Progress of Lift Upgrading Programme Ahead of 2014 Deadline
Parliament of Singapore · 17 February 2012
Official Report, 17 February 2012, Vol 88, Issue 14 · Open in the reader (summaries, search, filters)
Assoc Prof Dr Muhammad Faishal Ibrahim asked the Minister for National Development (a) if he will provide an update on the Lift Upgrading Programme (LUP); (b) what percentage of the eligible blocks have completed their LUP works; and (c) whether the Ministry is able to complete all LUP works by 2014.
Mr Khaw Boon Wan: We are on track to complete the Lift Upgrading Programme (LUP) by 2014. About 5,000 HDB blocks have been selected for the LUP. Polling has been completed for 94% of these blocks. LUP works have been completed for 65% of the blocks. The other LUP projects are in various stages of design development.
Page: 1233
Source: Singapore Parliament Official Report (Hansard) for 17 February 2012. Republished on SGParliament.