LINKING OF ANG MO KIO AVENUE 3 TO HOUGANG AVENUE 3
Parliament of Singapore · 14 March 1983 · 5th Parliament
Official Report, 14 March 1983, Vol 42, Issue 5 · Open in the reader (summaries, search, filters)
Mr Ng Kah Ting asked the Minister for National Development when Hougang Avenue 3 will be linked to Ang Mo Kio Avenue 3.
Mr Lee Yock Suan (for the Minister for National Development): Mr Speaker, Sir, Hougang Avenue 3 will be linked to Ang Mo Kio Avenue 3 by about the middle of 1984. The construction of the link, Hougang Avenue 2, is being carried out in two phases. Phase I is currently in progress and will be completed in March 1984. Work on Phase II, which is encumbered with squatters, is scheduled to commence in July 1983 and will be completed by June 1984.