As of March 2019, a total of 9,833 projects have been approved under RTP with the cumulative allocation of RM2.46 billion. Out of this, 5,877 projects or 59.8% have been completed while the remaining 3,956 projects are still at various stages of implementation.

Projek Rakyat

Projek Rakyat is another initiative by the Sarawak Government to embark on high impact projects aims at providing better public facilities and infrastructure, including housing and social amenities as well as road network.

The Sarawak Government had set aside a sum of RM1.0 billion under the Mid Term Review of the 11th Malaysia Plan for the implementation of various Projek Rakyat. In this respect, State Development Coordination Committee chaired by Yang Amat Berhormat Chief Minister had been set up to monitor the progress of these high impact projects to ensure speedy and timely project implementation. Projects Funded via Alternative Funding

List of projects to be funded under alternative funding covers, amongst others, roads network, water grid, rural electrification scheme and regional development projects.

Leveraging on alternative funding raised through Development Bank of Sarawak (DBOS) and Capital Market in financing these initiatives would allow the State to have the fiscal and financial flexibility in stepping up the implementation of these high impact development initiatives. Indeed, this fiscal and financial need are managed under good governance practices, strict financial discipline and prudence at all time.

Tuan Speaker, I would like to take this opportunity to urge all the implementing agencies to take proactive and diligent measures to ensure that programmes and projects approved are implemented expeditiously and completed within the stipulated time frame and in accordance to work specifications without compromising on the quality. Timely completion of the projects could avoid cost overrun and ensure the benefit of the projects can be immediately enjoyed by the rakyat.

Federal Fund Project

Dato Sri Wong Soon KohPSBMinister of Finance II · Bawang Assan

11th Malaysia Plan

Under the 11th Malaysia Plan, a sum of RM17.2 billion was approved by the Federal Government to implement various programmes and projects in Sarawak. With the development gap faced by Sarawak, this amount is obviously far from enough to develop Sarawak to be at par with our counterparts in Semenanjung Malaysia.

Equitable Federal Allocation

In gearing towards a high income and developed State status by 2030, Sarawak needs more allocation especially for the provision of basic infrastructure and amenities such as roads and bridges, schools, clinics, rural water and electricity supplies. Hence, I would urge the Federal Government to:

(a) implement all projects that have been approved for Sarawak; and (b) provide more allocation to assist the State in stepping up its efforts particularly in the development of the rural areas which are still largely under developed and lagging far behind as compared to our counterparts in Semenanjung Malaysia.

We must be accorded a fair and equitable share of the Federal development fund. The Federal Government must take cognisance of the significant contribution by Sarawak in terms of tax collection and oil and gas revenues to the Federal coffers.

State Road Maintenance

Tuan Speaker, I would like to respond to the issue with regard to the State road maintenance fund raised by Ahli Yang Berhormat for Kota Sentosa. For the State Road Maintenance Trust Fund was established to account for the grant provided by the Federal Government as stipulated under Article 109(1)(b) of the Federal Constitution. The fund is used for the repair and maintenance of State roads throughout Sarawak which are implemented mainly by Jabatan Kerja Raya and Local Authorities. The usage of the fund is governed by the guidelines issued by Federal Ministry of Finance.

Tuan Speaker, it is important to highlight that the account of the State road maintenance trust fund is audited every year by the Auditor General. It is also reported in the annual Auditor General’s report which is tabled every year to the Parliament and Dewan Undangan Negeri. Thus, rest assure the question of transparency and integrity of the account is undisputable.

For the information of this August house, for the past 4 years that is from 2015 to 2018, the State Government received a total grant for road maintenance of RM3.318 billion from the Federal Government. For the same period, a total sum of RM4.152 billion was allocated to all the implementing agencies which is obviously more by RM834 million than what the Federal Government had allocated to the State.

Out of the amount allocated to the implementing agencies, RM3.818 billion or 92% was spent. Again, this actual expenditure exceeded the total amount that we received from the Federal Government. So, to say that the money given was not spent but kept in the account is rather speculative and baseless. Even, the Auditor General in his annual report has acknowledged the satisfactory performance of the State road maintenance by the Sarawak Government.

With regards to the balance in the State road maintenance account, I wish to highlight that the sufficient balance in the road maintenance account is crucial to facilitate and enable the implementing agencies of the State to do better planning and implementation of the road maintenance programmes. Hence, having sufficient balance in the account does not mean that it is not utilized or maintenance works on the ground are not implemented. To make a statement that excess balance in the account associated to work not done on the ground is not true and is rather naive on the part of Yang Berhormat for Kota Sentosa.

Tuan Speaker, it is important for me to highlight this August house that the disbursement of grant for road maintenance by the Federal Government to the State is made on monthly basis. From perspective of project management, this is not at all effective in meeting the needs of the project planning and project implementation process. In this regard, Ahli Yang Berhormat for Kota Sentosa should discuss with his counterpart in the Federal Government particularly the Ministry of Finance to disburse the grant in one lump sum at the beginning of the year to facilitate the State to plan and implement the road maintenance programmes more effectively and efficiently.

Tuan Speaker, as I mentioned before this august House, we in the Government welcome different views in debates but the opposition must bring forth the views with the correct knowledge with facts and figures and indeed with a sense of discipline and responsibility. Ahli Yang Berhormat from the opposition must know that with most things rights and privileges ...(interruption)

Deputy Speaker

Minister, are you giving way for clarification?

Dato Sri Wong Soon KohPSBMinister of Finance II · Bawang Assan

Okay.

Deputy Speaker

Honourable Member for Pelawan.

Thank you Tuan Speaker, Honourable Member for Kota Sentosa is not here today, but then I read through the hansard, what he said was very valid. He actually said that the Auditor General has made a remark on the report of 2012 of the trust fund, that the Government has failed, the State Government has failed their duty to table such report in Dewan Undangan Negeri. I think that is a very valid question. As an ADUN, we are supposed to ask questions like this. As what the bargain has to say; okay as at 2015 it was RM779 million, 2016 RM822 million and 2017 RM847 million. Dato Sri, you came from Sibu Central Region, you know very well. The road in Sibu, SMC every time we ask for road maintenance or upgrading, no money. This RM847 million here, I think the money should be well spent to serve the rakyat isn’t it Dato Sri? And Auditor Report on the remark by Auditor Report, Auditor General can you explain that? Why did it take you so long from 2012 until 2019 now? Seven years to table this report. Thank you.

Dato Sri Wong Soon KohPSBMinister of Finance II · Bawang Assan

Tuan Speaker.

Deputy Speaker

Yes.

Dato Sri Wong Soon KohPSBMinister of Finance II · Bawang Assan

The State Government has to look after all the 26 Councils throughout the State and not just Sibu...(interruption)...

Deputy SpeakerEN

Challenger. Honourable Minister is explaining.

Dato Sri Wong Soon KohPSBMinister of Finance II · Bawang Assan

Tuan Speaker, as I said the State road maintenance funds is audited every year by the Auditor General. It is also reported that the Auditor General’s Report is tabled every year to the Parliament and also to Dewan Undangan Negeri. So you can see that there is transparency and integrity of the account maintenance. And also, as I said, and also…(Interruption)

Deputy Speaker

Ahli Yang Berhormat for Pelawan, let the Minister explain.

Dato Sri Wong Soon KohPSBMinister of Finance II · Bawang Assan

As I said Tuan Speaker, that sometimes, we the State Government has to grant more than what was required, exceeding, as I said earlier by a total grant for road maintenance from 2015 to 2018 was only RM3.318 billion but the total sum of RM4.152 billion was allocated to the implementing agencies which is a lot more than what was given. In fact, RM834 million. Let me continue Tuan Speaker…(interruption)

…(inaudible)…

Deputy Speaker

Let the Minister continue. You have raised the question. Let the Minister respond, okay?

Dato Sri Wong Soon KohPSBMinister of Finance II · Bawang Assan

As I said, Honourable Members of the Pakatan Rakyat should really talk to YB Lim Guan Eng so that he should disburse the grant in one lump sum not monthly. How do you expect us to do the planning, when the money is distributed only monthly. They should be given in one lump sum to enable the State to plan and implement the road maintenance program more effectively.

As I mentioned before in this august House, we in the government side, welcome different views and debate but as I said, the Opposition must bring forth their views with the correct knowledge and so on.

Tuan Speaker, if you go through, sit down…(interruption)

…(inaudible)…

Deputy Speaker

Let the Minister explain.

Dato Sri Wong Soon KohPSBMinister of Finance II · Bawang Assan

I have no time, I have explained. If you were to go through the Hansard for the past few years, you will find many incidences where the Opposition Members particularly the Honourable Member for Kota Sentosa had committed so many offences under Standing Order and the Privileges Powers Ordinance, 2007.

Tuan Speaker, I am sure the Honourable Members of the Opposition know exactly what offences they are likely to commit and the punishment or penalty for their offences under Standing Order and also under the Privileges and Powers Ordinance, 2007 but they were purposely and deliberately flout the rules to invite the Red Cards.

Tuan Speaker, if the Red Cards are not issued they get away. They achieved what they set out to do. That is to discredit the government…(interruption)

Encik David Wong Kee WoanDAP · PHPelawanEN

Mr Speaker, point of order. Clarification…(inaudible)…

Deputy Speaker

What point of order?

Dato Sri Wong Soon KohPSBMinister of Finance II · Bawang Assan

No point, no need to clarify. I am making a point. You listen. It is very clear.

Deputy Speaker

Which Standing Order are you looking at? Which Standing Order?

Dato Sri Wong Soon KohPSBMinister of Finance II · Bawang Assan

You listen. I said Tuan Speaker, if the Red Cards are no issue they get away. They achieved what they set out to do. That is to discredit the government, bringing the government into public ridicule. Sit down, please.

Point of order. Clarification.

Deputy Speaker

Which point of order?

I am rising on 33 (a). “No member shall interrupt another member except by rising to a point of order”.

Deputy Speaker

Point of order. Which point of order?

Improper motive. He said the Opposition knew that we are going through all this but we want to make a political point. That is improper motive. When we speak in this House as a Member, elected Members, we speak for all Sarawakian and the Minister, you have to understand, this House is to make the administration to account and these are monies belongs to Sarawakian and not the administration. Answer me? Why 12 years if you did not table the report?

Dato Sri Wong Soon KohPSBMinister of Finance II · Bawang Assan

As I said it is inspected by the Auditor General every year and it is tabled in this Dewan Undangan Negeri.

YB Encik David Wong Kee Woan:…(inaudible)…

Deputy Speaker

Honourable Member for Pelawan you have…(interruption)

Dato Sri Wong Soon KohPSBMinister of Finance II · Bawang AssanEN

Mr Speaker…(interruption)

Honourable Encik David Wong Kee Woan:…(inaudible)…

Deputy Speaker

Honourable Member for Pelawan, you let the Minister explain, please. He is explaining.

Dato Sri Wong Soon KohPSBMinister of Finance II · Bawang Assan

I said Members of the Opposition, particularly some of them would purposely or deliberately flout the rules to invite for the Red Cards. As I said if the Red Cards are not issued, they get away. They achieved what they set out to do namely to discredit the government, bringing government into public ridicule. If we issue the Red Cards, they surely could be suspended or referred to the Committee of Privilege.

Then they would become heroes, they would become martyrs. The Government would then be blamed for oppressing the Opposition. It looks like either way they win in the past few years. As you know, I play the dutiful role to discipline some of the Opposition Members particularly Member for Kota Sentosa. I think he was suspended from the Dewan three times and including all the others maybe ten times. In this process, I was branded a motion king as alleged the other days, of course by the Honourable Member for Kota Sentosa. Branded a motion king and oppressor and was called many names including a stooge to the Chief Minister, a puppet of the Government and a traitor to the people who want their voices to be heard.

Tuan Speaker, Ahli Yang Berhormat for Kota Sentosa continues to harp on the Government contribution towards approved agency trust fund. Again in his debate on TYT address, on 2nd of May, he raised the issue alleging that I quote; “Is this another 1MDB scandal in the making”?.

Tuan Speaker, we all know that the State Government and the State Financial Authority have instituted legal action for defamation against the Honourable Member for Kota Sentosa. Since justification has been pleaded by him as a defence to the Federal, to the Government suit, he should not have raised the same issue and should wait for the trial of the court, of the case, to substantiate his defence. In the meantime, Ahli Yang Berhormat for Kota Sentosa should respect that the matter is sub judice. He should wait for the day in court which will ultimately decide if he could substantiate his allegations. And so Tuan Speaker since this issue of the trust fund raised by Ahli Yang Berhormat for Kota Sentosa is a matter which is related to the Government defamation suit against Ahli Yang Berhormat for Kota Sentosa which is still pending in Court, I would therefore refrain from discussing the issue as it is sub judice and the Standing Order 32(2) prevents me from dealing with the issue raised by Ahli Yang Berhormat.

Tuan Speaker, if some opposition members are adamant on flaunting rules again and again perhaps more severe punishment ought to be instituted. Maybe we should consider more severe penalty not only suspend them from the House but also do away with their allowances. Perhaps in this way we are able to uphold or at least, I think a heavier penalty would add as a deterrent to the more recalcitrant behaviour of some of the opposition members. Only then perhaps with heavier penalty we can uphold proper conduct and good parliamentary practices.

In conclusion, Tuan Speaker, I would also like to express my utmost appreciation to your good self, both Tuan Speaker and Dato Deputy Speaker for having capably and successfully conducted another sitting in this august House. My sincere thanks also goes to all Government officers for their hard work, commitment and dedication.

Finally, I wish all our Dayak friends, Dayak colleagues and friends Selamat Hari Gawai, Gayu Guru Gerai Nyamai and to all our Muslim colleagues and friends Selamat Berpuasa and Selamat Hari Raya Aidilfitri.

Dr. Ting Tiong ChoonDAP · PHPujut

…(inaudible)…

Dato Sri Wong Soon KohPSBMinister of International Trade and E-Commerce · Bawang Assan

Minister for Finance, Chief Minister will answer your question.

Deputy SpeakerEN

Honourable Members, with respect, I invite Honourable Dato Sri Wong Soon Koh, Minister of International Trade and E-Commerce, to deliver the winding-up speech.

Dato Sri Wong Soon KohPSBMinister of International Trade and E-Commerce · Bawang Assan

Tuan Speaker, terlebih dahulu saya ingin mengucapkan setinggi-tinggi penghargaan dan terima kasih kepada Tuan Yang Terutama Yang di-Pertua Negeri Sarawak atas ucapan perasmian yang memberi semangat dan galakan kepada pengurusan Kerajaan untuk terus membangunkan ekonomi negeri dan rakyat.

Tuan Yang Terutama juga menyokong usaha Kerajaan untuk mengembalikan hak Sarawak sebagaimana yang termaktub dalam MA63 semasa penubuhan Malaysia. Beliau juga menyarankan agar Kerajaan terus memberi perhatian kepada pembangunan infrastruktur luar bandar termasuk meningkatkan capaian internet berkelajuan tinggi sejajar dengan usaha pembangunan ekonomi digital dan eDagang in Sarawak.

Tuan Speaker, this year is the second anniversary of the Ministry of International Trade and eCommerce. Although we are still in the infant stage, I am pleased to say that my Ministry has come a long way in achieving the intended objectives of the formation of the Ministry.

As an organisation, my Ministry has formulated strategies and implemented programmes and projects to empower our people with confidence in doing both international trade and eCommerce.

It has allowed some of our people to increase their daily business activities and raise their standard of living. As such, we should maintain the unity of our people and the stability of our State as it is the pillar for us to develop and move forward towards a high income and developed State by 2030.

Therefore, I urge all members of this august House to rally behind our Honourable Chief Minister and help to develop Sarawak and restore the eroded State rights under the constitution. This is very important for us to reaffirm the investors and our trading partners that we in Sarawak can make more independent decisions which are more business friendly than other States in Malaysia. Trade Performance

Global Trade

Tuan Speaker, my Ministry will continue monitor the development of global trade and trade activities. This is important to prepare the State in mitigating detrimental impacts as well as to enhance our competitiveness to remain resilient in the global trade.

The global economic growth is projected to soften from 3.6% in 2018 to 3.3% in 2019. The forecast of 2019 is revised downward by the International Monetary Fund (IMF) in its recent World Economic Outlook, partly because of the negative effects of tariff increases which include the tariffs imposed on USD200 billion of U.S imports from China. The tariff war between the U.S and China is expected to cause a global trade slowdown in 2019.

As a result, international trade and manufacturing activities are expected to decline, trade tensions may remain unresolved, and some large emerging markets may experience substantial financial market pressures. National Trade

Tuan Speaker, in 2018, Malaysia’s trade performance has registered a total trade value of RM1.9 trillion with total export of RM998.3 billion, and import of RM877.8 billion. Trade surplus was at RM120.5 billion which registered the highest rate in 10 years and the largest trade surplus since 2012.

For the period from January to March 2019, total trade decreased by 1.5% to RM435.1 billion compared to RM441.9 billion for the same period in 2018. Export totalled RM236.0 billion, a decrease

of 0.7 %, and import slipped by 2.5% to RM199.1 billion. A trade surplus of RM36.9 billion was recorded for the same period, increased by 10.7 %.

State Trade

I am pleased to inform this august House that the trade has been on a positive trend with high surplus trade balance for the last two decades. In 2018, Sarawak’s total trade was RM143.7 billion of which RM97.8 billion is export and RM45.9 billion is import value. The amount of total trade for 2018 increased by 4.4% or about RM6 billion compared to RM137.6 billion in 2017.

For the first 3 months of 2019, Sarawak's total trade expanded by 17.3% to RM35.6 billion compared to the same period in 2018 which was RM33.6 billion. Exports grew by 22.4% from RM23.6 billion to RM28.9 billion while imports increased by 5.4% from RM10.1 billion to RM10.7 billion. The trade performance indicates that we are on the right track of our development plan while the national trade decrease at the same period.

Export receipts from LNG remains the biggest contributor at 42.5%, followed by ships, vessels, boats and floating structures at 11.2%, crude petroleum at 10.3% and palm oil at 8.3%. This indicates that our maritime industry is gaining position in our export activities.

Our major export partners are Japan (23.1 %), Peninsular Malaysia (12.0 %), Sabah (11.2 %), China (10.1 %) and Republic of Korea (10.0 %) which make up of 66.4 % of the total export value. The increase in our export to Sabah is due to the Petronas Floating LNG Plant movement to Sabah.

Our main import items are still machinery and transport equipment (32.9 %), followed by chemical products (15.5 %) and manufactured goods (12.5 %).

Trade Development

Tuan Speaker, in order to diversify our export commodities, my Ministry is actively pursuing participation in trade promotion activities especially for agriculture and manufacturing products.

Therefore, my Ministry has established the Sarawak International Trade Development (SITDev) Committee as a platform to discuss issues and challenges confronting trade development in Sarawak. It is also a platform to strategize and recommend programmes and projects to strengthen our competitiveness on trade mainly on agriculture and manufacturing products.

I am glad to report that the formation of the committee has received overwhelming response from the industry players. Positive feedbacks and comments have been obtained on various subjects and issues with regards to methods of improving and strengthening Sarawak’s international trade.

One of the key issues raised by the members of the committee is the lack of understanding of the export markets on the part of the entrepreneurs. In view of this, the committee has strongly recommended that more related capacity building programmes for entrepreneurs especially SMEs.

Tuan Speaker, for that reason, my Ministry will continue to work with the relevant agencies to equip our entrepreneurs with the required knowledge and capability to explore and venture into export and import markets.

Now, let me share an export guideline produced by MATRADE for businesses. In summary, the guidelines state that before venturing into export markets, exporters must consider the following:

(a) Production Capacity

The exporters must be able to expand their production capacity to cater for export demands such as acquisition of suitable up-to-date technology, sufficient machineries and adequate supply of raw materials.

(b) Financial Strength

The exporters must be financially healthy and have access to funding facilities either from commercial or government as well as proficiency on international payment methods.

(c) Competent Human Capital

The exporters must have sufficient trainable and knowledgeable employees in marketing, legislative procedures, logistic handling and international commercial terms with addition of a multi-lingual work force. Of course, it is an advantage with a multi-lingual work force.

(d) Marketing Capability

It is important to have marketing capability with sufficient marketing collaterals, access to various distribution channels and knowledge in export market plans and strategies.

(e) Export Requirements and Compliance

Export business rules and regulations must also be adhered to. Non-compliance will result in the refusal of entry of the products by the importing countries. Therefore, exporters need to conform to mandatory international standards, accreditations and certifications as well as permit, licensing and quota requirements. Another important element is adhering to packaging and labelling requirements of the importing country.

(f) Legal Acumen

Export activities involve compliances ratified under the international trade agreements such as Bilateral and Multilateral Trade Agreements, Intellectual Property Rights (IPRs), International Sales Contract and others. Therefore, exporters must be knowledgeable in arbitration in handling dispute settlements and any other potential issues.

Apart from the said general guidelines, exporters should also be aware of other specific standard and certification requirements applicable to different products, such as:

(a) Food and beverages; (b) Electrical and electronics; (c) Machinery and equipment; (d) Pharmaceutical; and (e) Medical device.

My Ministry and MATRADE have been and will continue to actively promote and educate our SMEs on the guidelines so that they can be ready and well equipped to do the export.

Tuan Speaker, I wish to inform this august House that last year my Ministry has collaborated with experts from Malaysian Export Academy to conduct Export Bootcamp. My Ministry has also worked with MATRADE to organize Sarawak Export Day and other export related workshops and briefings to keep our entrepreneurs informed of the latest developments on export matters. These

programmes have benefited more than 500 Sarawakian entrepreneurs. More similar programmes will be carried out in the remaining months of this year with the intent to enhance knowledge and build up the confidence of more entrepreneurs in the State.

Tuan Speaker, another initiative of my Ministry to strengthen our export market is by way of exposing our entrepreneurs to the global market through trade promotions such as participations in international expositions and trade fairs, business matching, product sourcing and product demonstrations.

Since establishment in May 2017, my Ministry has coordinated the participation of Sarawak entrepreneurs in eighteen expositions and trade fairs. In total, our participation has enabled us to handhold and position 92 entrepreneurs to promote their products overseas. Among the local products that were exhibited in the expositions are food and beverages such as pepper powder, gula apong, laksa paste, coffee powder, banana chips, margarine and craft products such as pua kumbu, beads and baskets. The products that were promoted have received good response and are now receiving orders.

For the first quarter of this year, my Ministry has successfully arranged the participation of our entrepreneurs in three international and two domestic trade fairs and expositions, namely:

(a) 28thIndonesia International Education and Training Expo (IIETE) in Jakarta from 14th– 17th January 2019; (b) Foodex Japan 2019 in Tokyo from 5th – 8thMarch; (c) Vietnam International Trade Fair 2019 in Hanoi from 10th – 13thApril; (d) Export Furniture Exhibition in Kuala Lumpur from 9th – 12thMarch 2019; and (e) Malaysian International Halal Showcase (MIHAS) in Kuala Lumpur from 3rd – 6thApril 2019.

The programmes have successfully exposed and promoted our six higher learning institutions and 22 entrepreneurs from various sectors like food and beverages, beauty and health products, building materials and furniture.

For the next half of the year, my Ministry will coordinate and arrange the participation of our entrepreneurs in another seven trade fairs, namely:

(a) Food and Hotel Myanmar 2019 in Yangon on June 5th – 7th that brings major stakeholders and leaders within Myanmar's food and hospitality industry; (b) Food Taipei 2019 in Taiwan from 19th – 22nd June, an international display of diverse food culture; (c) Pacific International Maritime Exposition this is (PACIFIC 2019) in Sydney, Australia from October 8th – 10th, specifically developed to meet the needs of the broad spectrum of maritime industries; (d) ANUGA 2019 in Germany from 5th – 9th October, the world's largest trade fair held once every two years; (e) Second China International Import Expo (CIIE) in Shanghai from 5th – 10th November 2019, this is the first dedicated import exhibition in the world to explore Chinese market; (f) Malaysian International Food and Beverage Trade Fair (MIFB 2019) in Kuala Lumpur from 26th – 28th June, the largest food and beverage focused trade event in Malaysia with more than 600 companies from 50 over countries throughout the world; and (g) The Malaysian International Beverage Trade Network Fair 2019 (IBTN) from 31st October to 2nd November in Kuala Lumpur, the first ever beverages trade show in Malaysia to create an exciting impression in one of the most prominent markets in Southeast Asia.

In these coming expositions, we hope to exhibit and promote more variety of products including building materials, maritime vessels and equipment and furniture apart from food and beverages, other timber products as well as crafts.

My Ministry has disseminated the details of the trade fairs to relevant business associations for them to nominate their members to participate. We encourage more new local companies who are ready to export to participate and seek for international market opportunities.

Support and Assistance

Tuan Speaker, in order to encourage more entrepreneurs to market their products globally, my Ministry will continue to provide support and assistance for entrepreneurs to participate in trade fairs.

I wish to inform this august House that as of April 2019, a total of 70 companies have received support and assistance from my Ministry to participate in various trade fairs to promote their products and services.

My Ministry is also working continuously with the Federal agencies which provide incentives and funding for entrepreneurs to participate in export market. MATRADE is still providing four types of funding, which are:

(a) Market Development Grant (MDG); (b) e-Trade; (c) Services Export Fund (SEF); and (d) New Exporters Development Programme.

Apart from that, MATRADE also assist entrepreneurs by providing information on Market Intelligence through their 46 global offices, which act as the mediator and referral to international market players while at the same time providing support for local players.

MATRADE also maintained their Mid-Tier Companies Development Programme (MTCDP) where eight Sarawak companies are still in the nine months programme in preparation for global expansion opportunities.

In addition, I wish to inform that some of the export programmes conducted by SME Corp to support entrepreneurs by providing grants are still being conducted, namely:

(a) Galakan Eksport Bumiputera (GEB) is to increase the number of Bumiputera SMEs with export market potential and to create network and supply chain among them; (b) Tunas Usahawan Belia Bumiputera (TUBE) to educate and nurture youth in entrepreneurship through bootcamp, soft skill training and handholding; and (c) Bumiputera Enterprise Enhancement Programme (BEEP) is to provide comprehensive assistance packages, comprising financial assistance and advisory services.

So far, 271 Sarawak entrepreneurs have received assistance from the three programmes.

eCommerce Development

Tuan Speaker, eCommerce offers infinite possibilities for business, dictating the changes in the way we exist, purchase products and services, treat our free time and social life as a whole not only for the millennials but also the older generations. Day by day it is growing strongly with no signs of decline.

As shown in the global retail sales, the value has increased to USD2.85 trillion at the end of 2018 from USD2.43 trillion the previous year. According to Statista, an established market data and

research portal based in Germany, the worldwide eCommerce sales is projected to continue further growth to USD4.88 trillion by 2021.

eCommerce sales in Asia Pacific remains the fastest growing and are projected to be greater than the rest of the world combined by 2023. This major shift is due to:

(a) urbanisation and technological advancements; (b) growing number of middle class using mobile commerce; and (c) various government and private led initiatives.

Trends of eCommerce

Tuan Speaker, technological advancements such as Artificial Intelligence (AI), Augmented and Virtual Reality (AR/VR) and Blockchain technology are driving eCommerce’s rapid growth.

These technological advancements will pave the way for better customer services and satisfaction, giving more simplicity, personalised interactions and better product availability which add to better decision for shoppers.

Tuan Speaker, in order to strengthen eCommerce activities and development, the government has established the National eCommerce Council (NeCC) to oversee the planning, implementation and monitoring of eCommerce progress in the country.

I am glad to mention here that Sarawak, represented by my Ministry is a member of the Council chaired by the Minister of MITI. This is a show of recognition of the establishment of my Ministry in spearheading eCommerce initiatives and development in the State.

Under this Council, National eCommerce Strategic Roadmap (NeSR) was launched in October 2016 to develop eCommerce ecosystem in Malaysia. Since then, various programmes on eCommerce were implemented throughout the country including Sarawak.

In this respect, I am pleased to inform that through this initiative, my Ministry have been working closely with the relevant Federal agencies among others MARA, FAMA, MCMC, MDEC, SME Corp and MaGIC in implementing eCommerce programmes in Sarawak.

The programmes include the following:

(a) MARAGO: eCommerce On boarding; (b) Generate Income via Smartphone; (c) Borderless Marketing for Entrepreneurs; (d) Online Marketing Engagement Programme; (e) eUsahawan; and (f) eRezeki.

Tuan Speaker, as I have mentioned in the previous sitting, my Ministry has been actively conducting eCommerce programmes to educate, impart knowledge and skill, as well as to provide awareness to the people of Sarawak. As of January until April 2019, approximately 800 participants have benefited from our programmes. The programmes are:

(a) Seminar Usahawan Digital dan eDagang; (b) eUsahawan Digital: Kenyalang Archivers Rural SMEs; (c) Kampung Reachout: eCommerce Introductory Programme for the Community Leaders; (d) Shopee Uniday; and (e) Shopify Dropshipping Workshops.

The focus or intent of these programmes are to educate both urban and rural dwellers to establish eCommerce business and to train existing entrepreneurs and youth on updated eCommerce tools and knowledge to enhance their ways of doing business. At the same time, the programmes also disseminate information on eCommerce to rural communities.

This year my Ministry will intensify our efforts to make eCommerce accessible for every different age group across all walks of life in Sarawak, providing and expanding e-business trainings through existing e-market places and social media applications.

One of the programmes is the Shopify Dropshipping Workshop, a programme to train participants to do e-business by leveraging on existing available products in the marketplaces. This is a unique retail fulfilment method that requires minimal investment and non-stock keeping business where our youths can actively participate and generate income. As of April 2019, my Ministry has organised six (6) Shopify Dropshipping Workshops which benefited more than 200 youths.

Recently, my Ministry also collaborated with Shopee in organising a program called Shopee Uniday. This programme is specially designed to encourage members of the public to get onboard Shopee e-marketplace and provided a walkthrough on setting up their stores on the platform. In addition, tips to generate better sales were also shared by Shopee. This one-day programme was conducted by professional trainers from Shopee headquarters and attended by more than 50 participants. In the quest to assist the public to understand more about Shopee onboard programme, my Ministry has linked the tutorial videos on our website for them to access.

For the information of this august House, my Ministry also collaborated with Lazada Malaysia to integrate our local eMarket portal, Produk Sarawak with Lazada e-Marketplace. Lazada being Malaysia’s top rank eCommerce platform and one of the tops in Asia is expected to boost the promotion of our local entrepreneurs and their products.

Through all the programmes implemented and encouragement done by the Government, I am glad to announce that the homegrown eCommerce champions are mushrooming and are actively in business. Among those active players are:

(a) TIMOGAH - a platform that collects and delivers fresh local produce from our rural farmers; (b) Sarawak Focus - an online platform to promote property development in Sarawak locally and globally; (c) Easy Move - an online platform for domestic logistic and delivery services; (d) Empurau Sarawak - an online platform to promote and sell empurau fish and agro tourism products to overseas market; (e) OneFarm - an app to promote and sell agriculture produce locally; (f) BeGO - an app to facilitate domestic logistic and delivery services; (g) MELI - an app to connect online merchant with offline customers through a network of agent; and (h) GAGO Insta-job - a platform to connect businesses with full time or part time job seekers.

All of these new business ventures are start-up entities, owned and managed by our young technopreneurs. This augurs well with the effort of The Right Honourable Chief Minister in developing our economy through digital technology.

All these business ventures are able to create jobs and other business opportunities as well as generate income for our local youth. I am glad to say that the innovative business models by our young entrepreneurs or by our young technopreneurs have indeed provided solutions for our society’s daily needs and created a larger eCommerce community. I believe, in the near future more and more of our people will embrace eCommerce and digital technology as a way of life as envisaged by our Government.

Tuan Speaker, in view of the vast business and job opportunities offered by eCommerce activities beyond our boundaries, I would like to urge all aspiring online business entrepreneurs to participate in this digital economy and register their business especially with Companies Commission of Malaysia or Suruhanjaya Syarikat Malaysia (SSM).

It is important for Sarawak online business entrepreneurs to register their business under SSM as it provides the following benefits:

(a) Building customer and consumer confidence on the products and services offered by the entrepreneurs; (b) Facilitating customer and consumer to verify the information and validity of the business through SSM portal; (c) Providing more business opportunities in Semenanjung Malaysia and globally; and (d) Providing wider access to Government assistance related to community development and business prospect.

However, entrepreneurs in Sarawak who intend to register their business under SSM must have a registered address in Peninsular Malaysia as the Registration of Businesses Act 1956 is only applicable in Peninsular Malaysia. My Ministry acknowledged that many of our SMEs do not have a registered address in Peninsular Malaysia, therefore my Ministry and Ministry of Industrial and Entrepreneur Development (MIED) have created a special programme to enable the said registration.

Under this programme, a special arrangement with SSM and an appointed agent was made to facilitate the registration where a special counter for online business registration is set up at SSM Sarawak. Currently, more than 200 entrepreneurs have registered their online business through this programme. My Ministry will continue this efforts so that more Sarawakian online entrepreneurs are registered with SSM. Moving Forward

Tuan Speaker, my Ministry will amplify our efforts to promote international trade and eCommerce in the State through capacity building, technological adoption, promotion of creativity and innovation as well as market development.

I am pleased to inform this august House that my Ministry will collaborate with other State and Federal agencies, industry players and business associations to implement various initiatives for the development of international trade, namely:

(a) Capacity Building

Programmes to monitor SMEs from domestic and Mid-Tier companies to international exporting firms;

(b) Trade Promotion

We will continue to organise and manage Sarawak's participation in international trade fairs which helps companies to market their products and services;

(c) Export Acceleration Missions

Will be conducted to establish business networks and explore trade opportunities for selected products and services overseas;

(d) Trade Mission

To arrange trade mission to major existing and emerging markets to explore for new businesses;

(e) Market Development

We will also leverage on the existing regional cooperation such as ASEAN Economic Community, BIMP-EAGA and SOSEK-MALINDO to strengthen our trade relationship with the member countries in the region and deliver value to Sarawak export chain;

(f) Information Centre

Setting information centre at MATRADE Kuala Lumpur to promote local products and services as MATRADE is the first point of contact for foreign importers.

Tuan Speaker, as our people are becoming increasingly familiar with both sales and purchases through eCommerce, my Ministry is obliged to prepare our people with the required skills and knowledge in respect of new technologies, solutions and ways in dealing with sophisticated and modern eCommerce.

In this respect, my Ministry will collaborate closely with other Government agencies, industries and academia to continuously conduct relevant eCommerce knowledge and skills development programmes to solidify and guide entrepreneurs to grab the opportunities in the local, regional and global markets.

Besides that, my Ministry plans to develop more technopreneurs in creative and innovative industries which provide huge potential in international audience and market that will generate higher income. This is also for our people to be able to keep up with the new development in the digital world.

My Ministry will keep ourselves abreast of the evolution of digital technology especially eCommerce so that we can plan for our eCommerce industry accordingly and disseminate the latest information to our people for them to remain relevant and competitive.

My Ministry acknowledges that there are much more that needs to be done and executed but we need to be realistic and move forward wisely. As the saying goes “only fools rush in”.

Conclusion

Tuan Speaker, in conclusion I wish to emphasise that international trade activities are important sectors in our economic development which contributed to about 50 percent of the State’s Gross Domestic Product (GDP). I believe that the percentage will increase with the development and implementation of digital economy by most of the countries in the region.

However, the competition will be fiercer and we need to be agile in facing the challenges. What my Ministry is doing now is to prepare our people to be ready for the uncertainties of the future. That reminds me of a famous proverb “Give a man a fish, and you feed him for a day. Teach a man to fish, and you feed him for a lifetime.”

The effort to prepare our people for the future will continue as it is an obligation entrusted to my Ministry and I assure this august House that we will do our best no matter how difficult it will be, as the saying goes “It does not matter how slowly you go, as long as you do not stop”.

With this note, Tuan Speaker, I would like to convey my appreciation and gratitude to you for the judicious handling of the proceedings of this august House during the duration of this Sitting. I would also like to say many thanks to the House officials led by Mr. Semawi bin Mohamad, the House Secretary for the job well done in providing us with efficient and effective services.

Lastly, I wish all Muslims a religious fasting, Selamat Berpuasa and Selamat Hari Raya. To all our Dayak community, Selamat Hari Gawai, Gayu Guru Gerai Nyamai and Seramat Andu Gawai. Enjoy your celebration, stay safe till we meet again in the next Sitting. Terima kasih. Thank you.

Mr SpeakerEN

Honourable Members, with respect, I invite Honourable Datuk Amar Haji Awang Tengah Bin Ali Hasan, Deputy Chief Minister, Second Minister of Urban Development and Natural Resources, Minister of Industrial Development and Entrepreneurs, to deliver the winding-up speech.

Datuk Amar Haji Awang Tengah Bin Ali HasanPBB · GPSMinister of Urban Development and Natural Resources Second · Bukit SariEN

Thank you, Mr Speaker. First, I would like to extend my warmest congratulations to His Excellency the Yang di-Pertua Negeri of Sarawak, Tun Pehin Sri Haji Abdul Taib Mahmud, on the Opening Address to this August House's sitting on 29 April 2019.

In the Opening Address, Your Excellency has outlined a solid foundation and platform, as well as a clear direction, for us to achieve Sarawak's development vision.

I also extend my heartfelt thanks to all Honourable Members who took part in the debate and provided insightful views on matters under the purview of the Ministry of Urban Development and Natural Resources.

NCR Land Survey Programme: New Initiative

Mr Speaker, for the information of this August House, the Sarawak Government has always recognised and upheld the rights of the people over their land. This NCR land survey effort is not a new matter; in fact, it has been initiated since the 1960s through programmes such as Operasi Penyelesaian, Pengukuran Bahagian III Kanun Tanah Negeri and Pengukuran Kampung Tradisional, before we introduced the NCR Land Survey Programme: New Initiative in 2010. However, the earlier method was found to be less efficient because, in the period of about 50 years from the 1960s until 2010, only an area of about 260,000 hectares, equivalent to 642,460 acres of NCR land, was successfully settled.

For this reason, we introduced a new method in 2010, implemented in two stages.

The first stage is the perimeter survey and gazettement under Section 6 of the Land Code as a Bumiputera Communal Reserve (Agriculture). In the second stage, individual lot surveys and the issuance of land titles under Section 18 of the Land Code are carried out.

This new method has proven more efficient and thus has a significant impact, covering all Bumiputera communities in Sarawak. It is clear from the survey achievements up to 30 April 2019 that an area of 880,541 hectares, or 2,175,817 acres, of land has had its perimeter successfully surveyed under the first stage, of which 723,344 hectares, or 1,787,383 acres, have been gazetted. This means that in just eight years, we have managed to survey three times the area compared with the previous method.

In the second stage of this programme, the areas under Section 6 will be surveyed by individual lot for the purpose of issuing land titles under Section 18 of the Land Code. So far, a total of 26,036 individual lots have been successfully surveyed, involving an area of 32,376 hectares (80,001 acres) of land which has been or will be issued land titles under Section 18 of the Land Code.

In addition to perimeter surveys, this year's survey focus will be on individual lot surveys for areas that have been gazetted under Section 6 of the Land Code, based on applications and the readiness of the claimants of the land.

The previous Federal Government was very concerned about land matters in the State of Sarawak, even though they knew land falls under State jurisdiction. This is evidenced by the previous Federal Government's commitment in providing an allocation of RM161 million.

The current Federal Government, in the 2019 budget, did not specifically allocate funds for NCR land surveys in Sarawak. Therefore, out of the Sarawak Government's concern for safeguarding the rights of landowners, an allocation totalling RM40 million has been approved by the Sarawak Government to continue this NCR Land Survey Programme: New Initiative.

Perhaps the Federal Government felt pressured, so the current Federal Government has announced an allocation of RM21.5 million. So far, only RM10.75 million has been disbursed.

This programme has received a positive response from the majority of NCR landowners, and it has been proven that many have enjoyed its benefits. Landowners are aware that the GPS Government always fulfils its promises. Those who had previously been left behind have already re-applied to take part in this programme.

For this reason, the Sarawak Government has approved the recruitment of 467 officers across various categories to increase the existing capacity of the Sarawak Lands and Survey Department. The recruitment of the new officers will entail additional expenditure estimated at RM30 million a year for the Sarawak Government.

To ensure the sustainability of this programme, I would like to call on all Honourable Members and all parties claiming NCR land to give their full cooperation to the Lands and Survey Department so that these survey works can proceed smoothly, particularly those involving individual lots.

Resettlement Scheme (SPS) and Village Expansion Scheme (SPK)

Mr Speaker, out of the Sarawak Government's concern for the welfare of low- and middle-income people, and to ease their financial burden in obtaining residential lots, the Government has implemented a programme known as the Resettlement Scheme (SPS) and the Village Expansion Scheme (SPK).

As of January 2019, a total of 47,988 residential lots have been successfully prepared. Of that total, 36,578 lots have been distributed to those eligible.

Under the Eleventh Malaysia Plan and the Mid-Term Review of the Eleventh Malaysia Plan, the total allocation approved to implement 37 SPK and three SPS is RM333.4 million. Meanwhile, schemes that were not approved will be re-proposed in the Twelfth Malaysia Plan.

New Approach in the Implementation of SPS and SPK

Mr Speaker, as I have informed the State Legislative Assembly in its previous sitting, the Government has set the premium for residential lots in all Resettlement Schemes (SPS) and Village Expansion Schemes (SPK) at not exceeding RM2,500.00 per lot, except for Demak Resettlement Scheme Phases 3, 4 and 6. Accordingly, premium payments made in excess of RM2,500.00 have been decided to be refunded, with the application period being until 31 October 2019.

This refund is enjoyed by 7,174 landowners at a total cost of RM43.4 million. As of 31 March 2019, 4,537 owners have been refunded with a value of RM28.97 million.

However, this refund will not be made for lots involved in buying and selling or speculation.

The Sarawak Government's commitment and concern for low-income people, particularly in SPS and SPK, is continued through a new policy, namely improvements to the specifications and components of basic infrastructure in new schemes to be implemented. A total of 22 schemes are involved in these infrastructure improvements. These improvements involve basic infrastructure as follows: (a) The road network within SPS and SPK, which previously was only gravel road, has been upgraded to tar-sealed road; (b) Lots which were previously distributed unfilled have been improved with filled lots; and (c) The drainage system in the scheme, which previously was only earth drain, has been improved with concrete drain.

Rural and Urban Renewal Projects

Mr Speaker, The Sarawak Government through Land Custody and Development Authority (LCDA) continues to emphasize on the implementation of socio-economic projects such as Urban Renewal Projects and Service Centres. The main objectives of these projects are to improve the community’s quality of life through employment opportunities, provision of basic infrastructure, affordable housing and other public amenities.

The current progress in the implementations of Urban Renewal Projects are as follows:-

(a) Darul Hana Project, Kuching

The provision of infrastructure and construction of 564 houses for Blocks 1A and 2A is expected to be completed by the end of 2020.

(b) Sungai Bedaun Development Project, Kuching

The site clearing and earth filling works for Phase 2 is on schedule and expected to be completed by the end of 2019. 434 houses will be built within the area for the extended families from the Darul Hana area which is expected to be completed by the end of 2020.

(c) Kemuyang Project, Sibu

The site clearing and earth filling works for a total of 813 affordable houses including provision of basic infrastructures and building works for 186 houses are ongoing and expected to be completed by October 2020.

In promoting rural development through the provision of Service Centres, the Sarawak Government is focused on narrowing the economic gap between urban and rural areas. The following are the six Service Centres that have been approved and in various stages of implementation:

(a) Sebuyau New Township, Samarahan; (b) Sungai Lingga Waterfront; (c) Lingga Service Centre, Sri Aman; (d) Matading Service Centre, Mukah; (e) Ulu Merapok Service Centre, Lawas; and (f) Kampung Datu Waterfront, Kuala Lawas.

Mr Speaker, next, allow me to touch on the specific matters raised by Honourable Members during the debate in this August House.

Specific Issues

For the information of the Honourable Member for Bukit Assek, the Government has prepared a proposed master plan for the development of Sibu Town known as the “Conceptual Plan for Greater Sibu”. This proposed plan was approved by the State Planning Council in May 2014, yea, as a development control guideline plan that will ensure land development is in line with the approved land-use zones, in tandem with the planned road network system and existing socio-economic activities, to help drive the development of Sibu Town.

Following the implementation of the “Conceptual Plan for Greater Sibu”, the Government has also taken the initiative to prepare a new framework, such as development plans organised in a hierarchy, namely the Structure Plan, the Local Plan and the Action Area Plan for Sibu Town, so that it is better planned and more sustainable. This planning takes into account new development and the redevelopment of existing areas.

To ensure this plan can be implemented effectively, the Government is at the stage of collecting primary and secondary information for the purpose of analysing the relevant information. It also takes into account input from technical departments and the public through Focus Group Discussion (FGD) sessions so that it is comprehensive and practical.

Mr Speaker, for the information of the Honourable Member for Bukit Goram, at this time the Government ...(interruption)

Mr Speaker

Honourable Minister, you take?

Puan Irene Mary Chang Oi LingDAP · PHBukit Assek

Thank you Tuan Speaker and Honourable Deputy Chief Minister. Where can we get a copy of this plan? Are we able to have a copy of this plan that is in? You know planning... (interruption)

Datuk Amar Haji Awang Tengah Bin Ali HasanPBB · GPSMinister of Urban Development and Natural Resources II · Bukit Sari

In practice the plan is not to be publicised... (interruption)

Puan Irene Mary Chang Oi LingDAP · PHBukit Assek

But its not publicise, but... (interruption)

Datuk Amar Haji Awang Tengah Bin Ali HasanPBB · GPSMinister of Urban Development and Natural Resources II · Bukit Sari

Because if you publicise it, that will lead to speculation. Normally, we will not publicise it. It is just a guideline for us ... (interruption)

Puan Irene Mary Chang Oi LingDAP · PHBukit Assek

So, is actually the plan, I mean the masterplan is it completed yet? is it still in drafting?

Datuk Amar Haji Awang Tengah Bin Ali HasanPBB · GPSMinister of Urban Development and Natural Resources II · Bukit Sari

We have done the conceptual plan for the greater Sibu and we are now in the process of preparing the structure plan, local plan for the Sibu Town... (interruption)

Puan Irene Mary Chang Oi LingDAP · PHBukit Assek

But, but this kind of plan it should not be kept in a sense, I mean if the public, it should be made available to public to have a look and... (interruption)

Datuk Amar Haji Awang Tengah Bin Ali HasanPBB · GPSMinister of Urban Development and Natural Resources II · Bukit SariEN

No, no, no... (interruption)

Puan Irene Mary Chang Oi LingDAP · PHBukit Assek

Especially if say, if we write in to ask for a plan, to have a look at it and may be to propose, to make some proposal as well ... (interruption)

Datuk Amar Haji Awang Tengah Bin Ali HasanPBB · GPSMinister of Urban Development and Natural Resources II · Bukit Sari

It is a practice of government, but in formulating the master plan we engage with all the technical department and if neccessary with all the stakeholder to get input and comments, in order to come up with a comprehensive plan.... (interruption)

Puan Irene Mary Chang Oi LingDAP · PHBukit Assek

In that case, when can we expect the completion for this plan?... (interruption)

Datuk Amar Haji Awang Tengah Bin Ali HasanPBB · GPSMinister of Urban Development and Natural Resources II · Bukit SariEN

Conceptual plan is mainly focusing on land use, how certain area should be developed, for that we should have a proper structure and local plan.

For the information of the Honourable Member for Bukit Goram, the Government is currently in the process of preparing the proposed Kapit Town Development Master Plan. The Government will study the suitability of the area as proposed by the Honourable Member for Bukit Goram.

For the information of the Honourable Member for Ngemah, in 2010, the previous Federal Government had agreed to return the RASCOM area, which covers the settlement areas of Nanga Ngungun, Nanga Tada, Nanga Jagau and Nanga Sekuau, to the Sarawak Government. Accordingly, the Lands and Surveys Department has been in contact with the Department of the Director-General of Lands and Mines (JKPTG) to finalise the matter, but until now no official response has been given. The Sarawak Government will consider the applications of the residents concerned once the transfer of the land to the Sarawak Government has been completed.

For the information of the Honourable Member for Murum, out of 1,639 Head of Households (KIR) involved in the Sungai Asap, Bakun resettlement, a total of 1,178 land title letters have been issued for residential and agricultural lots respectively under Section 13 of the Land Code. As for the remaining 461, letters of approval for the alienation of agricultural and residential land were offered on 5 May 2016. However, the land title letters have not yet been issued as the land premium has not been paid.

As for the Murum Resettlement Scheme, the entire residential and agricultural lots have not yet been issued with title documents, as the survey and verification of the lots have not been finalised because there are objections on the ground.

The Government, in a Cabinet Meeting, has decided that the applications for exemption from payment of land premium and for refund of premium for the KIR involved in the resettlement for the Bakun and Murum HEP projects are not approved. However, the Government has directed that the best settlement mechanism be identified together with Sarawak Energy Berhad (SEB) to assist the residents involved.

With regard to the provision of additional land and applications for residential and agricultural lots for the Extended Family (Keluarga Baru), a written question has been submitted by the Honourable Member. Therefore, a written reply will be provided.

For the measurement of NCR land, the residents involved are advised to submit applications for perimeter measurement under the new initiative to the Lands and Surveys Department. Meanwhile, applications involving Native Territorial Domain (NTD) may be submitted when it is implemented in the future.

For the payment of land compensation, the Lands and Surveys Department has finalised the payment of compensation amounting to RM271,425,950.59 to the genuine NCR landowners involved in the Bakun HEP project.

For the information of the Honourable Member for Tamin, the issue of JV between NCR native customary land claimants and the private sector may refer to the NCL Development project in the area, which is managed by PELITA as the management agent. For such projects, after the development agreement period ends, individual land title documents will be issued to the project participants based on the existing records.

For the information of the Honourable Member for Daro, as of 30 April 2019, seven areas have been approved for perimeter measurement under the New Initiative NCR Land Measurement Programme within the Daro State Constituency. Of that total, two areas have not yet been completed for measurement, namely the Seredeng area (Kampung Sepenak, Kampung Bintangor, Stubah, Stabar and the Mupong area) in the Sarikei Division, covering 5,279 hectares, which is currently in the process of field measurement. Another area, namely Sungai Blusan & Sungai Sah, indeed confirmed, this is indeed confirmed, Kampung Sungai Sah, Nanga Singat, Batang Rajang in the Sibu Division, covering 116 hectares, cannot begin measurement because there are several issues on the ground that are still under discussion. Confirmed but not yet confirmed.

Meanwhile, of the five areas that have been completed for measurement, four areas covering 1,099 hectares have been gazetted as Bumiputera Communal Reserves (Agriculture). Another area covering 657 hectares is in the process of being gazetted.

For the information of the Honourable Member for Beting Maro, as of 30 April 2019, a total of 7,451 hectares (18,411 acres) of NCR land within the Beting Maro State Constituency have been approved for perimeter measurement under the New Initiative NCR Land Measurement Programme.

Of this total, 7,157 hectares have been completed for perimeter measurement. A further 234 hectares will begin measurement subject to verification of the boundaries of the adjacent Forest Reserve. Meanwhile, 60 hectares, namely the area near SMK Pusa, have not yet been measured because they are involved in a case at the Native Court.

For the information of the Honourable Member for Pelagus, based on a record check at the Lands and Surveys Department, a total of 13,925 hectares of land in the Sungai Merirai area that was applied for was found to be subject to genuine bumiputera native customary rights claims. It was approved in March 2016 for measurement under the New Initiative NCR Land Measurement Programme, and measurement work is now being carried out on the ground.

For the information of the Honourable Member for Opar, through the New Initiative NCR Land Measurement Programme, a total of 21 areas within the Opar State Constituency covering 9,930 hectares have been approved for perimeter measurement under the First Phase of this programme. Of that total, 19 areas covering 8,977 hectares have already been completed for measurement.

Through the Second Phase of this programme, six areas covering 4,315 hectares have been approved for individual lot measurement. So far, 224 individual lots have been measured and 103 lots have been issued with title documents under Section 18 of the Land Code.

Through the Traditional Village Measurement Programme, Kampung Jugan has been approved and the field measurement has been completed. Title documents under Section 18 of the Land Code will be issued once the results of the measurement work have been finalised. The Lands and Surveys Department has received 19 other applications, which are currently under review before being submitted for consideration and approval.

Mr Speaker, referring to the issue raised by the Honourable Member for Krian in questioning the effort of surveying land and declaring them under Section 6 gazette is not good enough to protect the right of the native, such statement is blatantly manipulating the fact. I would like to highlight to the Honourable Member the Federal Court case of the Superintendent of Land and Survey Department, Bintulu and others vs Amit bin Salleh and others wherein it was decided that any extinguishment of rights within gazetted Section 6 communal reserve would require payment of compensation. This shows that an area which has been gazetted under Section 6, enjoys protection by the law as opposed to what has been alleged by the Honourable Member for Krian.

I would like to emphasise the fact that gazetting the area under Section 6 of the Land Code is the first step to register and protect the rights of the people over land into a proper record. The land areas are demarcated, plotted onto the map and deposited with the Land and Survey Department, which can be inspected as it is properly surveyed. The second step is to survey the land individually and subsequently issue them with a document of title in perpetuity under Section 18 of the Land Code. This is what we have done.

And I too have on several occasions, including the late Tok Nan, during the ceremony to hand over Section 6 gazettes, many landowners attended. They received the Section 6 gazette documents. Tok Nan said, and I also said, if you do not believe that this Section 6 gazette document under the Land Code is not proof of your land ownership, you may return the gazette to the Government.

Mr Speaker, to this day, not a single group of landowners has returned their Section 6 gazette to the Government. In fact, what has happened is that landowners who already hold Section 6 gazettes have applied for individual measurement for the purpose of issuing individual title documents under Section 18 of the Land Code. Many Section 6 areas have been individually surveyed, and of course the individual lot measurement process takes some time, but what is certain is that this programme is a continuous programme of the Government.

Mr Speaker, as I have said earlier, we have carried out direct individual survey for the last 50 years since 1960s through Settlement Operation, Part III of the Land Code and Survey of Kampung Tradisional but it was proven slow and was exposed to unnecessary issues in settling individual dispute on the ground. This has delayed the process of such survey. As the Honourable Member for Krian can see today, we are focusing on converting more than 700,000 hectares (1.7 million acres) gazetted under Section 6 into individual Section 18 document of titles. This is a continuous effort and should be supported by every member of this august House.

With regard to the proposal to establish the Kampung Paroh and Kampung Sejijak Village Enlargement Scheme raised by the Honourable Member for Tupong, it is recommended that the Honourable Member discuss with the JKKK of the village concerned to identify a suitable area and subsequently make a formal application to the Lands and Surveys Department.

For the information of the Honourable Member for Beting Maro, the Government has implemented the Village Enlargement Scheme (SPK), and for Kampung Spinang/Semarang, which provides 188 residential lots, 128 lots have been allocated. A total of 31 lots have been recommended by the Selection Committee and will be distributed in the near future, while the remaining nine lots have been reserved for emergency needs. As for Kampung Tambak and Kampung Beladin, the proposal to establish an SPK will be submitted in the Twelfth Malaysia Plan. Meanwhile, for Kampung Pusa, so far the Lands and Surveys Department has not received any application to establish an SPK for the village.

For the information of the Honourable Member for Balingian, the proposal for the implementation of basic infrastructure development for the Balingian Phase II Village Enlargement Scheme will be submitted in the Twelfth Malaysia Plan. This scheme will provide 116 residential lots. For the Kuala Balingian New Village Enlargement Scheme, which provides a total of 180 residential lots, 74 lots have been approved for distribution. Meanwhile, for the Jebungan Phase I Village Enlargement Scheme, which provides 102 residential lots, 72 of them have already been approved for allocation to applicants.

For the information of the Honourable Member for Balingian as well, the Balingian Phase I Village Enlargement Scheme, which provides 112 residential lots, will be implemented by the Housing Development Corporation to be developed with affordable housing. The distribution process of the lots for eligible applicants will be managed by the HDC. The land filling works for 22 lots in the Balingian Phase I SPK were completed by HDC in 2011. Originally, HDC planned to build a total of 22 units of Rumah Mesra Rakyat on the lots filled through a collaboration with Syarikat Perumahan Negara Berhad. However, SPNB, Syarikat Perumahan Negara Berhad, does not have an allocation to build the houses. I understand that HDC plans to build Rumah Spektra Permata (RSP) and will apply for an allocation from the Sarawak Government in the Twelfth Malaysia Plan.

For the information of the Honourable Member for Bukit Goram, the site and layout plan for the Selirik Resettlement Scheme was approved by the State Planning Council on 24 April 2019. The land acquisition works and basic infrastructure development works are planned to be implemented in the Twelfth Malaysia Plan.

For the information of the Honourable Member for Simunjan, a site of 52 hectares adjacent to the existing Simunjan SPS has been identified as the site for the New Simunjan SPK and will be proposed for implementation in the upcoming Twelfth Malaysia Plan.

With regard to the implementation of the Lingga Service Centre and Lingga Waterfront raised by the Honourable Member for Lingga, the Land Development and Protection Board (PELITA) will implement the project in several phases. Phase 1, which involves basic infrastructure construction works and a wet market and dry market for the Lingga Service Centre, including Lingga Waterfront Phase 1, will be tendered in June 2019. Both projects are expected to be completed by the end of 2020.

For the information of the Honourable Member for Beting Maro, there are two oil palm plantation projects developed by PELITA together with Tabung Haji (TH) in the Beladin and Meludam areas, namely:

(a) TH Pelita Beladin Sdn. Bhd. – a Bumiputera Native Customary Land (NCR) development project developed together with TH Plantations Berhad; and (b) TH Pelita Meludam Sdn. Bhd. – a joint venture project on State land together with TH Plantations Berhad.

Based on the agreement signed between TH Pelita Beladin Sdn. Bhd. and the NCR land project participants, dividend payments will only be made once the company makes a profit. However, the Government is concerned about the project participants, so the company has been directed to make incentive payments starting from 2009. As of 31 March 2019, the incentive payments distributed amounted to RM5.1 million.

With regard to the land claim issue, it refers to claims by village residents on land within the oil palm plantation owned by TH Pelita Meludam Sdn. Bhd. To address this matter, the parties involved are in discussions to find the best solution.

For the information of the Honourable Member for Pujut, among the main factors that affect the current market value of land are as follows:

(a) Location; (b) Land use conditions including the approved density for land that is ready for development; (c) Date of valuation; (d) Period of land tenure; (e) Topography; (f) Accessibility; and (g) Size, shape of lot and other relevant factors.

The compensation for Lot 2262 Block 9 Miri Concession Land District, covering 1.3053 hectares, was valued at RM1,700.00 per square metre based on a valuation date of 13 November 2018. Lot 2262, which is located in a prime location in an exclusive area near the Miri Marina Bay area, which is also a tourist hotspot in Miri City, has been approved for mixed development use, with a lease period of 99 years. This lot is connected to a very good road network, is located only about 1 kilometre from the centre of Miri town, has a very ideal size and shape, has been fully filled to road level and is ready for development at any time.

Therefore, the Lands and Surveys Department has decided that the reasonable and fair current market value for Lot 2262 as at 13 November 2018 is RM1,700.00 per square metre. This valuation is lower than the valuation made by a Registered Private Valuer, which was claimed by the landowner during the land acquisition process at a rate of RM1,980.00 per square metre.

Lot 3559 Miri Concession Land District, on the other hand, covering approximately 2.87 hectares, was granted for development for the purpose of the Miri Food Court Redevelopment. It is located in the Tanjung Lobang area approximately 3 kilometres from the centre of Miri town. The approved redevelopment component is low density, I'm fasting, my tongue is also stiff, stiff. Low density not exceeding two storeys consisting of:

(a) one two-storey block for hawker centre and shops/restaurants; (b) one single-storey kiosk block; (c) one single-storey ice cream parlours block; (d) one two-storey fast food restaurant block; and (e) one open plaza.

The rest is for car parking, recreational/leisure areas and open spaces. Lot 3559 Miri Concession Land District only has a tenure period of 40 years, has an irregular and elongated lot shape, and its valuation date is in 2012.

Based on the factors that have been stated, it is clear that Lot 2262 Block 9 Miri Concession Land District is more valuable than Lot 3559 Miri Concession Land District. Therefore, the current market value of Lot 2262 Block 9 Miri Concession Land District is far higher than that of Lot 3559 Miri Concession Land District. That is the situation, Mr Speaker.

For the information of the Honourable Member for Serembu, based on the records of the Lands and Surveys Department, within the Serembu State Constituency there are four (4) quarry licences that have been issued and are in operation. Quarrying operations may only commence after the licence holder has obtained approval of the Environmental Impact Assessment (EIA) Report from NREB. In addition, the Lands and Surveys Department and other authorities such as NREB, the Minerals and Geoscience Department (JMG), PDRM and JPJ constantly carry out monitoring on the ground to ensure that licence holders comply with the licence conditions and other rules that have been set, including the load limit for lorries. Firm action such as suspension of licences will be taken if non-compliance occurs.

With regard to the issue of the use of Kampung Keranji road as an exit and entry route by a quarry located in the area, the road is the only connecting road to the quarry area and is maintained by the quarry licence holder. Based on information obtained from the quarry licence holder, discussions have been held with the JKKK of Kampung Keranji regarding the use of the road, including a proposal for a new alternative road, but until now the outcome of these discussions has not been communicated to the Lands and Surveys Department for consideration.

For the information of the Honourable Member for Demak Laut, it is the Government's intention to issue title documents to the Sarawak Islamic Council for mosque sites, surau and Islamic cemetery sites. Therefore, the Sarawak Islamic Religious Department together with the Lands and Surveys Department constantly cooperate to achieve this intention.

For the information of the Honourable Member for Engkilili, the proposal to establish the Skrang Service Centre may be submitted directly to the Lands and Surveys Department for processing and consideration by the Government.

Mr Speaker, Forestry and Timber Industry Sector

The forestry sector continues to be among the major contributors to Sarawak's economic development and revenue. Besides that, forests also play an important role as habitats for flora and fauna, some of which are endemic or can only be found in the Borneo islands. Therefore, the Sarawak Government is highly committed to ensuring that forest resources are managed sustainably and durably for present and future generations.

Mr Speaker, the Sarawak Government is also carrying out the transformation of the forestry and timber industry sectors to achieve the objective of sustainable forest management. The Ministry, with the cooperation of all forestry agencies including industry players, is reviewing these policies and legislation by taking into account environmental protection, economic development and the social well-being of the people of Sarawak so that they keep pace with current needs and meet best forest management practices.

Accordingly, I call on all agencies and industry players to provide support and cooperation in drafting and implementing these policies.

Mr Speaker, Forest Management Certification in Sarawak

For the information of this august House, ten years ago Sarawak had only one forest management unit (FMU) that had successfully obtained forest management certification status, covering an area of approximately 84,000 hectares. Up until 2018, we have succeeded in increasing the number of natural forest concession licence areas that have obtained forest management certification status to six FMUs covering approximately 561,000 hectares. Meanwhile, six FMUs under forest plantation concession licences covering approximately 101,000 hectares have also been certified. To ensure that forest management is further strengthened, this year the Government is targeting one million hectares cumulatively of forest areas in this State to be certified. This achievement proves that the forest management implemented in Sarawak complies with the standards set by the Programme for Endorsement of Forest Certification (PEFC), which is based in Geneva, Switzerland.

Forest Landscape Restoration Programme

Mr Speaker, the Forest Landscape Restoration programme is a major agenda that will be implemented on a large scale in 2019 with the objective of enrichment planting. This includes the planting of local tree species in degraded forest areas. In this regard, the Forestry Department has developed three nurseries, namely at (i) Sabal, Serian (ii) Jalan Oya, Sibu and (iii) Niah, Miri. The Forestry Department will also enhance the implementation of outreach programmes involving local communities to achieve the objectives of the forest landscape restoration programme throughout Sarawak.

In line with that, research work at the nursery sites and in the field will continue to be strengthened to produce High Quality Planting Materials suitable for Sarawak's forest ecosystems. Research cooperation on this matter is actively being carried out with the Vietnamese Academy of Forest Science (VAFS), Vietnam; the Commonwealth Scientific Industrial Research Organisation (CSIRO), Australia; the China Eucalyptus Research Centre, Zhanjiang, Guangdong, China and several other research institutions within and outside the country as well as the private sector. Meanwhile, disease studies and disease spread mitigation are also actively being carried out with the cooperation of the Forest Research Institute of Malaysia (FRIM), Universiti Putra Malaysia (UPM) and the private sector.

For the information of this august House, forest restoration efforts such as planting trees are not a new initiative and have been carried out by various parties for a long time. Based on records, from 1996 until 2018, a total of 528,238 hectares have been planted with approximately 634 million trees of various species. Accordingly, I call on all parties, including corporate bodies and Non-Governmental Organisations (NGOs), to actively participate to make this programme a success.

Combating Illegal Logging

Mr Speaker, the Government is highly committed to combating illegal logging to the grassroots. We will strengthen collaboration with all enforcement agencies in this State such as the Forestry Department, Sarawak Forestry Corporation (SFC), Sarawak Timber Industry Development Corporation (PUSAKA), State Security and Enforcement Unit (UKPN), Malaysian Anti-Corruption Commission (SPRM), Road Transport Department (JPJ), Malaysian Maritime Enforcement Agency (APMM), Sarawak River Board (LSS), Royal Malaysia Police (PDRM) and others.

Between 2014 and 2018, a total of 32 cases were charged in Court. Of this total, 21 cases succeeded in securing convictions in Court, with 24 persons sentenced to fines and imprisonment.

The Future Direction of the Timber Industry

Mr Speaker, the timber industry's future direction will focus on the development of the value-added products utilising timber from industrial forests to meet the global market requirements. The Timber Industry Transformation Plan and the Forestry and Timber Industry Master Plan (2019-2040) will facilitate the growth of a strategic and sustainable downstream processing industry in Sarawak. To keep abreast with the changes in the raw material supply, the industry players would need to upgrade and retool their manufacturing facilities and reskilling the human resource. This change is inevitable for the industry to remain relevant and competitive globally.

The Sarawak Government will constantly review the current policy on the Log Reservation Quota to support the growth of the value-added industry. The Government also allows the industry players to import timber species which are not endemic to Sarawak to add value to their products. STIDC will also continue to enhance its promotional activities especially participation in international exhibitions and exploring the new market potentials.

For the first quarter (January-March) of 2019, the export of logs and timber products has registered an export earnings of RM1.28 billion, a decrease of 3% compared to RM1.32 billion in the same period of 2018. The decline was mainly attributed to the drop in the production of the products resulted from the declining supply of raw materials and global economic uncertainties.

The Sarawak Artificial Reef Ball Project

Mr Speaker, the Artificial Reef Ball Project is an initiative of the State Government since 1998 to protect and enhance the marine resources along the coastal waters of Sarawak. Up until now, around 7,000 units of artificial reef balls had been deployed with funding from the State Government and Corporate Sectors. Under the current Projek Rakyat, a total of 2,400 units are to be deployed from Kuala Rajang to Balingian and Lawas coastal waters with an allocation of RM10 million. The first batch of 600 units was deployed in the Belawai-Paloh waters in September 2018 by The Right Honourable Chief Minister. Another batch of 600 units will be deployed in the Lawas waters in June 2019. The rest of the 1,200 units will be deployed in Daro to Balingian in September this year.

Specific Issues

Mr Speaker, for the information of the Honourable Member for Krian, the total area approved for the implementation of the Land Planting Facility (LPF) programme in Sarawak is 2.8 million hectares. However, of that total, only 1.05 million hectares or 37% can be planted (plantable area), while the remaining 1.75 million hectares are areas that will not be developed due to various factors such as the following;

(a) Steep slope areas (Terrain Class IV); (b) Buffer Zones for Water Catchment Areas; (c) Wildlife Corridors; (d) High Conservation Value Forest; and (e) Land claim issues by local residents.

Since its implementation in 1996 until 30 April 2019, a total of 435,000 hectares, equivalent to 41%, have been planted with various fast-growing tree species.

The Government is aware that the achievement of this programme is less encouraging. This is due to several factors as follows:-

(a) Facing problems of land ownership claims by local residents; (b) Shortage of labour; and (c) Shortage of high-quality planting materials.

To address the land claim problem, the Government, through the Sarawak Forestry Department, is working together with the Lands and Surveys Department to identify genuine NCR areas to be excluded from the licence areas.

Meanwhile, to address the shortage of high-quality planting materials, the Government, through the Sarawak Forestry Department and the Sarawak Forestry Corporation (SFC) as well as the licensees, is working together to strengthen Research and Development (R&D) work to produce high-quality planting materials.

The Government has also directed forest plantation licence holders to develop their respective catch-up plans to achieve the target of one million hectares overall by 2025.

From 2011 until 31 March 2019, more than seven million cubic metres of timber have been extracted, and royalties and cess amounting to RM70 million have been collected from the forest replanting programme in Sarawak.

For the information of the Honourable Member for Pelagus, with regard to the NCR issue contained within 11 forest plantation licences (LPF) in the Kapit Division as well as any other LPF areas in Sarawak, these have been excluded from the LPF licences. However, if there are still genuine NCR land claims within any LPF licence area, applications for measurement and gazetting work on that land may be submitted to the Lands and Surveys Department. Only after it is gazetted can the land be released.

Haze Issue

Mr Speaker, following the hot weather and lack of rain in March last, in fact yesterday was also hot, yes, several incidents of scrub and peat fires have occurred in Sarawak, especially in the Miri area and at the international border with Brunei Darussalam. This situation was worsened by open burning activities carried out by smallholders along roadsides and in open land areas that have not yet been developed. This caused air quality to reach an "unhealthy" level in Miri on 18 and 19 April 2019.

To address this situation, among the actions taken by the Sarawak Government through NREB are:-

(a) Legal action, where a total of six compounds were issued to individuals caught carrying out open burning without a permit. Meanwhile, four Investigation Papers have been prepared for cases involving open burning by developers; (b) Establishing close cooperation between the Miri Division Resident's Office, the Department of Environment, BOMBA teams and the developers concerned in efforts to prevent and extinguish fires; and (c) Distributing a total of 34,500 face masks to eight schools in the Bandar Baru Permyjaya, Kuala Baram areas and Curtin University.

The Government extends its highest appreciation and thanks for the cooperation given by all parties in addressing this situation.

River Water Quality Management

Mr Speaker, the Sarawak Government has set a general policy for rivers in Sarawak to achieve Class IIB of the National Water Quality Standard for Malaysia (NWQSM). In line with this, NREB has conducted carrying capacity studies for six river basins in Sarawak as follows:-

(a) Batang Sadong; (b) Batang Lassa; (c) Batang Oya;

(d) Batang Mukah; (e) Batang Kemena; and (f) Batang Baram.

This study aims to formulate guidelines and regulations on the amount and types of development activities as well as the level of sewage that may be discharged into a river to ensure that river water quality and river ecosystems are preserved. This study is expected to be completed in July 2019.

Integrated Management of Domestic and Commercial Waste

In line with population growth and rising living standards, the volume of waste disposed has also increased from 774,530 metric tonnes in 2000 to 965,425 metric tonnes in 2018. To address this issue, the Government has also carried out an Integrated Solid Waste Management study which aims to provide a master plan for domestic waste management for the whole of Sarawak. As a result of the study, the Government will draft a policy and strategy to manage and maintain integrated domestic and commercial waste management centres based on reducing the average waste disposed and increasing recycling activities.

Mr Speaker, that concludes my winding-up speech for the Ministry of Urban Development and Natural Resources. I hope that the matters I have mentioned earlier have been able to answer the various issues raised by the Honourable Members in this session. Thank you.

Mr Speaker

Dengan hormatnya saya menjemput, are you ready? Deputy Chief Minister and Honourable Member for Baleh, are you ready to proceed? Or you want to be in the afternoon? Okay. Ahli-ahli Yang Berhormat, sitting is adjourned until 2:30pm in the afternoon.

(Mesyuarat ditangguhkan pada pukul 1.14 tengah hari)

(Mesyuarat dimulakan pada jam 2.45 petang)

(Tuan Speaker mempengerusikan Mesyuarat)

Mr SpeakerEN

Honourable Members, with respect, I invite the Honourable Datuk Amar Haji Awang Tengah Bin Ali Hasan, Deputy Chief Minister and Minister of Industrial Development and Entrepreneurs, to deliver the winding-up speech.

Datuk Amar Haji Awang Tengah Bin Ali HasanPBB · GPSMinister of Industrial Development and Entrepreneurship · Bukit Sari

Terima kasih Tuan Speaker.

Introduction

First of all, I would like to thank Tuan Yang Terutama Yang di-Pertua Negeri Sarawak for his kind advice during his Opening Address in this august House. Among others, Tuan Yang Terutama Yang di-Pertua Negeri Sarawak touched on economic growth of Sarawak and the need for more investments to propel Sarawak towards a high income economy by 2030.

In line with this, my Ministry will refine our focus, strategies and efforts to move our industries and entrepreneurs forward. We are grateful to the previous Federal Government for their support and co-operation on our investment promotion and the entrepreneurship development programmes. We will continue to work closely with the current Federal Government to ensure our development agenda is not interrupted. I would also like to thank Ahli-Ahli Yang Berhormat for your constructive comments and suggestions on issues affecting my Ministry.

Tuan Speaker, I will now report on my Ministry’s achievements thus far.

Industrial updates

Performance of the State’s Manufacturing Sector

Our programmes and initiatives in investment promotion for the manufacturing sector have produced good results, where Sarawak has remained among the top three most preferred investment destinations in Malaysia for the past six years. With the strong support from the Yang Amat Berhormat Ketua Menteri, I am confident that there will be more investments coming to Sarawak. Performance in 2018

In 2018, Sarawak managed to attract a total investment of RM8.8 billion, out of which RM8.6 billion was under Industrial Coordination Act 1975 (ICA) and RM189 million under State Industrial Co-ordination Committee (ICC). These investments are expected to create 1,840 employment opportunities.

Sarawak’s performance in 2018 (RM8.6 billion) was the third highest investment in Malaysia after Johor (RM30.5 billion) and Selangor (RM18.9 billion). The 11 approved investments under ICA were mainly in the following sectors:-

(a) Petroleum related products – RM5.7 billion (methanol); (b) Basic metal products – RM2.8 billion (electro-deposited copper foil and metallic silicon); and (c) Non-Metallic Mineral Products – RM44.5 million (Industrialised Building System components and pre-mixed bitumen).

The 26 approved projects under ICC were mainly in food manufacturing (seafood processing), services (logistics and warehousing), wood-based (veneer, furniture, plywood, etc.) and basic metal products (fabrication of steel and other metals).

Performance in 2019

As at April 2019, Sarawak has supported a total of five projects worth RM17.05 billion for Manufacturing Licences under ICA (high grade steel, cement and chemical products, and food manufacturing). For the same period, a total of nine projects have been approved under ICC totalling RM27.4 million in non-metallic mineral products (batching plant), services (logistics and warehousing), plastic, basic metal and wood-based products (plywood door & sawn timber), etc. These investments are expected to generate about 8,760 employment opportunities in the State.

Tuan Speaker, my Ministry will continue our efforts to diversify our industrial landscape through strengthening and expanding the industries in oil & gas; energy intensive; high-tech; food; shipbuilding alongside the traditional timber based, oil palm based and other manufacturing activities all over Sarawak.

For sustainable economic growth, Sarawak shall move away from the low tech, low wage and labour intensive model. We shall encourage investments in industries that:

(a) employ the latest modern technology to help us move up the value chain in the global economy; (b) reate highly skilled workforce through technology transfer; (c) create supporting clusters and downstream industries that benefit the local business community, especially the SMEs; and (d) promote sustainability, green and environmentally friendly technology.

In this respect, Sarawak has been quite successful in attracting these types of investments, such as those in Samalaju and Sama Jaya.

Samalaju Industrial Park

Tuan Speaker, since its inception in 2008, SCORE has been a major attraction for FDI and DDI. To date, SCORE has attracted a total investment of RM39.94 billion. Samalaju Industrial Park is promoted for the energy intensive and petrochemical industries. To date, it has attracted a total of RM28.43 billion worth of investments from local and foreign multinational corporations from South Korea, China, Singapore, Japan, South Africa and Taiwan, producing polycrystalline silicon, aluminium ingots and ferroalloys, etc.

New investments that have been supported recently include the RM17 billion steel project and the proposed USD133 million foaming agent project. For the steel project, the detailed EIA report has been approved and the company is now preparing the plant design, while the foaming agent project is at the pre-implementation stage.

Currently, eight companies in SIP are in operation, creating 7,670 employment opportunities where 61% (4,250) of the workforce is local. These companies in SIP are generating about RM500 million of economic spinoffs to the local economy monthly. In 2018, the total export value from SIP amounted to RM8.055 billion. Meanwhile, construction works on Malaysian Phosphate has commenced. Sama Jaya High Tech Park

Sama Jaya High Tech Park is promoted as a hub for the high tech sector in Sarawak, being the regional operational base for multinational corporations from Germany, USA, Japan, South Korea and China. They are supported by clusters of industries made up of local SMEs. These MNCs are producing many high tech and sophisticated products used mainly in smartphones, solar panels, automotive and electronic industries.

To date, Sama Jaya has increased its workforce to 12,200 where 98.5% are locals. In 2018 alone, Sama Jaya paid RM460 million in wages to its workforce and exported RM4.6 billion worth of E&E products. These companies in Sama Jaya are generating about RM215 million of economic spinoffs to the local economy every month. I must thank Yang Amat Berhormat Ketua Menteri Sarawak for the success of Sama Jaya as he has been instrumental in the establishment of Sama Jaya when he served as the Minister for Industrial Development.

Major Business Expansions in Sama Jaya and Samalaju

Tuan Speaker, the conducive business environment in Sarawak has enabled these investors to expand their operations to cater to the global demand. I would like to update this august House on some of the major investment expansions in both Sama Jaya and Samalaju.

ILJIN Materials from South Korea has successfully completed Phase I of its electro-deposited copper foil project in Sama Jaya with investment of RM475 million, and it was launched by the Right Honourable Chief Minister in January 2019. ILJIN is now commencing works on its RM475 million Phase II expansion.

LONGi Group from China has also expanded its operations in Sama Jaya with an additional investment of RM820 million for monocrystalline silicon cell production. The plant is already in operation. In recent years, Taiyo Yuden (Japan), X-FAB Sarawak (Germany) and Toko Electronics (Japan) have also expanded their business operations, investing an additional RM493 million, RM499 million and RM105 million, respectively.

In Samalaju, Press Metal expanded its aluminium ingot production and diversified its business capacity to produce aluminium wire rods in 2016 with an additional investment of RM2.2 billion. Meanwhile, OCI Malaysia plans to invest an additional RM569 million to produce caustic soda and expand its polycrystalline silicon production capacity.

Tanjung Manis Economic Growth Area (T-MEGA)

Tuan Speaker, the re-positioning of Tanjung Manis as Tanjung Manis Economic Growth Area (T-MEGA) marks a new milestone in the development of the region. T-MEGA provides investment opportunities in timber processing, Palm Oil Industrial Cluster (POIC), shipbuilding industry, deep sea fishery industry, agro-based and halal-related industry. To date, T-MEGA has attracted a total investment of RM4.02 billion, in both FDI and DDI. Out of this, RM1.1 billion have been realised. In 2018, Tanjung Manis Port handled RM13.2 billion worth of import and export cargoes.

Since the establishment of Tanjung Manis in 1990, the government has invested about RM3.145 billion for infrastructure development such as port, airport, telecommunication, electricity, water, wharf and housing. Presently, a 16-storey administrative centre is under construction to serve as a one stop service centre for both the government and private sectors.

While Sarawak Government has successfully attracted many FDI and DDI which have created more business and employment opportunities for the locals, our SMEs themselves must be proactive to grab these opportunities to grow and expand their businesses so that they are not left behind. They must be creative and innovative by leveraging on advanced technology such as automation, robotics, big data and artificial intelligence to remain competitive and successful.

Entrepreneur Development

Tuan Speaker, Small and Medium Enterprises (SMEs) including micro-enterprises are important in fostering economic growth, creating employment and generating income. They play an integral part to Malaysia’s economic transformation process, representing 98.5% of the business community. The same scenario also applies to Sarawak.

SMEs are closely related to every facet of the economy, from microenterprises to the rural community, the bottom 40% of the income pyramid, suppliers to businesses and end-producers. Based on SME Annual Report 2017/2018, share of Malaysia’s SMEs to GDP was 37.1% in 2017 and expected to increase to 37.4% in 2018. In 2017, SMEs contributed 66.0% to employment opportunities and expected to grow to 66.2% in 2018.

Therefore, the full potential of SMEs must be harnessed, in order to achieve a high income economy. In this respect, my Ministry will continue to assist our SMEs in providing various entrepreneur development programmes and financial assistance, as well as the provision of infrastructure support including Anjung Usahawan and Industrial Parks.

Untuk tahun 2019, Kementerian saya telah memperuntukkan sebanyak RM103.7 juta bagi melaksanakan program-program pembangunan usahawan seperti latihan, dana, pembangunan serta pemasaran produk, infrastruktur perniagaan (taman perindustrian dan Anjung Usahawan) dan khidmat nasihat.

Sementara itu, agensi-agensi di bawah Kerajaan Persekutuan seperti berikut juga turut menyediakan dana sebanyak RM317.36 juta untuk tujuan yang sama bagi tahun 2019:

AIM

-RM232 juta; SME Bank - RM29.4 juta; TEKUN - RM25 juta; MARA - RM22.36 juta;

MIDF - RM6.5 juta; dan PUNB - RM2.1 juta.

Empowerment of PKS

Datuk Amar Haji Awang Tengah Bin Ali HasanPBB · GPSMinister of Industrial Development and Entrepreneurship · Bukit SariEN

Business Fund Assistance

Mr Speaker, the Small and Medium Industry Loan Scheme (SPIKS) is an easy loan of up to a maximum of RM250,000 at an interest rate of 4%, with a loan period of up to seven years. Since its introduction in 1999 until March 2019, a total of RM20.6 million has been disbursed to 237 SMEs. As of March 2019, my Ministry has approved RM1.19 million in SPIKS loans which have benefited nine SMEs for working capital, the purchase of machinery or equipment, and renovation of premises.

My Ministry has also implemented the Graduates Towards Entrepreneurship (GERAK) and Technical and Vocational Entrepreneurs (USTEV) programmes. Both programmes aim to encourage graduates and school leavers from vocational and technical institutions to start and expand their businesses. As of March 2019, a total of RM769,316 has been disbursed to 107 young entrepreneurs.

My Ministry is also planning to introduce the Micro Credit Scheme to help micro entrepreneurs, especially entrepreneurs in the B40 group. The scheme aims to provide easy loans to them to start or expand their businesses. This scheme will be opened to all eligible micro entrepreneurs in Sarawak, regardless of race.

The Sarawak Economic Development Corporation (SEDC) offers the following financial assistance schemes:

(a) Niaga Fest Scheme – an interest-free loan of RM1,000 as capital for sales during fairs/expos; (b) Niaga Jaya Scheme – an interest-free easy loan, maximum RM10,000 for business expansion; (c) Niaga Perdana Scheme – an easy loan at 2% interest rate, RM11,000-RM50,000 for business expansion; (d) Cottage Entrepreneur Development Programme – an assistance scheme in the form of a combination of 60% loan and 40% grant, amounting to RM20,000 for product development; and (e) PUTERA – grant assistance in the form of business equipment, with a maximum of RM5,000.

For 2019, SEDC has been allocated RM5.2 million to implement the above business assistance schemes. To date, SEDC has disbursed assistance of RM592,056 to 135 entrepreneurs through these programmes.

In the same period for this year, the following agencies have also disbursed funds to entrepreneurs in Sarawak:

(a) AIM – RM42.6 million to 33,789 entrepreneurs; (b) SME Bank – RM30.2 million to 31 entrepreneurs; (c) MARA – RM14.4 million to 587 entrepreneurs; (d) TEKUN – RM12.2 million to 605 entrepreneurs; (e) Sarawak Department of Agriculture – RM9.7 million to 600 entrepreneurs; (f) MIDF – RM1.8 million to one entrepreneur; (g) PUNB – RM1.72 million to 5 entrepreneurs; and (h) TERAJU – RM1.6 million to 6 entrepreneurs.

Capacity Development Programme

To enhance the skills and knowledge of local entrepreneurs, my Ministry will continue to implement various capacity development programmes such as Entrepreneurship Training, Food Processing Technology Course, Product Development and so on.

My Ministry has also organised several series of Contractor Entrepreneurs Symposiums which were attended by 2,364 entrepreneurs from Kuching, Samarahan, Serian, Miri, Sibu, Bintulu, Sri Aman, Betong, Limbang and Lawas. The main objective of organising the symposiums was to provide explanations on the procedures and opportunities relating to the implementation of projects under the Rural Transformation Programme. Given the encouraging response, my Ministry will continue to organise this symposium for entrepreneurs in Mukah, Sarikei, Kapit and Marudi.

Promotion and Marketing

My Ministry also assists SMEs in terms of promotion and marketing of products so that more SMEs can expand their markets at the domestic and international levels.

As of March 2019, the Ministry has assisted a total of 292 entrepreneurs to participate in various promotional programmes. Among the promotional programmes that have been and will be organised and participated in by the Ministry are as follows:

(a) Entrepreneur Showcase Programme (SUS) in the districts and divisions of Sarawak; (b) Lesfes Tour 2019 in Kuching; (c) Malaysia International Halal Showcase (MIHAS) in Kuala Lumpur; (d) Halfest 2019 in Kuala Lumpur; and (e) One District One Industry Showcase (SDSI).

My Ministry, together with the Sarawak Timber Industry Development Corporation (STIDC), will organise the Sarawak Timber and SMEs Expo 2019 from 27 to 30 June 2019 at BCCK. The programme will bring together SMEs from various sectors to promote and sell their products. Apart from participation from local and national SMEs, the organisers have also invited SMEs from abroad such as Brunei, Indonesia and India. Given the encouraging response at the previous event, I call on local entrepreneurs to participate in this expo.

Development of Industrial Parks and Anjung Usahawan Premises

Mr Speaker, now, I would like to report on the development of infrastructure facilities undertaken by my Ministry, consisting of 19 industrial parks and 8 Anjung Usahawan with a total allocation of RM366.7 million under RMK-11.

Industrial Parks

Under RMK-11, the Ministry has completed seven projects, namely:

(a) Miri Biovalley Park; (b) Sama Jaya Extension Phase V; (c) Demak Laut Industrial Park Phase 2B Stage 1 and 2; (d) Access Road at Demak Laut Industrial Park; (e) Tebedu Industrial Park; (f) Marudi Industrial Park Phase 1; and (g) The upgrading works for Rantau Panjang Industrial Park Phase 1, Sibu.

For Kapit Industrial Park Phase II, the project is expected to be fully completed by end of May. Physical works for various industrial parks at Betong (69.1%), Demak Laut Phase 2B (continuation) (20.89%), Samalaju SME Clusters (47.57%) and Sri Aman (42.57%) are progressing well as scheduled. Miri Biovalley Park

Mr Speaker, the Miri Biovalley Park is physically completed except for the last batch of equipment which is scheduled to be delivered by end of May 2019. The RM60.6 million project will be fully operational by June 2019 and will be handed over to the Sarawak Research and Development Council under the Ministry of Education, Science and Technological Research, Sarawak.

The completed Miri Biovalley project will be able to greatly assist our local industries especially the SMEs through the followings:

(a) supporting the development of new products and processes especially on bio-based products; (b) providing pilot plant facilities to assist industries in their production at the pilot scale; (c) providing high quality testing and development facilities for industries in the form of product analysis, enhancement and quality assurance; (d) providing facilities for incubators; and (e) providing contract research and training for the industry and research agencies.

Sibu Industrial Park

Mr Speaker, the site for Sibu Industrial Park has been acquired through State fund, with all design and documentation completed in May 2018 and ready for tender purposes. In June 2018, the Federal Government through the Ministry of International Trade and Industry (MITI) had instructed that the project be put on hold. Subsequently, the Federal Government has agreed to fund the project and the Value Management Lab will be held on 13th to 17th May 2019. The tender for this project is expected to be called in the fourth quarter of 2019.

The land acquisition exercise for the proposed industrial parks in Bau and Sematan have been completed while the acquisition exercise for Rantau Panjang Phase 2 Sibu is on-going. Tenders for Bau and Sematan projects are expected to be called by fourth quarter of 2019, while the tender for Rantau Panjang Phase 2 is expected to be called in early 2020. For Sebuyau Industrial Park, a new site has been identified and submitted for siting approval.

Anjung Usahawan Premises

For 2019, the Government has approved eight Anjung Usahawan projects in Kuching, Samarahan and Limbang Divisions. All the sites for these eight Anjung Usahawan projects have been identified and tenders for these projects will be called by fourth quarter of 2019. Preliminary designs for all the premises have commenced. Due to its popular demand, more Anjung Usahawans will be implemented in stages, including one for Telok Melano as requested by the Honourable Member for Tanjung Datu.

Apart from the Anjung Usahawan developed by the Ministry, SEDC has also developed various premises for the entrepreneurs as follows:

(a) 17 incubator facilities benefiting 2,974 entrepreneurs; and (b) 523 business premises such as lockup-shops (gerai) and shop-lots. As at March 2019, 388 units have been rented.

Mr Speaker, for the information of the Honourable Member for Meluan, I understand that the programme for the construction of rural mini petrol stations and the Portable Container System under the Ministry of Domestic Trade and Consumer Affairs (KPDNHEP) is still continuing. Therefore, entrepreneurs interested in this business from the Meluan area may submit applications to KPDNHEP. Woabw, panjang sangat! My Ministry and several other agencies also provide various forms of financial assistance that can be utilised by entrepreneurs to undertake such businesses.

I would like to thank the Honourable Members for Piasau, Samalaju, Meluan, Lingga, Tupong, Layar, Simunjan, Demak Laut and Tanjung Datu for their concern about industrial and entrepreneurial development in their respective areas. My Ministry will consider all the suggestions from the Honourable Members. Conclusion

Mr Speaker, the political landscape of Malaysia has changed after GE14. The new PH Government is now in charge at Putrajaya. But Petrajaya, Kuching remains the bastion of Sarawak based political parties under GPS who are firmly committed to put "Sarawak First".

The GPS Government will maintain good relationship with the PH Government to advance the interests of Sarawak and the expectations of Sarawakians. Our relationship must be based on a Federal System of Government whereby the respective rights, responsibilities and powers of the Federal Government and the State Government as spelt out in the Federal Constitution, and the constitutional safeguards for Sarawak and the sources of revenues assigned to Sarawak are enshrined in the Federal Constitution and the Malaysia Agreement 1963.

For this relationship to be sustained, it is important that the Federal Government must respect and honour the promises made to Sarawak to secure our agreement to the formation of Malaysia in September, 1963. The Federal Government should not encroach or trespass on the State's autonomy over land, land use, and planning, natural resources, immigration and in matters within the executive authority of the State like regulating oil mining under the Oil Mining Ordinance, and the downstream activities of oil and gas industries under the Distribution of Gas Ordinance.

Mr Speaker, the territory of Sarawak before the formation of Malaysia extended to the continental shelf. This territory shall not be altered except with the consent of this august House by reason of Article 2(b) of the Federal Constitution. The Territorial Sea Act 2012 passed by the Federal Parliament has the effect of altering the boundaries of Sarawak and enabling the Federal Government to exercise control over the continental shelf within the boundary of Sarawak. The seabed and subsoil within the continental shelf of Sarawak is "State Land" under the control of the State Government by reason of Sections 2 and 12 of the Land Code of Sarawak and the Sarawak (Alteration of Boundaries) Order in Council 1954. The Territorial Sea Act should be amended or repealed because certain provisions thereof altered the territory of the State without the approval of this august House in contravention of Article 2(b) of Federal Constitution.

Mr Speaker, the people of Sarawak have made their feelings known in this august House through their elected representatives to the infringement of our State's constitutional rights and safeguards by the Federal Government. The support for the Motion by the Honourable Member for Samariang for amendments to the Federal Constitution was unanimous. I would like to thank all the Honourable Members from both sides of the House, for setting the records right and putting across our feelings, our aspirations and our expectations on the Federal Government to right the wrongs, and return Sarawak's rights and autonomy back to Sarawak. There should be meaningful and constructive consultations in those areas which the constitution calls for such consultations.

We are only fighting for the rights of Sarawak which are constitutionally ours. We shall stand solidly behind the Most Honourable Chief Minister of Sarawak in safeguarding Sarawak rights and autonomy in accordance to Federal Constitution and MA63. We are not asking for more, and neither are we asking for less. We are just claiming our right!

Mr Speaker, before concluding this winding-up speech, I would like to express my appreciation to Mr Speaker for successfully conducting the sitting of the State Legislative Assembly (DUN) firmly and well, which facilitated the smooth running of our business. I would also like to thank all the officers involved in making this sitting a success.

Finally, I take this opportunity to wish all the Honourable Members and all the people of Sarawak a blessed fasting month, Happy Gawai Day, Happy Hari Raya and Happy Sarawak Day, which we will celebrate.

MA63, mother of Malaysia, Uniting Sarawak, Sabah and Malaya, Sarawak's autonomy must not be made meaningless, Because Sarawak's rights are ours.

Sarawak's rights are ours alone, GPS, the fighters, stand as warriors, The common people have already spoken out, Defend our homeland, for we come first.

Thus, I conclude this winding-up speech for the Ministry of Industrial Development and Entrepreneurs. That is all, thank you.

Mr SpeakerEN

Now, with respect, I invite the Honourable Tan Sri Datuk Amar Dr James Jemut Anak Masing, Deputy Chief Minister and Minister of Infrastructure Development and Transport.

Tan Sri Datuk Amar Dr James Jemut Anak MasingPRS · BNMinister of Infrastructure Development and Transport · Baleh

Tuan Speaker, my colleague from Bukit Sari, N.82 had just finished with his winding up speech. I am now ready, Sir. May I start? Thank you. Terima kasih, Tuan Speaker.

Jalan pesisir banyak jambatan, Untuk kemakmuran rakyat tempatan, Kesejahteraan rakyat jadi tumpuan, Matlamat benar persidangan dewan.

Dari Kuching hendak ke Sibu, Singgah sebentar di Pekan Engkilili, Saya berucap usah diganggu, Sila duduk jangan lari.

Before I deliberate on my winding up speech, I would like to express my utmost appreciation to Tuan Yang Terutama Yang di-Pertua Negeri Sarawak, Tun Pehin Sri Haji Abdul Taib Mahmud for his invaluable advice and guidance during his opening address at the First Meeting of the Fourth Session of the 18th Sarawak Legislative Assembly Sitting on 29th April 2019.

In His Excellency’s address, one of the issues touched on was the importance of social media which has grown tremendously in the last few years. It plays a pivotal role in our daily life. The use of this social media has become more intense in the Government Agencies especially in the

engagement with the Rakyat. With the presence of the social media, Rakyat’s expectation has become very high for an efficient service delivery and decision making.

Tuan Speaker, breaking news and other important information can be disseminated immediately on social media and are often taken seriously which include the spread of fake news. This can cause panic and severe misinformation which is detrimental and destructive to us all. We have to be mindful of this and must be able to filter all the information shared on the social media, Sir. – Tidak pasti, jangan kongsi.

On the economic performance, Sarawak’s economy recorded a positive growth of 4.6% in 2018. We are confident that under the able leadership of The Right Honourable Chief Minister, Sarawak will continue with its economic growth as we are certain on our direction, focusing on the needs of the Rakyat. The Sarawak Government’s Budgetary Policy of Development-Biased Budget focusing on the rural areas would enable us to ensure that projects implemented are of high impact and Rakyat-centric.

At this juncture, I would also like to take this opportunity to extend my heartiest congratulations to His Royal Highness Al-Sultan Abdullah Ri’ayatuddin Al-Mustafa Billah Shah on his installation as our 16th Yang di-Pertuan Agong of Malaysia on 31st January 2019. I am confident that under his Majesty’s leadership, Malaysia will continue to enjoy harmony, prosperity and progress.

Overview of Sarawak’s Infrastructure

Sarawak is unique and its population is scattered throughout its vast land area. Sarawak’s geographical condition is undulating and its terrain is very challenging, hence, it is difficult to develop the whole region uniformly.

Jabatan Kerja Raya (JKR) Sarawak is currently implementing 388 projects with a total project value of approximately RM43.8 billion (including the three mega projects, namely, the Pan Borneo Highway, the Coastal Road Network and the Second Trunk Road to be completed within the period of five years.

For Pan Borneo Highway Project, JKR Sarawak is leveraging on the Project Delivery Partner (PDP). PDP is appointed by the Government to develop, implement, manage, design, monitor and deliver the project to the owner which is Federal and State Government within the agreed Key Performance Indicators (KPIs) on time and cost. Should the project be delayed beyond the stipulated KPI, there would be a cost penalty on the Project Delivery Partner.

Similarly, in consideration of their complexities and the technical challenges especially with the construction of major bridges as well as extensive peat soil conditions of the Coastal Road Network and the Second Trunk Road projects, JKR Sarawak had also looked into capacity leveraging via Project Management Consultant (PMC). Capacity leveraging via PMC will greatly facilitate the smooth implementation of the Coastal Road Network and the Second Trunk Road projects in view of the tight timeframe for project delivery, which is within five years.

The Sarawak Government had approved the appointment of OPUS Consultants (M) Sdn. Bhd (OPUS) as the PMC on 28 February 2019. OPUS is 100% wholly owned by UEM Edgenta Berhad. UEM Edgenta Berhad is 69.14% owned by UEM group which is 100% subsidiary of Khazanah Nasional Berhad which again is wholly owned by the Ministry of Finance, Malaysia.

OPUS is a leading multi-disciplinary consultancy firm with over two decades of experience. To date, OPUS has gained extensive experience in providing engineering design and supervision consultancy services for some of Malaysia’s most impressive infrastructure and built-environment projects, including expressways & highways, airports & railways and also urban utilities. OPUS’ consultancy expertise and experience allow it to apply proven and innovative methodologies to all

aspects of asset development and asset management services across the whole-life cycle of an asset.

The appointment of OPUS as the PMC is not to replace the responsibility and the day-to-day management of the projects from JKR Sarawak. The integration of the PMC into JKR Sarawak as a Hybrid PMC model serves to enhance the capacity of JKR Sarawak by extending the current technical capacities and capabilities. By doing so, it enables JKR Sarawak to have a close day-to-day involvement managing the project starting from design to Tender Preparation, Estimates and Tender Evaluation, Post Contract and Construction Management.

The State Cost Committee approved the appointment of OPUS as PMC with the following pertinent points:

(a) Partnership and integration with local consultants (such as Concept-P Jurutera Sdn. Bhd., Perunding Iriz and Konsultant Timur) in order to develop local Sarawak professional workforce. There are also active participations by other local consultants as the design consultants for the projects. JKR Sarawak is expecting to appoint a total of around 30 local consultants and the design fee amounting to about RM300 million; (b) The number of professional and semi-professional staff involved in the project must consist of at least 51% Sarawakians; and (c) A Memorandum of Understanding (MOU) with JKR Sarawak’s Research Centre on pavement enhancement, to develop solutions for a better, more durable, recycleable and economical pavement for the future of Sarawak’s infrastructure.

The PMC model also allows for:

(a) The flexibility of expansion and reduction of project team size based on requirements throughout project phases, therefore, optimizing the need for professional human capital while reducing the burden of overhead cost; (b) Knowledge transfer of project management skills and best practices for development of JKR Sarawak’s workforce; (c) Collaboration with local universities to provide Graduate Learning & Development Programme; and (d) Reduction of personnel requirement. For Coastal Road Network and Second Trunk Road projects, the estimated personnel required throughout the entire phase of the project, by means of capacity expansion of JKR Sarawak through PMC is around 200 personnel.

For the information of this august House, the coastal road network projects are proceeding within the targeted timeline with four projects which have already been awarded with an expected cost of about RM600 million below estimated project cost.

Over the years and under the current development agenda, we are witnessing rapid infrastructure development particularly on the implementation of Rakyat-centric projects in the rural areas.

The obvious evidences are the implementation of many high impact projects which amongst others are:

(a) The Coastal Road Network; (b) The Second Trunk Road, namely, (i) Jalan Kota Samarahan/ Batang Sadong Bridge/ Sebuyau/ Batang Lupar/ Batang Saribas/ Roban/ Sarikei/ Upper Lanang Bridge, Sibu; (ii) Jalan Sebuyau/ Lingga/ Sri Aman/ Betong; and

(c) The New Kuching/ Samarahan Trunk Road.

Tuan Speaker, infrastructure as we all know, is neither about business nor having high profile or mega projects. It is about providing the physical components into interrelated systems, providing commodities and services essential to enable, sustain or enhance the societal living conditions of the Rakyat. It is the road network that paves the way for greater productivity, powers smartphones for better communication and advancement in digital technologies, bringing water to our taps and most importantly, shortens our travelling time through continuous and uninterrupted journeys.

With the successful completion of the construction of the first Works Package of the Pan Borneo Highway from Telok Melano to Sematan, this would give a socio-economic well-being to the populace at the surrounding area. This is in tandem sir, with Sarawak’s Development Agenda, which is to continue with its socio-economic development and rural transformation endeavours.

With greater connectivity taking place, our Rakyat will be able to fully enjoy the good quality of life with the necessary infrastructure and basic amenities, particularly for those in the rural areas. This would open up greater opportunities in the rural areas to further spur their economic activities and improve the standard of living of the Rakyat in Sarawak.

Rural Transformation Initiatives (RTI) Cabinet Committee on Rural Transformation (CabCom-RT)

Tuan Speaker, Cabinet Committee On Rural Transformation (Cabcom-RT). I reported in the last sitting of this House that the Sarawak Government has approved an allocation of about RM335.1 million to implement 306 projects under the Cabinet Committee on Rural Transformation (CabCom-RT). I am pleased to report that as at March 2019, 167 or 55% of the 306 Rural Transformation Initiatives (RTI) projects have been completed while the rest are in various stages of implementation.

Projects under CabCom-RT are those which are not normally planned or implemented under the Malaysia Plan. These are normally small projects or programmes but have significant impact on the lives of the rural population. For examples, the establishment of Cluster Clinics under this CabCom-RT have been made possible because the CabCom-RT initiated the purchase of medical equipment to equip the rural clinics so that these clinics can serve smaller rural clinics around it. Thus, people in the Baram area need not go to as far as Miri to get some of their medical services; instead, they can go to Long Lama Cluster Clinic to do so, saving them the travelling time and transportation costs.

For the resettlers at Murum Hydro Dam area, the CabCom-RT has been able to speed the surveying of land for their residential lots, agriculture lots and home garden at Metalun Resettlement Scheme in Belaga.

For rural dilapidated schools, the CabCom-RT has been able to repair and upgrade 26 schools, in the rural areas including the SJK Chinese Schools and Mission Schools which could not be implemented in the normal Malaysia Plans.

For the rural population shoes land is affected by some conservation projects, for example, the orang utan conservation projects in Batang Ai, the CabCom-RT is introducing income generating community support programmes to cater for their loss of economic opportunities. There are many other examples of the so-called “intervention projects” under the CabCom-RT.

On this note, Tuan Speaker, I must commend the efforts of the nine Lead Ministers who are responsible for the guidance and achievement of Key Results Areas (KRAs) under their charge. The Lead Ministers, who are members of this Committee are assigned to lead their KRAs, and are responsible for the outcomes of their respective KRAs. I must also record my appreciation to the Working Committee led by Deputy State Secretary (Rural Transformation), State Implementation Monitoring Unit (SIMU) and many agencies and ministries for their effective supporting role to the CabCom-RT.

Tuan Speaker, because of their small sizes, these projects and programmes can sometimes be overlooked in the normal Malaysia Plan. This is where the CabCom-RT would be able to play their role to cater for these projects, which are much welcomed by the rural communities. Some people also refer to these initiative as “last miles projects”. For example, some kampung enjoy 24-hour electricity through connection to the nearby grid. Some kampung have not been able to enjoy treated water in the past even though the main pipeline is just nearby. This is now made possible because the CabCom-RT, through its Lead Minister, identified such kampungs to be connected to the nearby watermain.

Because of its importance and the difference, it can make to the lives of the rural communities. As Chairman of the CabCom-RT, I feel strongly that this Committee should be further enhanced and be continued in the future. There are many more “last mile projects” and “intervention projects” or programmes that we can identify for the convenience and livelihood of the rural population. These are in short, are the low hanging fruits.

With the highest ever Sarawak Budget allocation of about RM9 billion for development, particularly for rural development, this is Sarawak Government’s way of sending out the message that we are indeed resolute and adamant about our concern towards rural population. We want our rural population to progress in tandem with our urban counterparts and global development in general. Projek Rakyat

Tuan Speaker, since being appointed as Sarawak’s 6th Chief Minister, he has introduced 65 initiatives with the theme, “For the People of Sarawak – Team Abang Jo Initiatives”, to further boost growth in the various sectors and propel Sarawak to greater heights. One of the 65 initiatives of Team Abang Jo, which is close to the heart of my Ministry, is the acceleration of project implementation. This initiative is introduced to improve the monitoring systems of high impact rakyat-centric projects with the setting up of the State Development Coordination Committee (SDCC). The committee meets regularly to get updates on the progress and to resolve issues that may hinder the smooth implementation of Projek Rakyat.

As a member of SDCC, my Ministry has taken tasked to take charge of 85 infrastructure projects worth about RM5.18 million, comprising the followings:

(a) 47 roads amounting to about RM2.3 billion, amongst others are the Proposed Upgrading and Rehabilitation of Belaga to Menjawah Road at Kapit Division worth RM105 million, membina jalan dari Sibu Jaya ke Jalan Kong Yit Kim at Sibu Division worth RM175 million and jalan menuju ke Rumah Panjang Nicholas anak Sandom (34 km), Sungai Sigu, Sebauh at Bintulu Division worth RM200 million;

(b) 16 bridges amounting to about RM2.2 billion, amongst others are Projek Jambatan Muara Lassa at Mukah Divison worth RM671.1 million, Pembinaan Jalan Pasi ke Jalan Tanjung Manis termasuk pembinaan Jambatan Batang Rajang at Sarikei Division worth RM450 million and proposed Sungai Limbang Bridge, Sungai Bunut No.2 Bridge and connecting roads in Limbang Division worth RM205 million;

(c) 20 government buildings amounting to RM335 million; and

(d) 2 STOL ports namely, Lapangan Terbang Baru Bukit Mabong worth RM180.7 million and Lapangan Terbang Baru Bebuling in Spaoh, Betong worth RM176 million.

To date, five projects have been completed, 52 projects under construction, five projects under tender, 21 projects under design and two projects under feasibility study.

Costal Road Network

Tuan Speaker, the implementation of the Costal Road Network project is currently on-going. Our Government is fully committed to ensure that their project is implemented in a cost effective and timely manner so that the benefits of economic growth can be enjoyed by the rakyat.

Under the 11th Malaysia Plan, the Sarawak Government provides sufficient allocation for the project. Currently, the components of the project are at various stages of implementation.

Tuan Speaker, I would like to enlighten this august House on the status of the Costal Road Network project:

(a) For Jalan Pasi to Jalan Sarikei/Tanjung Manis including Batang Rajang Bridge in Sarikei Division, the Letter of Award was issued on 22nd February 2019 with the contract sum of about RM321 million and is scheduled to complete on 21st March 2023. The ground-breaking ceremony for the project was officiated by The Right Honourable Chief Minister of Sarawak on 6th April 2019; (b) For Sungai Krian Bridge, the Letter of Award was awarded on 25th February 2019 with a contract sum of about RM75 million and is scheduled to complete on 24th March 2022; (c) For Batang Paloh Bridge, the Letter of Award was issued on 10th April 2019 with a contract sum of about RM299 million and is scheduled to complete on 7th May 2023; (d) For Muara Lassa Bridge, the Letter of Award was issued on 22nd February 2019 which a contract sum of RM598 million and is scheduled to complete on 21st March 2023; (e) For Batang Saribas Bridge, the tender was advertised on 7th January 2019 and closed on 11th February 2019. The Letter of Award will be issued soon; (f) For Batang Rambungan Bridge which was original a Federal funded project and now undertaken by the Sarawak Government, the tender was advertised on 13th April 2019 and the closing date is on 8th May 2019 which is today; (g) For the upgrading and rehabilitation of Coastal Road Network, it has two packages, that is, Packages A dan B. Package A comprises 13 sub-packages (namely A1 – A13) and Package B comprises 10 sub-packages (namely B1 – B10).

(i) For sub-package A4 (Kampung Sungai Buluh/Sebuyau), tender was advertised on 13th April 2019 and is closing date is on today 8th May 2019, which is today. Meanwhile, the rest of the 12 sub-packages is in the process of tender documentations; and (ii) For sub-package B1 (12.3 km of Sungai Nyalau/Bakam section), tender was advertised on 27th April 2019 and will close on 22nd May 2019. The other nine sub-packages are under site investigation and design.

(h) For Batang Igan Bridge which was originally a Federal funded project and now undertaken by the Sarawak Government, it is currently under detailed engineering design. This project will be tendered in the third quarter of this year; and (i) For Batang Lupar Bridge, which was originally a 50:50% cost sharing with the Federal Government and is now fully undertaken by the Sarawak Government and is currently under detailed engineering design. This project will be tendered within the fourth quarter of this year.

Second Trunk Road Project

Tuan Speaker, the Second Trunk Road serves to provide shorter alternative routes to Pan Borneo Highway and the Coastal Road Network.

The first section of the Second Trunk Road is from Kota Samarahan to Roban, which is approximately 112km of single carriageway JKR R5 two-lane highway. The last section which is approximately 30km, includes the upgrading of the existing Jalan Kelupu/Jalan Tanjung Genting Lanang Bridge, Sibu from two lanes to four lanes JKR R5 highway. The Sebuyau/Lingga/Sri Aman/Betong Expressway is approximately 94km of single carriageway JKR R5 two-lane highway. Currently, the project is under design and it is expected to be tendered within the fourth quarter of this year.

Tuan Speaker, the Sarawak Coastal Road Network will be connected seamlessly between towns such as Kota Samarahan, Asajaya, Sadong Jaya, Sebuyau, Kabong, Tanjung Manis, Daro, Matu, Igan, Oya, Mukah, Balingian, Bintulu and Miri to the Pan Borneo Highway while the Second Trunk Road will link Kuching-Sibu with the Pan Borneo Highway through Jalan Sebuyau-Sri Aman-Betong.

The aspiration of the Sarawak Government on the need for greater connectivity since independence will become a reality once all these projects are successfully completed within the period of five years. Not only does it enhance greater connectivity, it also bring substantial socio-economic development, particularly in the agriculture sector and opening up of new areas for development. Traffic Management Division

Tuan Speaker, Sarawak is the “victim” of its economic success. Economic success in terms of excess money to be spent, leads to the increase in the number of vehicles on the road. In 2018, we have about 68,000 registered new vehicles with about 22,000 newly registered drivers in Sarawak. The consequence of such increase in the number of vehicles is simple Sir, traffic congestion.

This is a glaring indicator that Sarawak is undergoing a tremendous economic, transformation like other States in Malaysia. Traffic congestion does not only occur in our cities like Kuching and Miri, but also in our rural town. Even town like Kapit Sir, which is not connected by road to the rest of Sarawak yet, does not escape the woes of traffic congestion. During peak hours which is (6am-8am and 5pm -6pm), Kapit is experiencing at least a kilometre–long queue at both sides of the traffic light. I cannot imagine Sir, what it would be like when the town of Kapit is connected to the rest of Sarawak by October 2020.

Traffic congestion in Greater Kuching is getting worse by the day. The traffic gridlock is everywhere during peak hours and the worst is along the Kuching/Kota Samarahan expressway. Road users are lucky if they can drive at 10km per hour along this expressway. Such congestion is both a waste of time and fuel, and can caused tremendous stress and frustration to both the drivers as well as the passengers alike.

My Ministry has completed a traffic study on the five roundabouts to ease the congestion along Kuching/Kota Samarahan Expressway. As a short-term measure, the Government will construct two punch through roundabouts with traffic lights while the remaining three will be upgraded to traffic light intersections. The construction plan will commence by the end of this year.

Concurrently, Sarawak Government will construct an alternative road by-passing Kuching Central Business District from Petra Jaya to Kota Samarahan with a new bridge crossing Sungai Sarawak within the vicinity of BCCK, upstream of Senari Port.

The traffic congestion is an ever-growing problem in our cities and towns in Sarawak. Therefore, we must take this matter seriously and urgently. I was briefed by a traffic management consultant that transportation in Kuala Lumpur for instant, is 75% private and 25% public, Singapore is 33% private versus 65% public while Kuching, is 96% private and only 4% public. Unless we are

serious about our traffic management, Sarawak will suffer traffic gridlock in 10 years time even less, Tuan Speaker.

A proposal will be submitted to Sarawak Government to engage a local Traffic Management Specialist Consultant to carry out traffic study in Greater Kuching first, then Kapit town Sir before the town is linked to the rest of Sarawak by October 2020.

There is also a dire need for the Sarawak Government to have a Traffic Management Division in my Ministry to be headed by experts in managing our traffic flow. The sooner the better, Tuan Speaker. E-Hailing Services

Tuan Speaker, regulating e-hailing is one of the Government’s initiatives to create a level-playing field for both the e-hailing and taxi services. Jabatan Pengangkutan Jalan (JPJ) will be enforcing a new ruling on e-hailing drivers effective 12th July 2019 in accordance with Land Public Transport Act 2010, Commercial Vehicles Licensing Board Act 1987 and the Road Transport Act 1987.

In line with these new ruling, e-hailing drivers are required to possess Public Service Vehicle (PSM) license similar to taxi drivers. Effective 1st April 2019, these drivers can submit their PSV license application to any Driving Institute approved by JPJ. Criteria for PSV License application are as follows:-

(a) Four to eleven-seater vehicle are allowed; (b) Annual PUSPAKOM inspections when the age of the vehicle is more than three years of the date of registration; dan (c) Age of vehicles: (i) CKD (Completely Knock Down) – not more than 10 years from the date of JPJ registration; (ii) CBU (Completely Build Up)- not more than 10 years of manufactured; (iii) age of vehicle should be based on the approval by Commercial Vehicle Licensing Board based on vehicle permit; (iv) E-hailing sticker from JPJ to be placed on the front-screen; and (v) Insurance coverage for driver; passengers and third party.

Road Safety

Tuan Speaker, based on JPJ’s statistics, the average newly registered vehicles and drivers in the last three years (2016-2018) in Sarawak is about 62,000 and 24,000 respectively.

The road traffic accident is the fifth leading cause of deaths in Malaysia. They have adverse effects on everyone and will result in the loss of human resources as well as productivity. In Sarawak, Polis DiRaja Malaysia recorded 20,065 traffic accidents in 2016, 19,832 in 2017 and 20,600 in 2018. For 2018 alone in Sarawak, these accidents led to 322 deaths (about one fatality per day), 204 serious injuries and 190 minor injuries. This statistic is horrifying Tuan Speaker, horrifying reminder as we strive to achieve better and broader land transportation network. We must impress upon the public that road safety is of paramount importance. The causes of road accident indentified are:

(a) driving under the influence of alcohol or drugs; (b) speeding; (c) beating the red light; (d) changing lane without signalling; (e) using handphone while driving; and (f) poor road conditions.

Road traffic accidents can be avoided, Tuan Speaker. In many countries, the number of road traffic accidents has declined despite increasing motorization. The Road Safety campaign plays a vital role in enhancing road users’ awareness on road safety practices. This campaign emphasises on educating, particularly the young road users on the impact of road accidents and its preventions.

Tuan Speaker, the Road Safety Council practises a balanced approach in implementing road safety initiatives based on the 5E concepts:

(a) Education; (b) Enforcement; (c) Engineering; (d) Environment; (e) Evaluation.

Education plays the most important role to foster and inculcate the culture of road safety to all of us. The revised Road Safety Education (Pendidikan Keselamatan Jalan Raya) curriculum has been taught since January 2019 to all levels in all primary schools while for pre-schools and lower secondary schools, students will be taught in 2020.

Tuan Speaker, in Sarawak alone, there were about 30,000 summonses issued in 2018 as reported by JPJ. Amongst the offences committed were heavily tinted vehicle windows (706 cases), unfastened seat belts (707 cases) and overloaded lorries (3,199 cases).

Road Safety lies in all of us; you and me. Political commitment to educate the public is also essential. Therefore, through education we can change our behaviour to make roads safer for everyone. Together Tuan Speaker, we can make the difference.

Safety During Road Construction

Safety of road users and workers during construction is the responsibility of all parties involved, be they road users, construction workers, contractors, supervising consultants, implementing agencies or also the coordinating ministries.

My Ministry which is responsible for coordinating infrastructure development projects in Sarawak is also taking Road Construction Safety as a serious issue that needs to be addressed diligently and continuously. MIDT, Tuan Speaker and agencies under its purview have pledged safety as their utmost concern and priority.

On this note Tuan Speaker, we call upon the Safety Officers of all implementing agencies to be vigilant to assess all risks and hazards at construction sites and immediate mitigation plans to be put in place so as to avoid accidents. Inspection by Safety Officers of implementing agencies on a daily basis must be carried out as all risks and hazards at road construction sites change, continuously.

We request all road users also be vigilant at all times and to be extra careful while road construction is going on. They have to be responsible for their own safety, too. One of the ways it to reduce their speed upon approaching road construction sites and be alert of the hazards that may be encountered along the way. We do apologise for any inconvenience caused during construction, which is unavoidable. However, we will strive to minimise inconvenience at all times.

Road users are kindly advised to drive slowly and cautiously at the road construction sites and where possible, to use alternative routes or avoid travelling at night. The maximum speed recommended at road construction sites is 30km/hr.

Air Transport

Tuan Speaker, in ensuring that the network of air connections can be expanded throughout Sarawak, the Sarawak Government has approved the proposal to build new airports at Bebuling, Betong Division and Bukit Mabong, Kapit Division as these are part of the long-term plan for the areas. The increase in air connectivity in these areas would not only give impact to the agriculture sector but could also boost our tourism industry, which is vital for our economic prosperity.

Due to the greater connectivity and accessibility, Air Asia has established air route networks to all major cities and towns in Sarawak and has undoubtedly made Air Asia the leading airline service provider in our Land of Hornbills. We are indeed happy that low fare air tickets offered by Air Asia has made travelling cost more affordable.

Leveraging on the Sarawak students’ welfare Tuan Speaker, the Right Honourable Chief Minister had announced... (Interruption)

Encik Chiew Chiu SingDAP · PHTanjong Batu

Thank you Tuan Speaker, thank you Honourable Minister. I mentioned about the Bintulu Airport where if you come in from Kuala Lumpur and have to do immigration clearance. And if you land on the tarmac and not on the aero bridge then you have to walk the stairs up and it’s very troublesome indeed for those elderly person and those we have problem walking and all that, whether you will either have the Immigration move downstairs or whether you build escalator for people to go up because there is one staircase going up and it’s making if very difficult for the passengers travelling walking up and down the stairs. Thank you.

Tan Sri Datuk Amar Dr James Jemut Anak MasingPRS · BNMinister of Infrastructure Development and Transport · Baleh

Tuan Speaker, if my collegues from Tanjung Batu, if you patience enough I will answer your question later. Please ya. Let me continue again with this Tuan Speaker if I may, leveraging on the Sarawak students welfare, the Right Honourable Chief Minister had announced a maximum subsidy of RM600 per year for each Sarawakian students studying in West Malaysia, Sabah and Labuan for return tickects to their home town in Sarawak during the festive seasons.

This is an initiative taken by the Sarawak Government to help ease the burden of the university students studying in West Malaysia, Sabah and Labuan. We are fortunate to have a caring Government that continuously looks into the welfare and well-being not only the Rakyat but including the students who studying away from Sarawak.

Sarawak-Owned Ports

The cargo throughput handled by Sarawak-owned Port Authorities namely, Kuching, Kajang, apa salah ini, Kuching, Miri, Tanjung Manis and Samalaju indicated an increase of 7.2% or 1.53 million tonnes from about 21.26 million tonnes in 2017 to about 22.79 million tonnes in 2018.

Kuching Port Authority, Miri Port Authority, Rajang Port Authority and Samalaju Port recorded an increase of 6.1%, 7.3%, 11.8% and 49.6% in 2018 respectively in cargo throughput. However Tuan Speaker, Tanjung Manis Port Authority reported a decrease of 24.9% mainly due to a decrease in export of timber commodities handled through this port.

The main issue that constrains the growth of these ports is the shallow access channel. The shallow depth of Kuala Baram has become an obstacle for Miri Port to attract bigger vessels. Presently, Miri Port handles a cargo of 25.8% of its design throughput capacity of 3.5 million tonnes, whereas this port located strategically within a vast industrial estate at Kuala Baram, servicing Miri City and the northern region of Sarawak, facilitating the local industrial and commercial and economic activities of Miri Port in Sarawak as a whole.

In 2010, the Ministry of Transport, Malaysia has appointed a local specialist consultant in the fields of hydraulic and coastal engineering, port economics, logistics and transport planning to carry out the study on the deepening of Kuala Baram access channel under the Federal Government funding. The study was completed Tuan Speaker in October 2012.

The proposed capital dredging of the Kuala Baram riverine access channel was submitted to the Federal Government under the 11th Malaysia Plan but it was not approved.

Therefore, the proposal will be resubmitted in the 12th Malaysia Plan. Meanwhile, a task force committee headed by Miri Port Authority has been set up to work out short-term strategies to alleviate the shallow channel. One of the proposed solutions is to utilize the channel maintenance fee collected to carry out the dredging of the access channel in stages.

Kuching Port, with its strategic location and servicing the capital city of Sarawak, is also facing a similar riverine access channel issue. However, the Sarawak Government has managed to secure funding from the Federal Government for capital dredging and it is implemented by Jabatan Laut Malaysia under the Ministry of Transport, Malaysia.

As of March 2019, the physical progress was reported at 75.4% against the schedule of 66.7%. They have an advance in term of work development. The project is expected to be completed as scheduled on 24th November 2019 this year.

Sarawak Rivers Board

Tan Sri Datuk Amar Dr James Jemut Anak MasingPRS · BNMinister of Infrastructure Development and Transport · Baleh

Sibu Passenger Terminal

River transport remains as an integral part of our transportation network in Sarawak with a total of 2.6 million passengers using our waterways and a total of about 5,000 registered vessels of various tonnages as recorded by Sarawak Rivers Board in 2018.

The busiest terminal in Sarawak is the Sibu Passenger Terminal with a passenger traffic in excess of one million handling capacity. Although there is a high passenger traffic, the terminal is under-equipped to meet the demand especially during festive seasons.

Sarawak River Board or SRB is planning to upgrade the existing Sibu Passenger Terminal in order to provide quality service to the passengers and as an alternative to the land transportation. This project is essential and will greatly contribute to the mobility of the Rakyat staying along the Batang Rajang river.

The Proposed Upgrading of the Sibu Passengers Terminal which includes the upgrading of arrival and departure facilities at the terminal, the goods loading/unloading area, pontoon and the River Monitoring System estimated at RM45 million will be submitted under the 12th Malaysia Plan for consideration by the State Government.

Issues raised by Ahli-Ahli Yang Berhormat

Tuan Speaker, please allow me to respond to the various issues raised by Ahli-ahli Yang Berhormat while debating on Tuan Yang Terutama’s address in this august House.

Sarawak Government Funded Roads

For the information of Ahli-Ahli Yang Berhormat for Repok, Tamin and Pelawan, the following proposed roads have been submitted under the Mid Term Review (MTR). These roads are:

(a) Proposed construction of Jalan Nyelong By-Pass to Jalan Kwong Ming/Minah (2km at an estimated cost of RM21 million); (b) Proposed upgrading of Jalan Nyelong By-Pass to a dual carriageway (3.6km at an estimated cost of RM32.2 million); (c) Proposed construction of Jalan Rumah Janggit/Rumah Bubong, Ulu Dijih, Tamin (9.5km at an estimated cost of RM57 million); (d) Proposed construction of Jalan SK Pakoh/Nanga Bunau, Ulu Oya (11km at an estimated cost of RM66 million); (e) Proposed construction of Jalan Sibu Oya Outer Ring road (30km at an estimated cost of RM300 million); (f) Proposed construction of Jalan Ulu Sungai Merah/Kemuyang (12.5km at an estimated cost of RM100 million); and (g) Proposed construction of Jalan Aman to Jalan Sibu Airport (4.5km at an estimated cost of RM38 million).

However, Tuan Speaker, these projects were not approved under MTR. My Ministry, so talking about hope yet, my Ministry will pursue these projects again under the 12th Malaysia Plan for their consideration. Sarawak Government Funded Bridges

Tuan Speaker, for the information of Ahli Yang Berhormat for Balingian, the proposed Jambatan Kedua Mukah including its access roads (also known as Kampung Penakub/Kampung Teh Bridge, 150 meters length at the estimated cost of RM30 million) has been submitted under the Mid Term Review (MTR) but it was not approved.

My Ministry, however, will pursue this project again under the 12th Malaysia Plan for its consideration. Electric Railway Network from Kuching to Miri

Tuan Speaker, in response to the issue raised by Ahli Yang Berhormat for Kabong on the possibility of undertaking a study to construct electrified railway lines railway network from Kuching to Miri, this matter needs to be studied seriously.

At the moment, Tuan Speaker, our priority is to provide connectivity and to improve road network system through the implementation of various projects namely, Coastal Road Network, Second Trunk Road, Pan Borneo Highway and urban roads and rural road projects as well as rural air connectivity. Ferry Services

My Ministry acknowledges the importance of ferry services in the coastal belt of Sarawak where there are no bridge crossings.

For the information of Ahli-Ahli Yang Berhormat for Daro and Kabong, JKR Sarawak pledges to study the need to deploy bigger or additional ferries at Muara Lassa and Batang Paloh and the new ferry service at Kabong, crossing at Sungai Krian to connect Pekan Kabong and Kampung Paloh. The study is expected to be completed by the end of this year.

Sungai Sarawak Kanan

Tuan Speaker, for the information of Ahli Yang Berhormat for Tasik Biru, my Ministry concurs with the statement made by the Right Honourable Chief Minister of Sarawak to promote tourism on the use of river as the mode of transportation for tourism activities from Kuching Waterfront to Pekan Siniawan.

To ensure that the channel is safe for navigation, the Sarawak Rivers Board will carry out river cleaning activities from Muara Sungai Sarawak Kanan until Pekan Siniawan by the end of this year and thereafter, to Clearwater Cave by July next year 2019.

Request for New Projects

Tuan Speaker, in response to the other various projects, I would like to highlight the requests by Ahli-Ahli Yang Berhormat, namely:

(a) Ahli Yang Berhormat for Tupong on the proposed construction of Jalan Kampung Paroh and Kampung Sejijak to Jalan E-Mart/Stapok; (b) Ahli Yang Berhormat for Tamin on the request: (i) To upgrade Jalan Nanga Tajam/Nanga Dijih, Tamin, Jalan Sapudun, Balingian and the existing logging road at Ulu Oya, Ulu Pakoh, Ulu Mukah and Ulu Selangau; and (ii) The new road construction of Jalan Rumah Pengarah/Rumah Emong, Uu Mukah, Jalan SK Nanga Selangau/Rumah Dinggai, Ulu Mukah, Jalan Rumah Bubong/Nanga Dijih, Tamin.

(c) Ahli Yang Berhormat for Beting Maro, on the proposed upgrading of Jalan Pusa/Beting Maro; (d) Ahli Yang Berhormat for Tanjung Datu, on the proposed alternative road to Kampung Stunggang Baru, Lundu; (e) Ahli Yang Berhormat for Balingian, on the replacement of bridge at Kampung Tutus Uu and Kampung Suyong; (f) Ahli Yang Berhormat for Pelawan, on the proposed construction of road from Jalan Teku to Sibu Golf Club;

(g) Ahli Yang Berhormat for Murum, on the proposal: (i) To construct the alternative road to SK Kuala Kebulu; and (ii) Upgrading of Jalan Rumah Mering Madang/Rumah Wan Usin/Rumah Lasah Tuba/Rumah Pesu/Rumah Resah/Rumah Ramli, Tubau, Jalan Rumah Ding/Rumah Ugak, Tubau, Long Bala and Jalan Long Koyan.

(h) Ahli Yang Berhormat for Bukit Semuja, on the proposal to construct:

(i) An exit road from Taman Pasir to Serian Flyover No. 1 and P-Turn or traffic ight junction to Serian town; (ii) A minor bridge for motorists and pedestrian crossing Sungai Sadong to the Mosque and underpass at Sadong Bridge; and (iii) A P-Turn or U-Turn at strategic location along the Pan Borneo Highway near kampungs.

(i) Ahli Yang Berhormat for Engkilili, on the proposed:

(i) Construction of Jalan Rumah Jabu, Nanga Tebas/Nanga Belaie/Nanga Mujuau, Ulu Skrang; (ii) Upgrading of ex-logging road from Sebliau Junction/Rumah Merutih Junction/Rumah Dau/Klinik and SK Nanga Entalau/Nanga Emperan/Panchor/SK Nanga Mejuau/Rumah Lidom, Sungai Paya, Ulu Skrang; (iii) Upgrading of Jalan Rumah Gait, Keranggas and Rumah Bellisan, Uu Skrang; (iv) Construction of road from Stuga to Jalan Empelam/Jalan Ensurai/Basi/Leo/ Tekalong/Tanjong/ Langkang/Tawai/Ijok/Pak/ Sengkabang/Nanga San in Sri Aman;

(v) Construction of Jalan SK Nanga Empelam/Geligau Ili, Geligau Ulu/Spalau and Rumah Nayang, Engkilili; (vi) Construction of Jalan Rumah Nibong, Titok Ulu, Titok Hilir/Bunu, San Semanju; (vii) Construction of Jalan Rumah Merio/Skim Merindun; another one is I think eight, that one was seven, now is eight (viii) Construction of bridge crossing Sungai Ulu to connect Rumah Dau, Nanga Entalau, Klinik Kesihatan Entalau, SK Nanga Entalau with Jalan Ulu Skrang; (ix) Construction of bridge to Rumah Ambu, Emperan to Jalan Ulu Skrang; and finally (x) Construction of suspension bridge to connect Merio to Pekan Engkilili.

(j) Ahli Yang Berhormat for Kedup, on the proposal to upgrade Jalan Kampung Sungai Aping/Kampung Empessa/SK Triang; (k) Yang Berhormat for Batu Danau on the proposal to upgrade Jalan Bukit Sagan to SK Ulu Lubai/Jalan Long Serangan/Jalan SK Ukong/ Jalan Iduk Sangkar/Jalan Kampung Tanjung Unggar/Lubuk Bidai/Jalan Kampung Bambangan/Braong/Jalan Rh Nonong, Kampung Kelati/Jalan RH Peter Ipok, Kampung Sepangih dan Jalan Rh Agan Siran, Ulu Tubai; and (l) For the information of Ahli Yang Berhormat for Machan, on the road linking Ulu Poi to Ulu Machan dan continuation of road beyond Nanga Jerangku.

My Ministry, Tuan Speaker recognizes the importance of all these requests and JKR Sarawak will study them thoroughly, taking cognizance of their benefits to the Rakyat and financial implications to the Sarawak Government before their implementation.

Approved Projek Rakyat

For the information of Ahli Yang Berhormat for Bukit Goram, the Proposed Jalan Nanga Menuan/Nanga Setepus is an approved project under the Projek Rakyat programme with a project cost of RM67.5 million. The proposal to construct the remaining 5 km upper Sungai Menuan, Nanga Setepus which include Rumah Seli, Rumah Gia, Rumah Jackson, Rumah Ujah dan SK Ulu Menuan is part of the said project which is to be implemented under Phase 2. Its implementation is subject to the approval of additional funding.

For the information of Ahli Yang Berhormat for Meluan, the proposed Jalan Rumah Kedit, Sungai Buloh/SK Ulu Entabai Kemalih, Pakan (Phase 1: 10 km road) is an approved project. The remaining 13 km of road to be implemented under Phase 2. Its implementation is subject to the approval of additional funding. Project Progress

Tuan Speaker, for the information of Ahli Yang Berhormat, the upgrading and widening of Jalan Bleteh, Kapit (3km at an estimated cost of RM16.5 million) has been considered by the Right Honorable Chief Minister of Sarawak while he was in Kapit on 23rd April this year.

For the information of Ahli Yang Berhormat for Pelawan, the land acquisition for the proposed upgrading of Jalan Ulu Sungai Merah and Jalan Oya is in progress by the Lands and Surveys Department. The implementation of both projects will be submitted under the 12th Malaysia Plan for consideration.

For the information of Ahli Yang Berhormat for Saribas, on the proposal to upgrade Jalan Kampung Buda dan Kampung Medang in first quarter of 12th Malaysia Plan, my Ministry took note on the request.

For the information of Ahli Yang Berhormat for Batu Danau, the Sarawak Government is planning to construct a 15km road from Limbang Bridge to Pendam and to Negara Brunei

Darussalam and not to construct the whole original alignment of the proposed Pan Borneo Highway Phase 2. Federal Projects under Kementerian Pembangunan Luar Bandar (KPLB)

Tuan Speaker, for the information of Ahli Yang Berhormat for Murum, the upgrading of ex-logging road to Ulu Jelalong, Tubau has been approved under the project entitled, “Menaik taraf bekas Jalan-Jalan Balak Fasa 4” in Rolling Plan 1 of the 11th MP. The appointment of consultant is in progress and the project is scheduled to be tendered by next year.

For the information of Ahli Yang Berhormat for Bukit Begunan, Projek Jalan Bukit Balau/Banting, Sri Aman is approved under Rolling Plan 2 of the 11th MP.

JKR Sarawak is waiting for approval from KPLB on the re-appointment of the consultant. While the proposed upgrading of Jalan Panti/Keranggas Engkeranji, Pantu has been put up to KPLB under Rolling Plan 4 (2020) for their consideration.

For the information of Ahli Yang Berhormat for Meluan, the construction of Jalan Nanga Maong/Klinik Nanga Maong/Sk Nanga Ju/Rumah Gerasi/Rumah Mengiring, Ulu Ju, has been approved under Rolling Plan 4 (2019) of the 11th MP. Value Management Lab (VML) is expected to be conducted soon.

While, the construction of Jalan Nanga Entabai/Rantau Limau Phase 2 has been submitted to KPLB under Rolling Plan 4 (2020) of the 11th MP for their consideration.

Road Maintenance

Tuan Speaker, for the information of Ahli-Ahli Yang Berhormat for Balingian and Simunjan, JKR Sarawak will investigate, study dan bid for MARRIS funding where applicable on the request of road repairs at Kampung Tutus Ulu, Mukah, Kampung Kuala Balingian, Skim Pembesaran Kampung Sungai Alo, Kampung Masjid, Kampung Lintang, Kampung Baru, Kampung Suyong, Kampung Tabuan Iban, Kampung Sageng, Kampung Segendu, Kampung Sg Ringkau and Kampung Simunjan Jaya.

For the information of Ahli Yang Berhormat for Bukit Semuja, JKR Sarawak will study your request on the proposed installation of speed breakers, signboard and zebra crossing at Air Manis Stabun, Kampung Kakai, Tangga Mawang, Jalan Baki Riih, Kampung Labak Tungan, Jalan Gedong, Kampung Remun, Kampung Lebor dan Kampung Kual.

Upper Rajang Development Authority (URDA)

For the information of Ahli Yang Berhormat for Ngemah, the remaining 14.5 km of Jalan Nanga Ngungun/Nanga Jagau project has been approved by the Kementerian Pembangunan Luar Bandar (KPLB) for its implementation by JKR Sarawak with a cost of RM50 million.

For the information of Ahli Yang Berhormat for Pelagus, the Sarawak Government is pursuing with the Federal Government for the funding to construct the road from Nanga Melakun, Tuli Kapit to Nanga Merit and further to Anap and Sangan, Bintulu.

The project cadangan pembinaan jalan seterusnya dari KM18.2 ke KM68 (Sungai Anap) has been submitted to Ministry of Finance (MOF) under Rolling Plan 4 (2020) for their consideration.

Meanwhile, the 22km stretch of road to Tunoh Administrative Centre has been tendered and will close on 26th May 2019.

Building Projects

For the information of Ahli-Ahli Yang Berhormat for Beting Maro, Kabong and Balingian on the proposed construction of Kompleks Pentadbiran Baru Daerah Pusa, request for additional fund for Dewan Masyarakat Kabong and proposal for the new Rumah Rehat Kerajaan Balingian, my Ministry recognizes the importance of all these requests and JKR Sarawak will study them, taking cognizance of their benefits to the Rakyat and financial implications to the Sarawak Government before implementation.

For the information of Ahli Yang Berhormat for Bukit Semuja, the Corporate Social Responsibility (CSR) programme undertaken by the Works Package Contractors (WPC) of the Pan Borneo Highway Sarawak to rebuild dilapidated schools identified by the Jabatan Pendidikan Sarawak (JPNS) has been implemented accordingly (1 school per WPC).

Bintulu Airport

Tuan Speaker, my ministry acknowledges the fuss to walk up and down the staircase for immigration clearance and luggage collection as raised by Ahli Yang Berhormat for Tanjong Batu. However Tuan Speaker, I wish to inform Ahli Yang Berhormat that this subject matter is under the purview of the Federal Government.

Encik Chiew Chiu SingDAP · PHTanjong Batu

Tuan Speaker, thank you very much. Honourable Minister, the Immigration Department partly is also under the State Government, isn’t it? Whether it is possible that either we move, you know an old airport on arrival from outside has no escalator or a lift going up to the building. How could it be an airport to be like that only staircase? Whether the State Government will build it first and then you contra with the Federal Government? …(Laughter)

Tan Sri Datuk Amar Dr James Jemut Anak MasingPRS · BNMinister of Infrastructure Development and Transport · Baleh

Tuan Speaker, that suggestion is good and I will consider that, we will talk because we have Member of Parliament over there…(Interruption)

Mr Speaker

Honourable Member for Tanjong Batu, Yang Amat Berhormat Prime Minister himself went to Bintulu to open the Sarawak branch for Pribumi. So, Bintulu is very important.

Tan Sri Datuk Amar Dr James Jemut Anak MasingPRS · BNMinister of Infrastructure Development and Transport · Baleh

Tuan Speaker, if we can work together, I’m sure a lot of thing can be done.

Puan Violet Yong Wui WuiDAP · PHPending

Thank you Tuan Speaker. Honourable Minister, would be there any more answer on PMC that you already have tell in beginning of the speech? I just want to clarify it first, before I ask you some clarification.

Tan Sri Datuk Amar Dr James Jemut Anak MasingPRS · BNMinister of Infrastructure Development and Transport · Baleh

Those are the answers, and there will be no more answers…(Interruption)

Puan Violet Yong Wui WuiDAP · PHPending

Thank you Honourable Minister. Thank you for giving the answer on PMC but I noticed that there are still certain issues which I raised that you did not touch on it. Maybe it is too sensitive but may I just bring it to your attention in particular, that how was the selection done and who’s decision in the State Government one was it to choose of first or whether there is any committee been set up for the appointment and the other one is why is there still a need for the allocation of RM10 million as travelling expenses for JKR Sarawak’s staff for the coastal road network project? This few questions I would like your goodself to give us and enlighten us, thank you.

Tan Sri Datuk Amar Dr James Jemut Anak MasingPRS · BNMinister of Infrastructure Development and Transport · Baleh

Thank you. Tuan Speaker, if I may. Thank you very much to Yang Berhormat bagi Pending, isn’t it? One is the selection of post is based on the understanding that it is 100% owned by MOF. That was the understanding that we have and JKR and SFS decided based on the issue. So, if it is 100 own by MOF then there is no problem in terms of who should get it. Second thing, 51% of all posts must be local people involved in it and that is good enough to ensure that Sarawak engineers are involved in it.

And second one, what was it just now?

Puan Violet Yong Wui WuiDAP · PHPending

On the RM10 million allocated to the JKR Sarawak‘s staff.

Tan Sri Datuk Amar Dr James Jemut Anak MasingPRS · BNMinister of Infrastructure Development and Transport · Baleh

RM10 million allocation is a capping. We need not used all the RM10 million after the project has been completed and within the period of …(Interruption)

Puan Violet Yong Wui WuiDAP · PHPending

This is for the whole project RM10 million?

Tan Sri Datuk Amar Dr James Jemut Anak MasingPRS · BNMinister of Infrastructure Development and Transport · Baleh

Yes, it is for the whole project.

Puan Violet Yong Wui WuiDAP · PHPending

Only for the coastal roads and second trunk?

Tan Sri Datuk Amar Dr James Jemut Anak MasingPRS · BNMinister of Infrastructure Development and Transport · Baleh

No, no, no, for the whole project. That is just a capping we don’t need to use the RM10 million.

Mr Speaker

Are you taking from Pelawan?

Tan Sri Datuk Amar Dr James Jemut Anak MasingPRS · BNMinister of Infrastructure Development and Transport · Baleh

Yes.

Thank you Tuan Speaker. Thank you Honourable Minister for giving me a chance to clarify on this Sibu Outer Ring. My proposal for the Sibu Outer Ring is only RM70 million. I think Honourable Member for Bawang Assan actually came of the news after my proposal and that he would submit something around RM130 million proposals, similar to mine, the road everything but you mentioned just now, it cost more than RM400 million. I am just asking whether the thing actually less than RM100 million. Can the State Government pick it out? Instead of everything rely on the Federal Government? Because we have so much, you know? We all talking about, I don’t know where you get the figure lah. Honourable Minister, who gave you that figure? My figure might be wrong but mine is RM70 million, Member of Bawang Assan, he went to the news and he has another proposal like mine RM130 million. Almost double but you are talking about RM400, RM500 million, I don’t know how. Something is wrong. If it so, it can be reduced I think RM70 million for the State Government with the budget RM11.9 billion, I think sap sap sui. Thank you Honourable Minister.

Tan Sri Datuk Amar Dr James Jemut Anak MasingPRS · BNMinister of Infrastructure Development and Transport · Baleh

Thank you. Tuan Speaker, there is something wrong here. I said the outer ring road in Sibu was RM300 million. That was the cost, but despite of that we give you another RM100 over million worth of projects for Jalan Yong Yut Ming or something like that in Sibu you know. This is part of our understanding of some of your request. If we cannot fulfil the ring road that you need at least some road coming in to help you out in this one. But the RM400 million I don’t know where you get the figure from but it’s not mine. No, no well he will try his best. If you can, if KKR can work with JKR and work out the cost instead of RM300 million and you can bring it down

to RM70 million, my officer will be very happy to talk with you on the issue. Of course if it is a decrease in price we will accept that for the same spec you know. Jangan tukar spec. Okay, thank you.

Public Bus Services

Tuan Speaker, may I continue. I now talk about public services. Tuan Speaker, for the information of Ahli Yang Berhormat for Bukit Semuja, my Ministry acknowledges the difficulties encountered by the rakyat due to the lack of public bus services especially in the rural area. However, I wish to inform Ahli Yang Berhormat that this subject matter is under the purview of the Federal Government. Nevertheless, we will discuss with them how best to solve the problem.

Conclusion

Tuan Speaker, we will continue? to work closely with the Federal Government as it is for the betterment of Sarawak. In accelerating the infrastructure development in Sarawak, I also call upon the Federal Government to fulfil its promises in providing sufficient allocation for high impact and Rakyat-centric projects. We hope that there will be no further review of “U-Turn” or “P-Turn” on funding for all approved projects as this would dampen our planning and implementation schedules. Tuan Speaker, Sarawak GPS Government, when promises are made, promises ought to be kept and GPS Government will keep that in mind.

Effective engagement across all levels of Government Agencies and Departments is pivotal. We should not rest on our laurels. As in any development context, there is always scope to do more and to move faster. Therefore, it is crucial that we keep up our momentum in implementing all the approved projects. What we all want is to keep moving from talk to action, and we will.

Therefore, I call upon Ahli-Ahli Yang Berhormat from all political affiliations to work together with one objective that is to develop Sarawak as aspired by the Rakyat. And I am very pleased that member of the opposite bench agrees with me that we should work together with one objective; to make sure the people in Sarawak benefit from what are we doing.

I would suggest to all Sarawak members of Parliament that for those projects under the Federal purview and funding to raise all these issues in Parliament. Please, don’t just talk in this Dewan alone but please talk when you go to Parliament and Federal Government. Whatever you say there, we will support you for the betterment of Sarawak.

Before I end my speech Tuan Speaker, I would like to remind this august House that Gabungan Parti Sarawak or GPS, is a coalition of four Sarawak based parties namely parti Pesaka Bumiputra (PBB), Parti Rakyat Sarawak (PRS), Sarawak United People’s Party (SUPP) and Progressive Democratic Party (PDP). Therefore, I agree with Ahli Yang Berhormat from Pelagus, Tuan Speaker while debating on TYT’s address in this august House on 6th May 2019, when he said, I quote “GPS is not only political coalition. It is an institution that protects Sarawak’s rights”, they, he said referring to PSB, Ahli Yang Berhormat Pelagus continued “they have no place in the honourable institution like GPS”. I didn’t say that.

Hence, we in GPS are unanimous, we stand together as one to fight against any outside political force, may I repeat this again, we in GPS are unanimous, we stand together as one to fight against any outside political forces. Please bear that in mind and who ever try to hinder us from protecting and defending our objectives, nor do we tolerate anybody or any political organisation which tries to destabilize GPS under whatever pretexts and excuses. You have touched one; you have touched all. That is our principle. GPS will put Sarawak and Sarawak first. Utamakan Sarawak. Please help me with this.

Last but not least, I would like to thank Tuan Speaker himself for having successfully conducted this Sitting. I would also like to record my appreciation to Ahli-Ahli Yang Berhormat for raising relevant

issues, while comments and suggestions could be used as a guide to further improve our service delivery as well as our method of implementation to make Sarawak a better place for everyone of us. I would also like to thank my MIDT team, JKR, SRB, Port Authorities, Federal Agencies under our watching brief and Sarawak Civil Servants and members of the media for their full co-operation and dedication throughout this Session.

To all my Muslim colleagues and friends, Selamat Berpuasa and Selamat Hari Raya Aidilfitri, and to my Dayak friends, Selamat Hari Gawai Dayak, Gayu Guru Gerai Nyamai, Lantang Senang Nguan Menua.

Tuan Speaker,

Zaman dulu mudah berdalih, Tutu perlakuan tiada yang sahih, Teknologi kini di hujung jari, Rakaman audio visual menjadi bukti.

Ingatlah wahai rakan Yang Berhormat, Menabur janji biarlah cermat, Agar tertunai cepat dan tepat, Cukuplah sudah membohongi Rakyat.

That applies to all of us, you know.

Mr Speaker

Ahli-Ahli Yang Berhormat, the sitting is now adjourned and the House shall resume its sitting tomorrow 9th May 2019 at 9.00 am.

(Mesyuarat ditangguhkan pada jam 4.53 petang)